FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/TRANS/31258/2018   (ii). Name of Project for which Forest Land is required : JUSNL-NIT-43-220KV-Jasidih-Giridih Transmission Line   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Execution & Commissionining of JUSNL-220KVD/C Transmission Line for Jasidih -Giridih under rural electrification scheme of Govt. of Jharkhand.   (iv). State : Jharkhand   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 5850   (viii). Area of forest land proposed for diversion(in ha.): 53.7504   (ix). Non-forest land required for this project(in ha.): 213.87234   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : JUSNL   (ii). Address1 : Dabar Gram Grid, Jsidih- Deoghar   (iii). Address2 : Deoghar   (iv). State : Jharkhand   (v). District : Deoghar   (vi). Pin : 814142   (vii). Landmark : main Grid Jasidih-Deoghar   (viii). Email address : esetcdeoghar1@gmail.com   (ix). Landline Telephone No. : 6432-5678945   (x). Fax No. : 6432-345678   (xi). Mobile No. : 9431132746   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Sanjeev   (ii). Middle Name: kumar   (iii). Last Name: Barnwal   (iv). Gender: Male   (v). Designation: ESE   (vi). Address 1: Dabar Gram Grid   (vii). Address 2: Jasidih-Deoghar   (viii). State: Jharkhand   (ix). District: Deoghar   (x). Tehsil: Deoghar   (xi). Pin: 814142   (xii). Landmark: near main gid Jasidih-Deoghar   (xiii). Email Address: esetcdeoghar1@gmail.com   (xiv). Landline Telephone No.: 6432-5678945   (xv). Fax No.: 6432345678   (xvi). Mobile No.: 9431132746   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Deoghar12.9614127.46812
2.Giridih40.78986.40422
Total53.7504213.87234
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Deoghar12.9614127.46812
1.Giridih40.78986.40422
Total53.7504213.87234
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1kalipur00.12474
2kumaitha02.9106
3Sagdaha00.6237
4Deopur02.43936
5sarsa04.75398
6Kusmaha02.4948
7Bandahakendua02.27304
8Darpa01.92654
9Garjora03.7422
10Manikpur06.94386
11Mushradih00.12474
12kodadih1.32855.19956
13Kokribank04.06098
14Bhogtadih1.15512.3792
15Dharwadih06.66666
16Rakudih02.03742
17Lodharayadih01.96812
18Rajasar01.30284
19Birnia03.6036
20Raghunathpur01.42758
21Chitaaji Buribad01.2474
22Sardha03.29868
23Baghmari03.40956
24Dhartichak00.67914
25Chhota Rjasare03.29868
26Simrapoj00.9009
27Kokraha02.17602
28Kolharaiya0.0164.37762
29Kendua1.32554.31552
30Rajpura0.0941.87412
31Saharpur1.68484.56606
32Chitarpur0.7935.55488
33Phutabandh0.0052.5591
34Tilauna01.42758
35Choudharidih00.7623
36kinaidih02.13444
37Chaita00.40194
38Nepodih00.38808
39Samiatand00.7623
40Khiruadih0.4461.43896
41Muratari2.11680.61362
42Kasuadih1.3142.0817
43Madanpur0.0282.82716
44Baghmara0.36242.74224
45Lamba0.4512.33486
46Barmuka0.8714.17404
47Pindari0.4473.82188
48Narhasimal0.4714.87896
49Mohanadih0.05231.41686
50Ganro4.6235.79972
51Kumharia3.4021.1718
52Sathibad1.7082.02034
53Tilaiwana1.0278.68886
54Tarajori0.4166.26452
55Chandio0.8683.80282
56Gujrudih00.6237
57Pipratol4.0011.4044
58Fitkoria01.02564
59Chhachhando04.90644
60Dandatanr01.56618
61Durgapur00.54054
62Mahuar2.69211.32046
63Khutabandh03.3957
64Dagrawatanr00.11088
65Bijlibathan02.43936
66Madnatanr0.7842.15432
67Motileda7.6716.1197
68Mohanpur1.580.83164
69Pindatanr1.3023.29952
70Nawadih1.121.9292
71Girdharchak04.11642
72Sundartand00.4851
73Telodih3.9858.91866
74Lohpiti4.5711.37494
75Karharbari0.7561.12896
76Pandedih0.2830.9644
Total 53.7504 213.87234
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower2.8714.971075
2Conductor50.880375198.901255
Total 53.750375 213.87233
C. Maps of forest land proposed to be diverted
Division 1. : Deoghar
  (i). Area of forest land proposed to be diverted(in ha.) : 12.9614   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.12.9614    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Giridih
  (i). Area of forest land proposed to be diverted(in ha.) : 40.789   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.40.789    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 6   (iii). Temporary Employment(Number of person-days): 112500
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Tabular comparison of Alternative route examination with JJ & Forest land.
2Componentwise break-up of forset & non forest land.
3Environment Notification.
4Plot wise forest land Deoghar Division.
5Plot wise forest land Giridih Division.
6Village wise forest & non-forest land.
7Plot verfication report from CO-Giridih Block.
8Plot verfication report from CO-Bengabad Block.
9Plot verfication report from CO-Deoghar Block.
10Plot verfication report from CO-Devipur Block.
11Plot verfication report from CO-Madhupur Block.
12Plan & Elevation.
13Project Sanction order from Energy Deptt (Govt. of Jharkhand).
14Georefernce Map-Chandio.
15Georefernce Map-Ganro.
16Georefernce Map-Ganro.
17Georefernce Map-kumaharia.
18Georefernce Map-Madantnar.
19Georefernce Map-Mahuar.
20Georefernce Map-Mohanpur.
21Georefernce Map-Motileda.
22Georefernce Map-Tarajori.
23NPV
24Deoghar Division FRA.
25reply to DFO query vide letter no-1449 dtd. 20.6.18 . FRA attached & gram sabha copy submitted to Division in 10 copies.
26NOC Jj land from Comiisioner & DC of Deoghar & Giridih Distt.