FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/MH/ROAD/34047/2018
(ii). Name of Project for which Forest Land is required :
Diversion of 383.8535 Ha. (Final area 385.6147 Ha.) of Forest land in favor of Maharashtra State Road Development Corporation Limited, Bandra (W) Mumbai for construction of Nagpur-Mumbai Expressway (Package-V) passing from Village Taranganpada, Igatpuri Taluka, Nashik District to Village Amane, Bhiwandi Taluka, Thane District of 78 km in the state
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The Nagpur Mumbai Expressway has been designated as Maharashtra Prosperity Corridor basically with the three objectives, viz. to cut down distance/travel time between Nagpur and Mumbai, bring prosperity to the area by an agro-economic sustainable development model and curb the migration from rural a
(iv). State :
Maharashtra
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
964266
(viii). Area of forest land proposed for diversion(in ha.):
383.8535
(ix). Non-forest land required for this project(in ha.):
526.3233
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
MAHARASHTRA STATE ROAD DEVELOPMENT CORPORATION
(ii). Address1 :
Maharashtra state road development corporation opposite Bandra Reclamation bus depot Bandra (W) Mumbai
(iii). Address2 :
NIL
(iv). State :
Maharashtra
(v). District :
Mumbai (Suburban)
(vi). Pin :
400050
(vii). Landmark :
NIL
(viii). Email address :
msrdcmumbaipune@gmail.com
(ix). Landline Telephone No. :
22-26558175
(x). Fax No. :
22-26417893
(xi). Mobile No. :
9870646761
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
M
(ii). Middle Name:
Chetan
(iii). Last Name:
Wani
(iv). Gender:
Male
(v). Designation:
Executive Engineer
(vi). Address 1:
Maharashtra State Road Development Corporation, Opposite Reclamation Bus Depot, Bandra (W), Mumbai
(vii). Address 2:
NIL
(viii). State:
Maharashtra
(ix). District:
Mumbai (Suburban)
(x). Tehsil:
Kurla
(xi). Pin:
400050
(xii). Landmark:
NIL
(xiii). Email Address:
msrdcmumbaipune@gmail.com
(xiv). Landline Telephone No.:
22-26558175
(xv). Fax No.:
022-26417893
(xvi). Mobile No.:
8805622726
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
West Nashik(Nashik)
39.177
74.3264
2.
Shahapur
317.8486
303.9425
3.
Thane
26.8279
148.0544
Total
383.8535
526.3233
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Nashik
39.177
74.3264
1.
Thane
344.6765
451.9969
Total
383.8535
526.3233
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Taranganpada
0
5.3459
2
Pimprisadroddin
0
19.1192
3
Waghyachiwadi
5.659
6.2681
4
Borli
20.887
4.3029
5
Fugale
23.325
0
6
Dhakane
15.162
0
7
Vashala Bk.
42.459
12.47
8
Vashala Kh.
3.7938
0
9
Kasara Bk.
33.704
15.51
10
Shirol
34.5243
6.0282
11
Golbhan
1.5794
19.8621
12
Khardi
3.0605
6.23
13
Dhamni
0
2.9393
14
Dalkhan
4.1252
26.6864
15
Chande
2.9213
5.0637
16
Ratandhale
0.264
15.242
17
Lahe
2.2239
23.8993
18
Birwadi
7.1276
46.5071
19
Khutadi
15.8074
8.3883
20
Saralambe
0.5003
7.48
21
Arjunali
0
0.6746
22
Kasgaon
19.0073
4.8965
23
Shelvali
9.7901
14.2899
24
Sapgaon
5.3996
5.5555
25
Khutghar
19.8634
7.619
26
Andad
16.141
4.342
27
Hiv
9.605
13.655
28
Ras
14.681
8.017
29
Shere
17.1805
11.6689
30
Shei
5.514
20.0052
31
Ambarje
4.903
16.9125
32
Hal
5.186
0
33
Ushid
5.767
14.1206
34
Utane
0
9.284
35
Pitambare Nagar
0
2.1396
36
Chinchavali
0
17.8382
37
Raye
0
0.2445
38
Danbav
0
0.0861
39
Guravali
0
9.7935
40
Nimbavali
0
16.9462
41
Chiradpada
0
14.2214
42
Pise
0
12.2659
43
Vashere
0
0.0108
44
Amane
0
10.554
45
Nandgaonsado
0
26.1767
46
Fangulgavhan
12.631
13.1136
47
Phalegaon
7.6967
25.2209
48
Nadgaon
13.3642
15.3287
Total
383.8535
526.3233
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road
383.8535
526.3233
Total
383.8535
526.3233
C.
Maps of forest land proposed to be diverted
Division 1. : Thane
(i). Area of forest land proposed to be diverted(in ha.) :
26.8279
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Ten
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
2.343
View File
2.
2.6995
View File
3.
3.1727
View File
4.
6.707
View File
5.
4.3457
View File
6.
0.0123
View File
7.
1.5367
No Data
8.
0.244
View File
9.
2.286
View File
10.
3.481
0
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : West Nashik(Nashik)
(i). Area of forest land proposed to be diverted(in ha.) :
39.177
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Four
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
12.631
View File
2.
5.659
View File
3.
3.422
View File
4.
17.465
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : Shahapur
(i). Area of forest land proposed to be diverted(in ha.) :
317.8486
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Ten
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
26.8279
View File
2.
68.5908
View File
3.
24.0076
View File
4.
22.935
View File
5.
21.3754
View File
6.
25.1827
View File
7.
28.2286
No Data
8.
17.4302
View File
9.
24.0013
View File
10.
11.553
0
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
6000
(iii). Temporary Employment(Number of person-days):
2828570
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
Yes
(a). Status of the Environmental Clearance to the Project:
EC under process
(ii). Environmental Clearance File No.:
10-3/2017-IA-III
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
No
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application under process
(a). Date of submission of proposals :
08 Oct 2016
(b). Current status :
NIL
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
Three
District 1. : Aurangabad
(a). Village:
Umravati
(b). Area(in ha.):
12.8535
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
495
(e). Present owner:
User Agency
(f). Copy of Ownership proof:
District 2. : Aurangabad
(a). Village:
Andhari
(b). Area(in ha.):
239
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
293, 476, 740, 512
(e). Present owner:
User Agency
(f). Copy of Ownership proof:
District 3. : Aurangabad
(a). Village:
Jatwa
(b). Area(in ha.):
132
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
95, 93, 65, 14, 192
(e). Present owner:
User Agency
(f). Copy of Ownership proof:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
CA Land Andhari Village Map
2
CA Land Jatwa Village Map
3
CA Land Umravati Village Map
4
CA Scheme
5
CA Suitability Certificate
Print