FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/KA/TRANS/115396/2020   (ii). Name of Project for which Forest Land is required : Construction of 400 KV Quad D/C Transmission Line in forest lands of Kallumundkuru, Thenkamijaru Villages in Karkal Taluk of Udupi District, Ulipadi Village in Mangalore Taluk, Virakhamba, Vitlamudnuru Villages in Bantwal Taluk of Dakshina Kannada District for a length of 6.756 Km in favour of Udupi Kasargode Transmission Limited, New Delhi   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 31.079 ha of forest area for Construction of 400 KV Quad D/C Transmission Line in forest lands of Kallumundkuru, Thenkamijaru Villages in Karkal Taluk of Udupi District, Ulipadi Village in Mangalore Taluk, Virakhamba, Vitlamudnuru Villages in Bantwal Taluk of Dakshina Kannada District   (iv). State : Karnataka   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 20000   (viii). Area of forest land proposed for diversion(in ha.): 31.079   (ix). Non-forest land required for this project(in ha.): 282.889   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : UDUPI KASARGODE TRANSMISSION LIMITED   (ii). Address1 : F-1, Mira Corporate Suites, Mathura Road, Ishwar Nagar, New Delhi-110065   (iii). Address2 : NIL   (iv). State : Delhi   (v). District : South   (vi). Pin : 110065   (vii). Landmark : NIL   (viii). Email address : santosh.kumar@sterlite.com   (ix). Landline Telephone No. : 0-   (x). Fax No. : 0-   (xi). Mobile No. : 8260154039   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Santosh   (ii). Middle Name: NIL   (iii). Last Name: Kumar   (iv). Gender: Male   (v). Designation: Chief Manager   (vi). Address 1: House No. 13/131, Old No. 7/117, ITI Colony, Vidya Nagar, Kasaragod, Kerala-671123   (vii). Address 2: NIL   (viii). State: Kerala   (ix). District: Kasaragod   (x). Tehsil: Kasaragod   (xi). Pin: 671123   (xii). Landmark: NIL   (xiii). Email Address: santosh.kumar@sterlite.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 7908743457   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Mangalore22.111180.546
2.Kundapur8.968102.343
Total31.079282.889
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dakshina Kannada31.079255.361
1.Udupi027.528
Total31.079282.889
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Vitlamudnuru1.4675.431
2Vitla0.96124.298
3Veerakamba14.8997.777
4Ananthady1.2890.574
5Tenka Edapadhavu3.4957.944
6Tenka Mijaru5.17720.188
7Badagamijaru2.9854.205
8Kallamundkuru0.80614.826
9Punacha04.041
10Kepu024.268
11Balthila014.507
12Shambhuru07.642
13Narikombu013.732
14Bantwala013.363
15Punjikal012.522
16Arla016.963
17Kolavuru05.776
18Kilanjaru011.998
19Badaga Edapadhavu09.71
20Aikala00.323
21Ejinje016.51
22Ulipadi014.205
23Balkunje04.558
24Inna014.623
25Nandikure04.813
26Santuru02.414
27Elluru05.678
Total 31.079 282.889
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Transmission Line Corridor31.079282.889
2Sub-station (proposed in Kerala)00
Total 31.079 282.889
C. Maps of forest land proposed to be diverted
Division 1. : Kundapur
  (i). Area of forest land proposed to be diverted(in ha.) : 8.968   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.8.968    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Mangalore
  (i). Area of forest land proposed to be diverted(in ha.) : 22.111   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.22.111    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 60   (iii). Temporary Employment(Number of person-days): 1000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1LOI from REC Transmission Projects Company Ltd
2Section 68 from Ministry of Power
3Power of Attorney in the name of person making application
4Administrative and Technical Approval_Section 68 UKTL
5Compliance of the Queries Dated 01 Jan 2021
6Compliance of the Queries Dated 01 March 2021
7Coordinates of Angle Towers Located in Forest Area
8Detailed Note on Project Features
9Mail Communication with NIC
10Share Purchase Agreement UKTL
11Undertaking for Demarcation of Forest Area
12Statement on Mutation Details
13Area statement of the entire line from Karnataka to Kerala
14Area Statement of the Project in Karnataka
15DGPS Co-ordinates of the Forest Area under Kundapur Forest Division
16DGPS Co-ordinates of the Forest Area under Mangalore Forest Division
17Survey Number-wise DGPS Map Kundapur Division
18Survey Number-wise DGPS Map Mangalore Division
19Map II Forest Village Map Combined
20Map III Combined Village Maps of the Forest and Non-forest area
21SOI Map of the Entire Transmission Line
22Total Length of Project Alignment in Karnataka
23All Necessary Undertakings as required to submit with the forest diversion proposal
24DGPS & Tower Location Coordinates Convertible to Excel
25Segment-wise and Village wise Breakup of Forest and Non Forest Area
26Coordinates of Angle Towers Located in Forest Area
27Village wise Breakup of Forest and Non Forest Area
28Compliance of the query raised by the DCF on 29.06.2021
29Compliance of the query raised by the DCF Mangalore on 01.01.2022