FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/KA/ROAD/28960/2017
(ii). Name of Project for which Forest Land is required :
Strengthening and Widening of existing National Highway from Bellary (Km 253.600) to Hiriyur (Km 413.500) section of NH150A (Involving Forest land from Km 283.500 to Km 413.500).
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The Project Road starts near Bellary at existing Km 253.600 and ends at existing Km 413.500 near Hiriyur. The Total length of the project stretch is 159.900 km. The project involves Upgradation of existing road to Four lane divided carriageway from Bellary to Hiriyur including bypasses to major town
(iv). State :
Karnataka
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
137097.705
(viii). Area of forest land proposed for diversion(in ha.):
32.28
(ix). Non-forest land required for this project(in ha.):
488.83
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
NHAI PIU HOSPET
(ii). Address1 :
Shree Nilayam, 1st Main, 2nd Cross, Vivekananda Nagar, Hospet
(iii). Address2 :
NIL
(iv). State :
Karnataka
(v). District :
Bellary
(vi). Pin :
583201
(vii). Landmark :
NIL
(viii). Email address :
piuhospet@gmail.com
(ix). Landline Telephone No. :
8392-231565
(x). Fax No. :
8392-
(xi). Mobile No. :
9481353756
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central Government
A-3.
Details of Person Making Application
(i). First Name:
Suresh
(ii). Middle Name:
Raju
(iii). Last Name:
Vallabhaneni
(iv). Gender:
Male
(v). Designation:
General Manager (Tech)
(vi). Address 1:
Shree Nilayam, 1st Main, 2nd Cross, Vivekananda Nagar, Hospet
(vii). Address 2:
NIL
(viii). State:
Karnataka
(ix). District:
Vijayanagara
(x). Tehsil:
hosapete
(xi). Pin:
583201
(xii). Landmark:
NIL
(xiii). Email Address:
piuhospet@gmail.com
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
8369123961
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Approved
4-KRC918/2012-BAN/6308
FP/KA/ROAD/1300/2011
12.19
12.19
14 Feb 2013
08 Dec 2014
2
Inprinciple
FP/KA/ROAD/28960/2017
4-KRC1171/2018/BAN/1638
32.28
32.28
21 Feb 2019
3
Approved
4-KRC918/2012-BAN/6308
FP/KA/ROAD/1300/2011
12.19
12.19
14 Feb 2013
08 Dec 2014
Total
56.66
56.66
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Chitradurga
32.28
488.83
Total
32.28
488.83
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Chitradurga
32.28
488.83
Total
32.28
488.83
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Thammenahalli
0
5.5746
2
Somikery
0
6.2119
3
Rajapura
0
1.9425
4
Konapura
0
1.8716
5
Murudi
0
0.8802
6
Bammakkanahalli
0
5.7465
7
Obalapur
0
7.4609
8
Kerekondapura
0
2.6507
9
Ramapura
0
20.3453
10
Ramasagara
0
8.4983
11
Heruru
0
7.8004
12
Nagasamudra
0
4.8157
13
Amakundi
0
9.6112
14
Obalapura
0
4.502
15
Byrapura
0
3.9458
16
Rayapura
0
6.3636
17
Yerenahalli
0
5.2101
18
Manekota
0
29.5416
19
Kasaba Talaka
0
7.4866
20
Giriyammanahalli
0
10.5014
21
Buddanahatti
0
12.9296
22
Gorlahatti
0
1.032
23
Nagaramagery
0
10.3801
24
Lakshmipura
0
7.4866
25
Shiddapura
0
1.2342
26
Hotteppanahalli
0
7.8305
27
Kamatamarakunti
0
1.6896
28
Mummudisagara
0
6.4041
29
Sanikere Kavalu
0
15.398
30
Heggery
0
8.0025
31
Gollahalli
0
9.1662
32
Yaraballi
0
8.9434
33
Kalavibagi
0
0.081
34
Harti kote
0
8.529
35
Balenahalli
0
6.7481
36
Hemadala
0
2.4079
37
Myakalurahalli
0
6.6772
38
Babburu
0
27.1137
39
Kasaba Hiriyuru
0
23.0044
40
Somenahalli
0
15.1248
41
Hulagalakunte
0
2.0031
42
Katanayikanahalli
0
1.2104
43
Hirehalli
0
30.0835
44
Chikkammanahalli
0
10.0263
45
Devasamudra (Sy No: 32,33)
5.1933
1.4978
46
Gowrasamudra (Sy No: 69)
0.1291
7.8633
47
Guddadahalli (Sy No: 50)
0.8702
4.2099
48
Hanagallu (Sy No:30,55,88,102)
1.9728
16.8479
49
Adavimallapura (Sy No: 8,9)
2.2204
3.6061
50
Kamarada Kavalu (Sy No: 1)
13.3415
0
51
Thoomakoorlahalli (Tumatumakanahalli) (Sy No: 38)
2.1575
0
52
Bammagondanakery (Sy No: 23,24)
5.632
23.785
53
Obandanahalli Kavalu (Sy No: 88)
0.0698
8.97305
54
Kasaba Challakere(Sy No: 271,272,273)
0.6934
47.57
Total
32.28
488.82015
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Main Carraigeway
9.921
88.402
2
Service Road
0.5648
67.1402
3
Drain
3.5405
65.7675
4
Utility Corridor
2.3253
49.5787
5
Future Widening
15.9281
217.941
Total
32.2797
488.8294
C.
Maps of forest land proposed to be diverted
Division 1. : Chitradurga
(i). Area of forest land proposed to be diverted(in ha.) :
32.28
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
32.28
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Following Existing Alignment to the maximum extent
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
600
(iii). Temporary Employment(Number of person-days):
200000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
ProjectApprovalLetters-GazetteNotification
2
ProjectApprovalLetters-NHAI Handover Letters
3
NH-150A Executive Summary
4
Undertaking for Minimum Use of Forest Land
5
Undertaking for payment of NPV of Forest Land
6
Undertaking for payment of cost of compensatory afforestation
7
Compliance letter
8
EDS Compliance Letter
9
NH-150A Details of Forest and Non-Forest Land.
10
EDS Compliance Letter
11
Gudekote Sloth Bear Sanctuary ESZ Boundary along the Project Road
12
Justification for Non- Identification of Forest Land
13
Undertaking for Payment of Compensatory Afforestation Cost
14
Undertaking for Submission of FRA Certificate
15
EDS Compliance Letter
16
Compliance_to_REC_Comments
17
Hirehalli_Village_R&R
Print