FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/MH/ROAD/50280/2020
(ii). Name of Project for which Forest Land is required :
Diversion of 11.8639ha. area Reserved Forest, Protected Forest and Private Forest land for Rehabilitation and Up-gradation of two lane with paved shoulders Pune - Mulshi - Mangaon - Mhalsa -Dighi Por
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Diversion of 11.8639ha. area Reserved Forest, Protected Forest and Private Forest land for Rehabilitation and Up-gradation of two lane with paved shoulders Pune - Mulshi - Mangaon - Mhalsa -Dighi Port and Indapur (NH-66)-Tala - Mandad - Agardanda -Dighi Port (SH-96 & SH-92) [Section-II : Mangaon -M
(iv). State :
Maharashtra
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
45752
(viii). Area of forest land proposed for diversion(in ha.):
11.8639
(ix). Non-forest land required for this project(in ha.):
69.6579
(x). Total period for which the forest land is proposed to be diverted(in years):
NIL
A-2.
Details of User Agency
(i). Name :
MSRDC BANDRA MUMBAI
(ii). Address1 :
MSRDC, RGSL Project Office
(iii). Address2 :
Bandra (W), Mumbai
(iv). State :
Maharashtra
(v). District :
Mumbai (Suburban)
(vi). Pin :
400050
(vii). Landmark :
Near Leelawati Hospital
(viii). Email address :
sachinniphade11@gmail.com
(ix). Landline Telephone No. :
22-26517914
(x). Fax No. :
22-26417893
(xi). Mobile No. :
9987047659
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Sachin
(ii). Middle Name:
Narhari
(iii). Last Name:
Niphade
(iv). Gender:
Male
(v). Designation:
Engineer
(vi). Address 1:
Opp Bandra reclamation, Bus Depot, KC Marg, Bandra W,Mumbai.
(vii). Address 2:
NIL
(viii). State:
Maharashtra
(ix). District:
Mumbai (Suburban)
(x). Tehsil:
Kurla
(xi). Pin:
400050
(xii). Landmark:
NIL
(xiii). Email Address:
sachinniphademsrdc@gmail.com
(xiv). Landline Telephone No.:
22-26517914
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9881446456
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Roha
11.8639
69.6579
Total
11.8639
69.6579
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Raigad
11.8639
69.6579
Total
11.8639
69.6579
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Utekhol
0
0.0493
2
Khandad
0.0006
2.0217
3
Bamnoli tarfe Nijampur
0.1017
0.9618
4
Rile
0.1497
0.178
5
Nilgund
0.7531
1.5666
6
Morbe
0.0991
3.0571
7
Surle
0.903
0.4227
8
Borli tarfe Tale
0
3.7459
9
Naitne tarfe Tale
0
2.31
10
Dongroli
0
2.9283
11
Vihulekond Tarfe Tale
0
1.6115
12
Vihule Tarfe Tale
0
1.021
13
Sai
0.3894
4.9188
14
Usar Budruk
0
0.3616
15
Ranvde Kond
0
1.9575
16
Ghonse
1.4906
0.9082
17
Devghar
0.1126
1.0628
18
Sarvar
0.8295
0.7985
19
Chirgav
0.0735
0.4958
20
Savar
0.3026
0.7536
21
Mhasala
0.0752
5.0338
22
Saklap
0.3547
0.6921
23
Khargav Khurd
0.5447
0.3485
24
Tondsure
0
2.9242
25
Varvatne
0
1.563
26
Aagarwada
0.2062
1.3334
27
Revali
0
2.0121
28
Kharsai
0
5.3088
29
Mendadi Kond
0
1.1855
30
Mendadi
0.1638
4.1227
31
Khandoshi
0
0.1758
32
Kondghar
0
0.7729
33
Bhave
1.3796
0.272
34
Kharshet
0
0.7401
35
Vadwali
0.5322
3.4326
36
Mulvelas
0.2328
0.302
37
Velasaagar
0.7251
0.0624
38
Kudgaon
0.8969
0.8943
39
Karlas
0.116
1.0033
40
Dighi
0.1967
3.0298
41
Chandore
1.2346
3.3179
Total
11.8639
69.6579
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Rode widening
11.8639
69.6579
Total
11.8639
69.6579
C.
Maps of forest land proposed to be diverted
Division 1. : Roha
(i). Area of forest land proposed to be diverted(in ha.) :
11.8639
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
11.8639
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Rehabilitation & up gradation of Existing road int
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
6000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Linear or 'strip' plantation declared as protected forest along with road/rail/canal sides for widening or expansion of road/rail/canal
Additional information Details
Documents
S.No
Documents
Remarks
NIL