FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/TRANS/51259/2020   (ii). Name of Project for which Forest Land is required : 132 kV D/C Saria-Bishnugarh Transmission Line under NIT - 307   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : JUSNL (Jharkhand Urja Sancharan Nigam Limited) is primarily entrusted for the construction and successful operation of High Voltage Transmission line with a mission to from Grid Network to facilitate effective transfer of power within the state. The scheme is for construction of 132 KV D/C Saria-Bis   (iv). State : Jharkhand   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 421.98   (viii). Area of forest land proposed for diversion(in ha.): 56.988   (ix). Non-forest land required for this project(in ha.): 32.4844   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : JHARKHAND URJA SANCHARAN NIGAM LIMITED   (ii). Address1 : Jharkhand Urja Sancharan Nigam Limited, Transmission Zone-V, Hazaribagh, Jharkhand   (iii). Address2 : NIL   (iv). State : Jharkhand   (v). District : Hazaribag   (vi). Pin : 825301   (vii). Landmark : near Devangana chouk   (viii). Email address : eeetdhzb@gmail.com   (ix). Landline Telephone No. : 9431-707306   (x). Fax No. : 9431-   (xi). Mobile No. : 9534162127   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Gaurav   (ii). Middle Name: Kumar   (iii). Last Name: Singh   (iv). Gender: Male   (v). Designation: Senior Manager, Transmission D   (vi). Address 1: Jharkhand Urja Sancharan Nigam Limited, 1st Floor,Shringari Complex, Canary Hill Road, Hazaribagh, Jharkhand   (vii). Address 2: NIL   (viii). State: Jharkhand   (ix). District: Hazaribag   (x). Tehsil: NIL   (xi). Pin: 825301   (xii). Landmark: near montfort school   (xiii). Email Address: eeetdhzb@gmail.com   (xiv). Landline Telephone No.: 651-2400123   (xv). Fax No.: 06512400123   (xvi). Mobile No.: 8092901147   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/JH/SubStation/35726/2018Vanbhoomi-19/2019-2105 Va Pa4.044.0413 Jun 2019
Total 4.04 4.04
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Hazaribagh East56.98832.4844
Total56.98832.4844
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Hazaribag33.82916.9674
1.Giridih23.15915.517
Total56.98832.4844
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Nawadih, Bishnugarh, Hazaribag0.5270.9248
2Bhutahi Murgaon, Bishnugarh, Hazaribag0.6852.0498
3Upraili Murgaon, Bishnugarh, Hazaribag00.7187
4Hethili Murgaon, Bishnugarh, Hazaribag3.6221.8487
5Jamua, Bishnugarh, Hazaribag1.1122.0534
6Kusumbha, Bishnugarh, Hazaribag1.7370.3209
7Babudih, Bishnugarh, Hazaribag3.2060.212
8Nawada, Bishnugarh, Hazaribag0.3180.028
9Charnakhia, Bishnugarh, Hazaribag1.4040
10Nirghuna, Bishnugarh, Hazaribag2.6410.22
11Bakaspura, Bishnugarh, Hazaribag4.0070.5999
12Dandia, Bishnugarh, Hazaribag3.3130
13Mayapur, Bishnugarh, Hazaribag1.092.3568
14Simaria, Bishnugarh, Hazaribag1.3160.246
15Gundro, Bishnugarh, Hazaribag2.8413.273
16Barai, Bishnugarh, Hazaribag6.012.1154
17Bagodar, Bagodar, Giridih4.1996.0092
18Ghaghara, Bagodar, Giridih0.0720.3069
19Ambadih, Bagodar, Giridih2.8051.8811
20Dondlo, Bagodar, Giridih3.1290.8916
21Parria, Bagodar, Giridih0.8880
22Dhibra, Bagodar, Giridih0.41.7319
23Karamba, Bagodar, Giridih1.9531.4047
24Deoradih, Bagodar, Giridih1.0030.9899
25Barki Saria, Saria, Giridih6.730.762
26Mandramo, Saria, Giridih1.981.5397
Total 56.988 32.4844
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower5.2382.646
2Conductor laying within ROW51.7529.8384
Total 56.988 32.4844
C. Maps of forest land proposed to be diverted
Division 1. : Hazaribagh East
  (i). Area of forest land proposed to be diverted(in ha.) : 56.988   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.56.988    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 5   (iii). Temporary Employment(Number of person-days): 70000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Cost Benefit Analysis
2justification of the project in forest land
3Plan and elevation drawing of Saria to Bishnugarh TL
4Project approval letter of State Govt
5Undertaking for minimum use of forest land
6Undertaking for payment of compensatory afforrestation
7Undertaking for Payment of NPV
8Undertaking for state and central govt condition
9All Geo reference maps for Bishnugarh, Bagodar and Saria Block
103. Saria Plot verification report
111. Bishnugarh Plot verification report
122. Bagodar plot verification report
134. Undertaking of JJ Land NOC & FRA
14Abstract of Forest, JJ and Non-Forest land
15Brief Notes from Project
16Component wise Breakup
17Forest division wise statement of forest land and non forest land involved for the project
18Form-1 FRA Bishnugarh Block- Hazaribag District
19Form-1 FRA Bagodar & Saria Block- Giridih District
20NOC JJ land Bishnugarh Block- Hazariabag District
21FRA, PRECEEDING & GRAM SABHA
22Justification of project locating in forest area
23Length of Forest & JJ land involved
24purpose wise breakup of land required
25Statement of forest area (notified & Demarcated) and jj land involved under forest division Hazaribag East
26Tree Enumeration list & Summary.
27Undertaking for the submission of SSWCP & SMCP Plan
28Undertaking regarding additional NPV
29Undertaking regarding ECO Sensitive Zone & protected area.
30Undertaking regarding Environment Clearance & Environment impact Assessment.
31Undertaking regarding No Labour Camping installed.
32Undertaking regarding No Violation of Forest (Conservation) Act 1980.
33Village wish statement of forest and non forest land required under Hazaribag East division
34Toposheet map indicating location of alternative examined
35Undertaking in pending submission of NOC JJ Land (Giridih District)
36Tree Enumeration List
37Tree Felling (Cutting) List
38Tree Trimming List.
39Manual Form-A, Part-1
40NOC for JJ land in Giridih District
41Compliance dated 05.05.2023 undertaking Penal NPV & CA