FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/MH/WATER/138892/2021
(ii). Name of Project for which Forest Land is required :
Diversion of Forest Land for replacement of old existing Drinking Water Pipeline in Daund Tehsil of Pune District
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The Maharashtra Jeevan Pradhikaran (MJP), an undertaking of Government of Maharashtra had constructed a Reservoir, in Gut. No. 51 of Village Mergalwadi, Tehsil Daund, Dist. Pune under Rural Water Supply Scheme, in 1970s. An underground pipeline, having length of 3112.5 m., was laid from a well const
(iv). State :
Maharashtra
(v). Category of the Proposal :
Drinking Water
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
353
(viii). Area of forest land proposed for diversion(in ha.):
0.105
(ix). Non-forest land required for this project(in ha.):
0.206
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
NAGAR PARISHAD, DAUND
(ii). Address1 :
Nagar Parishad Office, Town Hall, Dr. Babasaheb Ambedkar Chowk, Daund
(iii). Address2 :
Tal. Daund, Dist. Pune
(iv). State :
Maharashtra
(v). District :
Pune
(vi). Pin :
413801
(vii). Landmark :
Town Hall
(viii). Email address :
nir.rashinkar@gmail.com
(ix). Landline Telephone No. :
2771-262444
(x). Fax No. :
2771-262444
(xi). Mobile No. :
9763313669
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Nirmala
(ii). Middle Name:
NIL
(iii). Last Name:
Rashinkar
(iv). Gender:
Female
(v). Designation:
Chief Officer
(vi). Address 1:
Nagar Parishad Office, Town Hall, Dr. Babasaheb Ambedkar Chowk, Daund
(vii). Address 2:
Tal. Daund, Dist. Pune
(viii). State:
Maharashtra
(ix). District:
Pune
(x). Tehsil:
Daund
(xi). Pin:
413801
(xii). Landmark:
Town Hall
(xiii). Email Address:
nir.rashinkar@gmail.com
(xiv). Landline Telephone No.:
2771-262444
(xv). Fax No.:
02771262444
(xvi). Mobile No.:
9763313669
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Pune
0.105
0.206
Total
0.105
0.206
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Pune
0.105
0.206
Total
0.105
0.206
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Mergalwadi
0.07
0
2
Gopalwadi
0.035
0.111
3
Lingali
0
0.095
Total
0.105
0.206
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Underground Drinking Water Pipeline
0.105
0.206
Total
0.105
0.206
C.
Maps of forest land proposed to be diverted
Division 1. : Pune
(i). Area of forest land proposed to be diverted(in ha.) :
0.105
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.105
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Proposal is for replacing existing old drinking wa
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
1920
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Project involves diversion of Forest Land to the extent of less than 1.00 Ha. No tree felling is required. The project is underground. The CA is subject to provision under Para 2.6 (b) of Handbook of FCA (2019 edition). NPV is subject to exemption up to 50% of normal rate. The project is covered under General Approval issued by the Central Government.
2
ERA Undertaking
Print