FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/JK/ROAD/43956/2020
(ii). Name of Project for which Forest Land is required :
Up-gradation of Reasi-Arnas-Mahore road to NHDL specifications from km 57.00 to km 68.00 in 31 BRTF area under project Sampark in J&K UT
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Up-gradation of Reasi-Arnas-Mahore road to NHDL specifications from km 57.00 to km 68.00 in 31 BRTF area under project Sampark in J&K UT
(iv). State :
Jammu and Kashmir
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
9083.62
(viii). Area of forest land proposed for diversion(in ha.):
3.22
(ix). Non-forest land required for this project(in ha.):
1.13
(x). Total period for which the forest land is proposed to be diverted(in years):
100
A-2.
Details of User Agency
(i). Name :
BRO, 110 RCC
(ii). Address1 :
110 RCC (GREF)
(iii). Address2 :
C/O 56 APO
(iv). State :
Jammu and Kashmir
(v). District :
Rajouri
(vi). Pin :
930110
(vii). Landmark :
NIL
(viii). Email address :
bro-110rcc@nic.in
(ix). Landline Telephone No. :
1962-262205
(x). Fax No. :
1962-
(xi). Mobile No. :
6005600662
(xii). Website (if any) :
bro.gov.in
(xiii). Legal status of User Agency :
Central Government
A-3.
Details of Person Making Application
(i). First Name:
SANDEEP
(ii). Middle Name:
KUMAR
(iii). Last Name:
RAI
(iv). Gender:
Male
(v). Designation:
LAND ACQUISITION SURVEYOR
(vi). Address 1:
F 33/3 OKHLA INDUSTRIAL AREA PHASE 2
(vii). Address 2:
NIL
(viii). State:
Delhi
(ix). District:
South
(x). Tehsil:
Kalkaji
(xi). Pin:
110020
(xii). Landmark:
NIL
(xiii). Email Address:
sandeep.rai@almondz.com
(xiv). Landline Telephone No.:
11-43500700
(xv). Fax No.:
NIL
(xvi). Mobile No.:
7080964970
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Mahore Forest Division
3.22
1.13
Total
3.22
1.13
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Reasi
3.22
1.13
Total
3.22
1.13
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
MAHORE
3.22
1.13
Total
3.22
1.13
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road widening
1
0.8
2
Curve Improvement
0.57
0.31
3
Muck Dumping point1
0.375
0
4
Muck Dumping point 2
0.3
0
5
Muck Dumping point 3
0.3
0
6
Muck Dumping point 4
0.375
0
7
Muck Dumping point 5
0.3
0
Total
3.22
1.11
C.
Maps of forest land proposed to be diverted
Division 1. : Mahore Forest Division
(i). Area of forest land proposed to be diverted(in ha.) :
3.22
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Two
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
1.57
View File
2.
1.65
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Very steep terrain so no alternate alignment
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
200
(iii). Temporary Employment(Number of person-days):
730
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Project Description
2
COST Bearing BRO
3
Approval of Project by competent Authority
4
Muck Dumping Plan
5
Justification letter for Muck dumping area more than road widening
6
LA Plan and Forest Location along with Proposed road widening
7
Muck quantity calculation and engineering measures taken
8
Muck disposal Plan with Engineering measures
9
Undertaking for soil stablization
10
Previous FC
11
layout
Print