FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/KA/Pipeline/47297/2020   (ii). Name of Project for which Forest Land is required : Laying of proposed 203mm,152mm,101mm diameter steel Gas pipeline, from Reliance Gas Transportation Infrastructure Limited terminal CS-05 at Jalsingi,along NH-50, within road RoW, to Bidar with forest diversion in Village Kabeerabad, Byalahalli and Andur of Tulaka Bidar of Bidar District in favour of Bharat Gas Resources Limited.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for Grant of permission for laying of proposed 203mm,152mm,101mm diameter steel Gas pipeline, from Reliance Gas Transportation Infrastructure Limited terminal CS-05 at Jalsingi,along NH-50, within road RoW, to Bidar in Bidar District.   (iv). State : Karnataka   (v). Category of the Proposal : Pipeline   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 9673   (viii). Area of forest land proposed for diversion(in ha.): 0.5712   (ix). Non-forest land required for this project(in ha.): 3.5222   (x). Total period for which the forest land is proposed to be diverted(in years): 100
A-2. Details of User Agency
  (i). Name : BHARAT GAS RESOURCES LIMITED   (ii). Address1 : 5th Floor , The IL & FS Financial Centre, Plot C-22, G Block , Bandra Kurla Complex( E) , Mumbai   (iii). Address2 : NIL   (iv). State : Maharashtra   (v). District : Mumbai City   (vi). Pin : 400051   (vii). Landmark : NIL   (viii). Email address : josephs@bharatpetroleum.in   (ix). Landline Telephone No. : 22-26381621   (x). Fax No. : 22-   (xi). Mobile No. : 9099069167   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Central PSU
A-3. Details of Person Making Application
  (i). First Name: Sajeev   (ii). Middle Name: NIL   (iii). Last Name: K   (iv). Gender: Male   (v). Designation: CGD Head   (vi). Address 1: Bharat Gas Resources Limited, Brindavan Commercial Complex, CMC no 19-1-207/30 and 31, 2nd Floor, Shiv Nagar South, Udgir main Road, Bidar, Karnataka-585401   (vii). Address 2: NIL   (viii). State: Karnataka   (ix). District: Bidar   (x). Tehsil: Bidar   (xi). Pin: 585401   (xii). Landmark: Above Andhra Bank   (xiii). Email Address: sajeevka@bharatpetroleum.in   (xiv). Landline Telephone No.: 22-26381621   (xv). Fax No.: NIL   (xvi). Mobile No.: 9606690008   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bidar0.57123.5222
Total0.57123.5222
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bidar0.57123.5222
Total0.57123.5222
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1JALSINGI CGS (STARTING STATION)00.4046
2JALSINGI00.3156
3CHINCHOLI00.0382
4KABEERABAD(NON FOREST)00.1799
5KABEERABAD FOREST (XX)0.21370
6KABEERABAD FOREST (81)0.01970
7HALLIKHED00.5299
8AMIRABAD00.0882
9SINDABANDAGI00.1617
10TUGANVACH00.1615
11BYALAHALLI (NON FOREST)00.3144
12BYALAHALLI FOREST(58/1)0.08590
13HALAHALLI00.1905
14NIRMANAHALLI00.0815
15MALACHAPURA00.0974
16ANDUR NON FOREST00.2218
17ANDUR FOREST (328)0.25190
18ANDUR FOREST (329)0.03080
19KOLARA BUZURG00.1336
20NIJAMPURA00.0785
21KOLARA KHURD00.3101
22NAUBADHA00.1773
23NAUBADHA DELIVERY STATION00.0067
Total 0.602 3.4914
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1STARTING POINT CGS LAND JALSINGI00.4046
2STEEL GAS PIPELINE0.6023.0801
3DELIVERY STATION AT BPCL NAUBADHA00.0067
Total 0.602 3.4914
C. Maps of forest land proposed to be diverted
Division 1. : Bidar
  (i). Area of forest land proposed to be diverted(in ha.) : 0.602   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.602    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: Proposed route is along NH-50 and within road RoW
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 10   (iii). Temporary Employment(Number of person-days): 150
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1Administrative Sanction/approval
2Detailed Project Report
3Consent from Highway Authority
4Clarification on points in the query document
5Undertaking for making physical markings
6Undertaking for NPV,CA and other stipulated charges
7Clarification regarding FRA Certificate
8AUTO CAD DRAWING OF ALL VILLAGE SURVEY NUMBER ALONG THE PIPELINE
9DETAIL NOTE
10DETAILS OF FOREST AND NON FOREST SURVEY NO WISE BREAKUP
11DETAILS OF FOREST LAND SURVEY NO WISE ,VILLAGEWISE BREAKUP
12DETAILS OF NON FOREST LAND SURVEY NO WISE ,VILLAGEWISE BREAKUP
13GPS READINGS OF POINT ALONG PIPELINE ROUTE IN FOREST AREA
14RTC RECORDS OF FOREST LAND IN ALL VILLAGES
15GEO REFERENCE MAPS WITH LARGE SCALE (1:4000)
16GEO REFERENCE MAPS WITH ORDINARY SCALE (1:7920)
17SINGLE MAP SHOWING THE ENTIRE PIPELINE ROUTE WITH FOREST AND NON FOREST SEGMENTS