FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/KA/IND/26447/2017
(ii). Name of Project for which Forest Land is required :
BALDOTA STEEL AND POWER LIMITED
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
BALDOTA STEEL AND POWER LIMITED (earlier project name Aaress Iron & Steel Limited) is setting up an Integrated Steel Plant (Special Alloy) of 1.0 MTPA capacity and MSPL LIMITED has set up a 1.2 MTPA capacity Pellet Plant at Halavarthi Village Koppal Taluk, District, Karnataka. The project has been
(iv). State :
Karnataka
(v). Category of the Proposal :
Industry
(vi). Shape of forest land proposed to be diverted :
Hybrid
(vii). Estimated cost of the Project(Rupees in lacs) :
230000
(viii). Area of forest land proposed for diversion(in ha.):
1.745
(ix). Non-forest land required for this project(in ha.):
4.869
(x). Total period for which the forest land is proposed to be diverted(in years):
50
A-2.
Details of User Agency
(i). Name :
AARESS IRON AND STEEL LIMITED
(ii). Address1 :
BALDOTA ENCLAVE, ABHERAJ H BALDOTA ROAD, HOSAPETE
(iii). Address2 :
NIL
(iv). State :
Karnataka
(v). District :
Bellary
(vi). Pin :
583203
(vii). Landmark :
Near Sai Baba Temple
(viii). Email address :
natesh@mspllimited.com
(ix). Landline Telephone No. :
8394-232005
(x). Fax No. :
8394-232444
(xi). Mobile No. :
9900256714
(xii). Website (if any) :
www.baldota.co.in
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
NATESH
(ii). Middle Name:
NIL
(iii). Last Name:
HOLLA
(iv). Gender:
Male
(v). Designation:
ManagerCorporateCommunication
(vi). Address 1:
BALDOTA ENCLAVE, ABHERAJ H BALDOTA ROAD, HOSAPETE
(vii). Address 2:
NIL
(viii). State:
Karnataka
(ix). District:
Bellary
(x). Tehsil:
Hospet
(xi). Pin:
583203
(xii). Landmark:
Near Sai Baba Temple
(xiii). Email Address:
natesh@mspllimited.com
(xiv). Landline Telephone No.:
8394-232005
(xv). Fax No.:
08394232444
(xvi). Mobile No.:
9900256714
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Koppal
1.745
4.869
Total
1.745
4.869
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Koppal
1.745
4.869
Total
1.745
4.869
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Chikkakasinkandi SY No 25
0.126
0.314
2
Hirekasinakandi Sy No. 33,34,35,37,41,40,38,18,17,
0
1.136
3
Hirebaganal Sy No. 64,63,57,58,59,45,44,43,42,20,1
0
1.096
4
Halawarthi Sy.No 55,56,57,48,58,59,47,46,44,42,43,
0
0.848
5
Basapura Sy.No 128,142,121,143
0
0.475
6
Holemudlapura
1.619
0
7
Lingapura submerged
0
1
Total
1.745
4.869
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Pipe line
0.702
4.869
2
Sub station
0.05
0
3
Transmission Line
0.9
0
4
Jack well cum Pump House
0.093
0
Total
1.745
4.869
C.
Maps of forest land proposed to be diverted
Division 1. : Koppal
(i). Area of forest land proposed to be diverted(in ha.) :
1.745
(ii). Nature of the Project:
Hybrid
(a). No. of patches :
Two
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
0.05
View File
2.
0.093
View File
(b). No. of Segments :
Two
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.702
View File
2.
0.9
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
No
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Vijayanagara
(a). Village:
Chattnihalli
(b). Area(in ha.):
1.84
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
131 BP1
(e). Present owner:
User Agency
(f). Copy of Ownership proof:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
FRA Certificate
2
Water draw permission from GOK
3
Undertakings of NPV and CA for AISL water pipe line
4
Justification for Transimision line power of AISL water pipe line
5
AISL Water Pipeline Replay letter with annexures
6
AISL endosment letter from ADLR koppal
7
AISL power Approva frm KPTCL
8
CND Land Suitable certificate
9
KAnnada translate documents for AISL water Pepeline
10
power requirement under taking
11
Shortcommings 091017 replay letter
12
AISL Justfication forest land
13
Clarification_transmission_line
14
Reply_Nodal_officer_200318
15
AISL CND Land DC Revised Order
16
AISL Endosment letter from KADA & ADLR Revnew dept
17
GOK Order dated 221205and 231206
18
Kannada Translate of KAda and ADlr and Forest dept
19
Reply letter short comings 160418
20
COMPONENTWISE_DETAILS_161018 - ANNEXURE - 1
21
C AND D LAND OWNERSHIP DC APPROVAL_REVISED LTR
22
TOTAL STATION MAP
23
VILLAGE MAP 161018
24
TRANSMISSION LINE _161018
25
GEO REFERENCE MAP - 161018
26
RELATIONSHIP BETWEEN_AISL & MSPL& MOU.PDF
27
AISL Pipeline NOC ackledgments by 3 User agencies
28
AISL Replay Letter for shortcomming 25-05-18
29
AISL replay Letter to DCF Koppal for CA land details
30
CA Land Suitability Certificate from DCF Davanagere as per corrospondance from Koppal DCF
31
MSPL Covering letter on 09.04.2021
32
AISL Reply letter dated 20.06.2022 in regards Moef EDS
33
AISL WATER DRAWING PERMISSION FROM GOK DATED 04.02.2020
34
CA SCHEME 10 YEARS AS PER FC GUIDELINES FROM DCF DAVANGERE
35
TOPO & GOOGLE MAP OF OPTION -II ALTERNATIVE
36
VILLAGE MAP OF OPTION -II ALTERNATIVE
37
TOPO & GOOGLE OF OPTION -III ALTERNATIVE
38
TOPO & GOOGLE OF OPTION -I ALTERNATIVE
39
MSPL letter to PCCF regarding area change Request in Online portal.
40
Justification for the project 1.84Ha to 1.745 Ha
41
AISL FRA COMPLIANCES TRANSLATED TO FROM KANNADA TO ENGLISH
42
UNDERTAKING FOR NPV AND CA OF 1.745 Ha
43
GOOGLE MAP OF 1.745 Ha
44
GPS READINGS IN CONVERTTIBLE FORM SHOWN IN MAPS
45
Lingapura village map not available endosment
46
COMPONENT WISE , VILLAGEWISE, SURVEY NUMBER WISE AREA DETAILS FOR 1.745 Ha
47
Inlet to tank model
48
COMPONENTWISE GPS READINGS
49
AISL submitted documents with replay Letter for EDS dated 23.01.23.
50
AISL Authorisation letter of Mr. Meda Venkataiah, Executive Director
51
CA LAND GOOGLE MAP
52
AISL EDS REPLY LETTER - 25.09.2023
53
AISL EDS replay to DCF koppal with documents dt_03_02_24
54
NOC letter form Kirloskar ferrous ind ltd and Karnataka Water urban water supply documents
55
BSPL EDS REPLY LTR TO DCF KOPPAL REGARDS OF MOEF EDS-20.08.2024
56
KPTCL NOC FOR 33KV SUB STATION
57
MOEF EC PERMISSION FOR PROJECT NAME CHANGE AISL TO BSPL
58
BSPL Eds replay letter to DCF Koppal on 190824
Print