FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/KA/TRANS/21198/2016
(ii). Name of Project for which Forest Land is required :
Construction 220/220KV MC line for shifting of existing 220KV B1, B2 & B3,B4 lines at proposed HAL land premises near Bidare Hallada kavalu village in Gubbi taluk Tumkur District
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Karnataka Power Transmission Corporation limited (KPTCL) one of the Govt. owned company in Transmission utility is Constructing the 220/220KV MC line for shifting of existing 220KV B1, B2 & B3,B4 lines at proposed HAL land premises near Bidare Hallada kavalu village in Gubbi taluk Tumkur District fo
(iv). State :
Karnataka
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
3645
(viii). Area of forest land proposed for diversion(in ha.):
9.437
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
30
A-2.
Details of User Agency
(i). Name :
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
(ii). Address1 :
office of the Executive Engineer, Major Works Division,KPTCL,
(iii). Address2 :
KOTHITHOP ROAD, TUMKUR
(iv). State :
Karnataka
(v). District :
Tumkur
(vi). Pin :
572102
(vii). Landmark :
NEAR SHIVAKUMAR SWAMIJI CIRCLE
(viii). Email address :
eeemwdtkr@yahoo.co.in
(ix). Landline Telephone No. :
816-2272905
(x). Fax No. :
816-2277995
(xi). Mobile No. :
9448365230
(xii). Website (if any) :
www.kptcl.com
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
LATHA
(ii). Middle Name:
NIL
(iii). Last Name:
B T
(iv). Gender:
Female
(v). Designation:
The Executive Engineer Ele.,
(vi). Address 1:
Major Works Division, KPTCL, Kothithop Road, Old ZP office building
(vii). Address 2:
Near Shivakumar Swamiji Circle, Tumkur
(viii). State:
Karnataka
(ix). District:
Tumkur
(x). Tehsil:
Tumkur
(xi). Pin:
572102
(xii). Landmark:
Near Shivakumar Swamiji Circle,
(xiii). Email Address:
eeemwdtkr@yahoo.co.in
(xiv). Landline Telephone No.:
816-2272905
(xv). Fax No.:
08162277995
(xvi). Mobile No.:
9448365230
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Tumkur
9.437
0
Total
9.437
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Tumkur
9.437
0
Total
9.437
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
MARASHETTIHALLI
9.437
0
Total
9.437
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
MARASHETTIHALLI
9.43699995
0
Total
9.43699995
0
C.
Maps of forest land proposed to be diverted
Division 1. : Tumkur
(i). Area of forest land proposed to be diverted(in ha.) :
9.437
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
9.437
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Due to railway Crossing which is passing about Apr
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
500
(iii). Temporary Employment(Number of person-days):
2000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Central Govt. Project
Additional information Details
Documents
S.No
Documents
Remarks
1
As PER YOUR LETTER TOPO SHEET, KML FILE, GEOGRAPHICAL, AND FORM-A HAVE BEEN UPLOADED AND KIND REFERENCE,AND NEED FULL APPROVAL.
2
Uploading undertakings and documents