FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/MH/ROAD/141097/2021   (ii). Name of Project for which Forest Land is required : Forest diversion proposal for construction of 2 lane / 4 lane with paved shoulder under configuration from Pen-Khopoli (KM 00+000 to KM 33+328) section of NH-166 D (Pen-Khopoli) in the state of Maharastra   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed Project is starting from existing (KM 00+000 to KM 33+328). The approximate length of Project is 33.328 KM, It passes through one district of Maharashtra, Raigad The villages falling on the alignment are Ramraj, Dhavte, Ambeghar, Savarsai, Sapoli, Pimpalgaon, Mangrul, Kamarli, Gagod   (iv). State : Maharashtra   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 18305   (viii). Area of forest land proposed for diversion(in ha.): 9.9249   (ix). Non-forest land required for this project(in ha.): 49.7396   (x). Total period for which the forest land is proposed to be diverted(in years): NIL
A-2. Details of User Agency
  (i). Name : OFFICE OF EE, NH PEN DIVISION   (ii). Address1 : Office of EE, NH Pen division, Pen   (iii). Address2 : NIL   (iv). State : Maharashtra   (v). District : Raigad   (vi). Pin : 402107   (vii). Landmark : Near Private high school   (viii). Email address : sdenhthane@gmail.com   (ix). Landline Telephone No. : 21-43256860   (x). Fax No. : 21-   (xi). Mobile No. : 9975010907   (xii). Website (if any) : www.mahapwd.com   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Shrikant   (ii). Middle Name: Raghunath   (iii). Last Name: Bangar   (iv). Gender: Male   (v). Designation: Executive Engineer EE   (vi). Address 1: Office of EE, NH division Pen, Pen   (vii). Address 2: NIL   (viii). State: Maharashtra   (ix). District: Raigad   (x). Tehsil: Pen   (xi). Pin: 402107   (xii). Landmark: Near private high school   (xiii). Email Address: sdenhthane@gmail.com   (xiv). Landline Telephone No.: 21-43256860   (xv). Fax No.: NIL   (xvi). Mobile No.: 9975010907   (i). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: No Data
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Alibag9.924949.7396
Total9.924949.7396
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Raigad9.924949.7396
Total9.924949.7396
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Gorthan budruk01.7738
2aajivali ( jambivali )01.4182
3Holare00.4444
4Vanvate01.2544
5Apti01.845
6Donvat01.5638
7Tambati03.6338
8Vadval00
9Savroli00.765
10Dahivali tarfe Beorti02.2388
11Nifan01.0238
12Sarsan01.3725
13Takai1.39010.405
14Anjoshi0.03941.6875
15Sheel00.945
16Tarankhop01.023
17Ramraj00.87
18Dhawte0.3063.6815
19Ambeghar07.1126
20Sawarsai02.682
21Sapoli01.3613
22Pimpalgaon1.56090
23Mangrul01.7636
24Kamarli1.21954.5686
25Gagode khurd01.0181
26Gagode Budruk5.4090
27Karambeli01.3129
28Ransai03.3394
29Shirvali tarfe chhatishi00.6356
Total 9.9249 49.7396
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Area9.924949.7396
Total 9.9249 49.7396
C. Maps of forest land proposed to be diverted
Division 1. : Alibag
  (i). Area of forest land proposed to be diverted(in ha.) : 9.9249   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.9.9249    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: upgradation of previous road with minimum acquisit
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 30   (iii). Temporary Employment(Number of person-days): 20
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Central Govt. Project
Additional information Details
Documents
S.No Documents
Remarks
1Linear project under process
2Forest complance reply resubmission letter dated 26-07-2022
3Forest complance reply resubmission letter dated 09-11-2022
4Enclosed refference letter for change in total area by DCF alibag.
5Enclosed All village map scan copy of taluka PEN.
6Enclosed All village map scan copy of taluka Khalapur.
7Enclosed letter Submission 8 set Hard copy proposal to DCF alibag
8Forest complance reply resubmission letter dated 23-01-2023
9Forest complance reply resubmission letter dated 10-02-2023
10Forest compliance reply resubmission letter dated 06-05-2023
11Reply of EDS