FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/JK/Others/142143/2021
(ii). Name of Project for which Forest Land is required :
Temporary Establishment of Crusher Plant for construction of Khellani Tunnel Project
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Temporary Establishment of Crusher Plant for construction of Uni-Directional Khellani Tunnel of length 1.574 Km & its approach Road from Km 29.030 to Km 31.449 of total length of 2.419 Km on NH-244 in Union Territory of Jammu & Kashmir on EPC Mode.
(iv). State :
Jammu and Kashmir
(v). Category of the Proposal :
Others
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
43128
(viii). Area of forest land proposed for diversion(in ha.):
0.3533
(ix). Non-forest land required for this project(in ha.):
0.1113
(x). Total period for which the forest land is proposed to be diverted(in years):
2.5
A-2.
Details of User Agency
(i). Name :
APCO INFRATECH PVT LTD
(ii). Address1 :
Village: Jangalwar, Panchyat: Paryote, Post: Malindal
(iii). Address2 :
Block: Khellani, District: Doda
(iv). State :
Jammu and Kashmir
(v). District :
Doda
(vi). Pin :
182201
(vii). Landmark :
NIL
(viii). Email address :
planning.ktp@apcoinfra.com
(ix). Landline Telephone No. :
0-
(x). Fax No. :
0-
(xi). Mobile No. :
7830020910
(xii). Website (if any) :
www.apcoinfra.com
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
Prakash
(ii). Middle Name:
Singh
(iii). Last Name:
Sodhi
(iv). Gender:
Male
(v). Designation:
Senior Manager
(vi). Address 1:
Village: Jangalwar, Panchyat: Paryote, Post: Malindal
(vii). Address 2:
Block Khellani, District Doda
(viii). State:
Jammu and Kashmir
(ix). District:
Doda
(x). Tehsil:
Doda
(xi). Pin:
182201
(xii). Landmark:
NIL
(xiii). Email Address:
pssodhi@apcoinfra.com
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
7477795272
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bhaderwah Forest Division
0.3533
0.1113
Total
0.3533
0.1113
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Doda
0.3533
0.1113
Total
0.3533
0.1113
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Jangalwar pariyote
0.3533
0.1113
Total
0.3533
0.1113
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Plant-02
0.0284
0
2
Plant-01
0.3249
0.1113
Total
0.3533
0.1113
C.
Maps of forest land proposed to be diverted
Division 1. : Bhaderwah Forest Division
(i). Area of forest land proposed to be diverted(in ha.) :
0.3533
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
Two
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
0.0284
View File
2.
0.3249
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
12000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
DPR Vol - I - Main Report
2
DPR Vol - II - Design Basis Report (Structure)
3
DPR Vol - II - Design Report (Roads)
4
DPR Vol - II - Design Report (Structure)
5
DPR Vol - II - Design Report (Tunnel)
6
DPR Vol - III - Material Report
7
DPR Vol - IV - EIA & RAP
8
DPR Vol - V - Technical Specifications
9
Layout Map for the proposed forest land.
10
25 Certificate of Minimum use of Forest Land
11
27 Statement Showing Detail of Non-Forest Area Involved in Proposal
12
28 Undertaking For Payment of Cost of Compensatory Afforestation
13
29 Undertaking For Payment of Net Present value (NPV) of Forest Land:
14
30 Undertaking For Payment of Additional Net Present value (NPV) of Forest Land
15
35 Muck Disposal Plan
16
NHIDCL LOA 08-02-2021
17
Receive from DC 12-05-2021
18
Receive from DFO 15-05-2021
19
Joint Inspection Report from UA.
20
02 The Status of the land coming in the alignment of khellani tunnel (No forest Land)
21
04 Approval of the project by the competent Authority of the UA (Sanction letter)
22
Submission of Confirmation of non Availability of suitable non forest land for Crusher establishment
23
Multiple polygon in single KML is not accepted by PARIVESH PORTAL, Hence Individual KML of each polygon is uploaded.
24
01 APCO-191 Reply to CCF against Quarry
25
02 The Status of the land coming in the alignment of khellani tunnel (No forest Land)
26
07 Land Agreement (Muck staking)
27
09 DGPS & TOPO Map Signed
28
09 Layout Plan Signed
29
03 Undertaking for Returning of Forest Land