FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/TRANS/41236/2019   (ii). Name of Project for which Forest Land is required : Construction of 400 kV D/C North Karanpura to Gaya transmission line (Jharkhand Portion)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Ministry of Power, Govt. of India has initiated a scheme for establishment of Transmission System for “Immediate Evacuation for North Karanpura (3X660MW) generation project of M/s NTPC North Karanpura. As a part of the said project a SPV is formed for Construction of Transmission system   (iv). State : Jharkhand   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 16700   (viii). Area of forest land proposed for diversion(in ha.): 197.0115   (ix). Non-forest land required for this project(in ha.): 123.7925   (x). Total period for which the forest land is proposed to be diverted(in years): 35
A-2. Details of User Agency
  (i). Name : NORTH KARANPURA TRANSCO LIMITED   (ii). Address1 : Sunita Sadan 1st Floor Ashram Marg Bariatu Near Military Firing Range   (iii). Address2 : NIL   (iv). State : Jharkhand   (v). District : Ranchi   (vi). Pin : 834009   (vii). Landmark : NEAR MILITARY FIRING RANGE   (viii). Email address : northkaranpuratransco@gmail.com   (ix). Landline Telephone No. : 79-25559476   (x). Fax No. : 79-   (xi). Mobile No. : 7808958161   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: CHANDRA   (ii). Middle Name: SHEKHAR   (iii). Last Name: SINGH   (iv). Gender: Male   (v). Designation: ASSISTANTMANAGER   (vi). Address 1: Sunita Sadan 1st Floor Ashram Marg Bariatu Near Military Firing Range   (vii). Address 2: NIL   (viii). State: Jharkhand   (ix). District: Ranchi   (x). Tehsil: NIL   (xi). Pin: 834009   (xii). Landmark: NEAR MILITARY FIRING RANGE   (xiii). Email Address: northkaranpuratransco@gmail.com   (xiv). Landline Telephone No.: 79-25559476   (xv). Fax No.: NIL   (xvi). Mobile No.: 7808958161   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/JH/TRANS/40694/2019FP/JH/TRANS/40694/201956.325456.325417 Jan 2022
Total 56.3254 56.3254
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Latehar15.358941.9412
2.Chatra South119.880661.1881
3.Chatra North61.77220.6632
Total197.0115123.7925
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Latehar15.358941.9412
1.Chatra181.652681.8513
Total197.0115123.7925
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1PHULBASIA ALIAS AMARWADIH3.6534.1919
2CHARRA1.6925.9558
3RAHEA2.194.804
4BARWADIH1.3413.3285
5BESRA5.47393.8828
6KUSAMHA0.2642.2946
7BHATCHATRA0.1443.0478
8MAKRA04.5982
9SIBLA0.6019.8376
10KASIYATU11.0934.4217
11KASARI2.4761.2767
12NAWADA04.6482
13KENDU4.2318.0932
14DUNDUA2.2113.1556
15BAGRA1.6278.4325
16BELGARA0.5290.001
17KUTHAN8.6261.5651
18BAKSI6.7521.169
19LAMTA1.5567.72
20JOGIADIH6.8460.015
21BHAGNADIH5.7770.104
22MANATU1.471.586
23BARHGAON0.7652.24
24PHERENDA01.4851
25BHANG4.6614.007
26KORCHA1.4620.004
27GULHUTU2.040.004
28PARBAT ALIAS BARAHMANA9.792.922
29AMBADIH1.0990
30GERI3.55263.31
31GHURNADIH1.1610.099
32NARTAMA1.0120.642
33KARMA2.8061.467
34SURUJ4.5960.982
35LARKUA5.8730.013
36SANGHRI11.0571.437
37DARHA9.6050.071
38SIKID7.2070.317
39POSTIA12.6595.6501
40BANDATAR2.690.0059
41DEMDEM4.150.6512
42DHOBEY00.5106
43PAINI KALAN6.5086.1835
44PAINI KHURD0.3060.6317
45KETARIBAR1.4150.1424
46JHAGARTARI4.4010.209
47BANIADIH2.5550.5874
48CHITUA5.4430.0382
49RAHARBAR3.0860.0456
50HALWARIA3.6852.8656
51BAIJNATHPUR0.1710
52KASDABAR0.3442.5143
53GAIGHAT1.9460.578
54BEDAULI7.7930.0396
55KOLWA4.620.0101
Total 197.0115 123.7925
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower Foundation3.46121.156
2STRINGING AREA96.76364.6026
3REMAINING ROW AREA96.787358.0339
Total 197.0115 123.7925
C. Maps of forest land proposed to be diverted
Division 1. : Chatra South
  (i). Area of forest land proposed to be diverted(in ha.) : 119.8806   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.119.8806    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Latehar
  (i). Area of forest land proposed to be diverted(in ha.) : 15.3589   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.15.3589    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : Chatra North
  (i). Area of forest land proposed to be diverted(in ha.) : 61.772   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.61.772    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 40   (iii). Temporary Employment(Number of person-days): 63250
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1SPV FORMATION INFORMATION Certificate of In-cooperation, Memorandum of Association and Article of Association of NKTL
2Transmission License for North Karanpura Transco Limited
3Section 68 Approval for North Karanpura Transco Limited
4Circle Officer Land Schedule Report Bariyatu
5Circle Officer Land Schedule Report Simaria
6Circle Officer Land Schedule Report Lawalaung
7Circle Officer Land Schedule Report Chatra
8Circle Officer Land Schedule Report Hunterganj
9Replies to EDS raise by Nodal Office
10LATEHAR DIVISION CADASTRAL MAPS
11LATEHAR DIVISION FOREST AREA STATEMENT
12Replies to EDS raise by nodal office
13EDS reply Annexure 1 Board Resolution
14EDS reply Annexure 3 CCL NOC letter to NKTL
15EDS reply Annexure 4 CO Report suggested route
16EDS reply Annexure 6 comparative tree enumeration
17Nodal EDS Presentation
18Annexure5 comparative area statements
19letter to Chatra South
20Chatra South EDS reply
21EDS reply Latehar DFO
22Request letter to DFO Chatra South - 14-9-2021
23Request letter for modification in Area in online portal
24component wise area
25district wise area
26VILLAGE WISE-signed
27UNDERTAKING FOR COMPENSATORY AFFORESTATION
28UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
29ARCHAEOLOGICAL IMPORTANCE
30CERTIFICATE FOR MINIMUM USE OF FOREST LAND
31COST OF FELLING TREE
32NOT PASSING THROUGH ANY PROTECTED WILDLIFE SANCTUARY , ECO SENSITIVE ZONE, NATIONAL PARK AND BIOSPHERE RESERVE
33undertaking cs-rs
34UNDERTAKING FOR MUCK DISPOSAL
35UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE & DIVERSION OF MINIMUM FOREST LAND-signed
36UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
37Final Area Statement Chatra (N)
38Final area Chatra (S)
39Final Area Statement Latehar div
40DGPSReport
41CHATRA SOUTH DIVISION SEMERIYA BLOCK CADASTRAL MAP
42CHATRA SOUTH DIVISION LAWALONG BLOCK CADASTRAL MAPS
43CHATRA SOUTH DIVISION CHATR ABLOCK CADASTRALMAPS
44CHATRA NORTH DIVISION HUNTERGANJ BLOCK CADASTRAL MAPS
45EMPLOYMENT GENERATION
46Updated Detailed Project Report (DPR)_NKTL
47CS-RS CERTIFICATE Chatra
48CS-RS CERTIFICATE Latehar
49Gm-JJ NOC Chatra
50NOC GM-JJ Latehar
51Land schedule missing plots Chatra
52Tree Enumeration Latehar -1
53Tree Enumeration Latehar-2
54Chatra South Chatra Range-1
55Chatra South Chatra Range-2
56Chatra south Chatra Range-3
57Chatra south Chatra Range-4
58chatra south simiriya range-1
59chatra south simiriya range-3
60chatra south simiriya range-4
61chatra south simiriya range-2
62Chatra North Hunterganj-1
63Chatra North Hunterganj-2
64Latehar Bariyatu Block gramshabha
65Chatra South simiriya block gramsabha
66Chatra South Lawalong block gramshabha
67CHATRA South Chatra block gramsabha
68Chatra North Hunterganj Block gramshabha
69GM JJ NOC addition land
70ESD reply Chatra South Division 15-02-2022
71EDS reply Chatra North 16-08-2022
72Form A Part 1 Chatra North Division
73Form A part 1 Chatra South
74undertaking for CA chatra south dividion
75Signed Area statement Chatra South
76Signed Area Statement Chatra North
77Undertaking for CA Chatra North Division
78Undertaking Net present value Chatra South
79Undertaking for Net Present Value Chatra North
80EDS reply Chatra South 30-08-2022
81Undertaking for CA -Latehar division
82Undertaking for any condition impose by MOEF
83Undertaking for wildlife management plan
84Area Statement Latehar div-signed
85Form A part 1 Latehar
86Undertaking for NPV -Latehar division
87EDS reply- Latehar DFO
88EDS reply- Chatra South DFO
89EDS reply- Chatra North DFO