FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/MP/RAIL/154962/2022   (ii). Name of Project for which Forest Land is required : Chhotaudepur to Dhar New Broad Gauge railway line project   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : construction of Chhotaudepur to Dhar New Broad Gauge railway line project was sanctioned by Railway board in year 2008-08. It will provide connectivity to toe tribal area of alirajpur & dhar district of M.P.   (iv). State : Madhya Pradesh   (v). Category of the Proposal : Railway   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 134726   (viii). Area of forest land proposed for diversion(in ha.): 244.039   (ix). Non-forest land required for this project(in ha.): 726.985   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : DY.CHIEF ENGINEER (CONSTRUCTION-I)   (ii). Address1 : AT/PO- PRATAPNAGAR   (iii). Address2 : NIL   (iv). State : Gujarat   (v). District : Vadodara   (vi). Pin : 390004   (vii). Landmark : RAILWAY COLONY PRATAPNAGAR VADODARA 390004   (viii). Email address : dycec1brc@gmail.com   (ix). Landline Telephone No. : 265-2641180   (x). Fax No. : 265-2630227   (xi). Mobile No. : 9724091250   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Central Government
A-3. Details of Person Making Application
  (i). First Name: DEVENDRA   (ii). Middle Name: MOHAN   (iii). Last Name: SINGH   (iv). Gender: Male   (v). Designation: DEPUTYCHIEFENGINEERII   (vi). Address 1: OFFICE OF DEPUTY CHIEF ENGINEER CONSTRUCTION-III   (vii). Address 2: RAILWAY COLONY PRATAPNAGAR VADODARA 390004   (viii). State: Gujarat   (ix). District: Vadodara   (x). Tehsil: Vadodara   (xi). Pin: 390004   (xii). Landmark: RAILWAY COLONY PRATAPNAGAR VADODARA 390004   (xiii). Email Address: dycec1brc@gmail.com   (xiv). Landline Telephone No.: 265-2641180   (xv). Fax No.: 02652630227   (xvi). Mobile No.: 9724091253   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dhar(T)237.385445.643
2.Alirajpur6.654281.342
Total244.039726.985
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dhar237.385445.643
1.Alirajpur6.654281.342
Total244.039726.985
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1KAKDWA08.073
2KARCHAT010.958
3JHAI011.176
4BAGOLI024.574
5BARAD021.12
6PARETHA00.192
7GHOR6.44524.12
8WAKI TANDA013.687
9KARANPURA05.664
10BARDAKHAS05.509
11TANDA08.47
12KORDA012.763
13DOBANI016.233
14CHUNPYA12.953101.518
15AMGHATA29.8869.233
16JAMLI50
17DHOLAHANUMAN37.66411.882
18LALGARH48.2637.275
19JAMNIYAPADA2.39718.149
20KARDHA20.5811.904
21BAWADIKHODRA18.362.475
22HATHIPAWA6.1140
23TANKJHIRI10.7410
24MAWAD29.8350
25BHURAKUND5.7510
26GUNGIDEVI2.5613.44
27GOLPURA0.8355.23
28MALGARH07.52
29JHIKNYABARDI07.769
30KALUKHEDI09.088
31JOLAKHYA08.594
32MACHHLAI09.435
33BIJALPUR04.886
34SULTANPURA011.099
35RANIPURA07.655
36AMBAPATDI01.918
37GANGANAGAR09.901
38TIRLA011.09
39GYANPURA013.285
40AMKHEDA01.557
41CHIKHLYA02.018
42MATLABPURA05.073
43ATHAR01.11
44CHAUGANWAT015.774
45KHANDALA038.263
46DUDALWAT020.666
47BALADMUNG012.833
48KHERWA09.041
49CHAMARBEGDA012.789
50KANDA017.624
51KASWA JOBAT07.453
52DEHADALA09.829
53DEGAON016.958
54BETWASA012.602
55KOSDUNA09.938
56JAYASINGHPUR011.868
57BALEDI0.28619.161
58DEKAKUND6.36813.624
59KOLIYABAYEDA027.446
60BEHEDIYA022.113
61CHULIYA03.36
Total 244.039 726.985
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1NEW BROAD GAUGE RAILWAY LINE244.039726.985
Total 244.039 726.985
C. Maps of forest land proposed to be diverted
Division 1. : Dhar(T)
  (i). Area of forest land proposed to be diverted(in ha.) : 237.385   (ii). Nature of the Project: Linear   (b). No. of Segments : Three
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.237.385    View File
2.0    View File
3.0    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Alirajpur
  (i). Area of forest land proposed to be diverted(in ha.) : 6.654   (ii). Nature of the Project: Linear   (b). No. of Segments : Two
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.6.654    View File
2.0    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 500   (iii). Temporary Employment(Number of person-days): 25000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1Reply letter dated 02-07-2022 enclosed.
2reply dated 1-2-2023
3management sheet sardarpur
4management sheet tanda
5IDMP SOI TOPO SHEET RANGE TANDA
6IDMP SOI TOPO SHEET RANGE SARDARPUR
7Project Sanction Letter.
8Response of Your office letter & Point wise Reply.
9Point no.-2 Comparative statement
10Point no.-6 NOC from DM-WRD-PWD Dhar
11Point no.-9 Administrative approval sanctioned
12FORWORDING LETTER 17-07-23
13Pervious letter No. BRC/W/115/17 (Forest)
14Pervious letter No. BRC/W/115/18 (Forest)
15Reply letter dated 20-12-2023
16Component Details in forest & Non forest land.
17Jamniya station Layout plan. Which is in Forest Area.
18FORWARDING LETTER BRC/W/115/21 (Forest) Dt.15.02.2024
19Cost Comperative
20Reply letter dated 14-03-2024 enclosed.
21Cost Benefit Ratio 14-3-2024
22Supp. Document for ATR