FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/ENCRH/39652/2019   (ii). Name of Project for which Forest Land is required : ALOKE STEELS INDUSTRIES PVT LTD   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Expansion of existing DRI plant (4 X 100 tpd kiln) by adding the captive power plant and SMS for capacity expansion and to control the pollution.   (iv). State : Jharkhand   (v). Category of the Proposal : Encroachments   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 20385   (viii). Area of forest land proposed for diversion(in ha.): 9.27   (ix). Non-forest land required for this project(in ha.): 11.89   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : ALOKE STEELS INDUSTRIES PVT LTD   (ii). Address1 : Beside PN Bank   (iii). Address2 : Ramgarh, Jharkhand   (iv). State : Jharkhand   (v). District : Ramgarh   (vi). Pin : 829122   (vii). Landmark : On Main Road   (viii). Email address : krpcmecon2017@gmail.com   (ix). Landline Telephone No. : 6553-224601   (x). Fax No. : 6553-223236   (xi). Mobile No. : 7061500799   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: KantiRanjan   (ii). Middle Name: pal   (iii). Last Name: Chaudhuri   (iv). Gender: Male   (v). Designation: Headtechnical   (vi). Address 1: Beside PN Bank   (vii). Address 2: Ramgarh, Jharkhand   (viii). State: Jharkhand   (ix). District: Ramgarh   (x). Tehsil: Patratu   (xi). Pin: 829122   (xii). Landmark: on Main Road   (xiii). Email Address: krpcmecon2017@gmail.com   (xiv). Landline Telephone No.: 6553-224601   (xv). Fax No.: 6553223236   (xvi). Mobile No.: 7061500799   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Ramgarh9.2711.89
Total9.2711.89
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Ramgarh9.2711.89
Total9.2711.89
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Burhakhap9.2711.89
Total 9.27 11.89
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Existing 4 nos of DRI Plant1.224.32
2Existing Road0.570
3Proposed power plant1.150
4Proposed Power Plant Block B2.530
5Steel Melting Shop01.38
6Rolling Mill01.26
7Filter Press0.081.04
8Proposed Pipe Line0.20
9Proposed Briquietting Plant00.86
10Proposed Slag crushing plant00.19
11Proposed Rain Water Harvesting0.10
12Proposed Parking0.470
13Proposed storage for cakes00.5
14Proposed Cooling tower0.420
15proposed canteen0.220
16proposed fuel storage0.20
17proposed repair shop0.320
18proposed intake well0.020
19proposed water storage0.040
20proposed green belt1.732.34
Total 9.27 11.89
C. Maps of forest land proposed to be diverted
Division 1. : Ramgarh
  (i). Area of forest land proposed to be diverted(in ha.) : 9.27   (ii). Nature of the Project: Non Linear   (a). No. of patches : Twelve
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.0.1    View File
2.0.04    View File
3.0.01    View File
4.0.07    View File
5.5.87    View File
6.0.34    View File
7.0.12    View File
8.0.01    View File
9.2.14    View File
10.0.32    View File
11.0.2    View File
12.0.05    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 500   (iii). Temporary Employment(Number of person-days): 1000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes   (a). Status of the Environmental Clearance to the Project: EC application yet to be submitted
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: Three
District 1. : Giridih
  (a). Village: purhara   (b). Area(in ha.): 4.04   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 29   (e). Present owner: User Agency   (f). Copy of Ownership proof:
District 2. : Giridih
  (a). Village: purhara   (b). Area(in ha.): 2.43   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 11   (e). Present owner: User Agency   (f). Copy of Ownership proof:
District 3. : Giridih
  (a). Village: korabandha   (b). Area(in ha.): 2.83   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 447,448,449, 450   (e). Present owner: User Agency   (f). Copy of Ownership proof:
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No Documents
Remarks
1The Company has received Environmental Clearance for Its Expansion Project vide MoEF & CC file no - J-11011/205/2016-IA.II (I) dated 23.07.2018. Copy of same attached herewith for Information
2Authnticated Land Schedule of 21.19 Hect of the Category of Forest & Non Forest Land within the Plant area is attached herewith for ready reference
3Sir, Please find attached herewith the item wise compliance of EDS dated 03.04.2019 for your kind information and necessary action
4Sir, Please find attached herewith the item wise compliance of EDS dated 12.06.2019 for your kind information and necessary action
5Sir, Please find attached herewith the item wise compliance of EDS dated 11.07.2019 for your kind information and necessary action
6Sir, Please find attached herewith the item wise compliance of EDS dated 16.07.2019 for your kind information and necessary action
7Sir, Refer to EDS dated 07.08.2019, the receipt copy of Acknowledgement of submission of hard copy to DC, Ramgarh is attached herewith for kind information and necessary action
8authorization of Sri Manoj Kuamr to sign and upload of proposal
9Board Resolution for authorization of Sri Manoj Kumar
10Village Map of Burhakhap Sheet no 1 showing applied forest area
11Village Map of Burhakhap Sheet no 2 showing applied forest area
12DGPS Plan of CA land in village Korbandha
13DGPS Plan of CA land in village Purhara
14CA land in village map of Purhara
15CA land in village map of Korabandha
16CA Scheme issued by DFO Giridih
17CA Toposheet of Korbandha land patch
18CA Toposheet of Purhara land patch
19Applied forest area plan for FC
20Declaration of minimum use of forest land
21Existing & item wise proposed land use
22Land Schedule of applied forest area for obtaining FC
23Undertaking for fulfilment of Law & Order
24Plan showing item wise existing & proposed land use
25NoC of JJ issued by DC Ramgarh
26Village-wise abstract applied land details
27Non Encroachment letter of CA land 1
28Non Encroachment letter of CA land 2
29CA Land Suitability certificate 1
30CA Land Suitability certificate 2
31Tree Enumeration list within plant
32Tree Enumeration list outside plant
33Undertaking for additional NPV
34Undertaking to bear CA cost
35Undertaking to pay NPV cost
36NoC of Gram Sabha
37Sir, Please find attached herewith the item wise compliance of EDS vide letter no 2126 dated 17.08.2019 for your kind information and necessary action
38Sir, Please find attached herewith the compliance of EDS vide letter no 1635 dated 05.08.2023 for your kind information and necessary action
39reference to your EDS dated 30.08.2023, Hard copies of Forest proposal in 8 set has already been submitted at your good office. Copy of receipt letter is herewith attached for your kind information and necessary action
40We Upload the correct KML file as per authenticated land schedule as per your EDS dated 14.09.2023
41We revised the cost benefit analysis as per NPV rate of MoEF&CC Guideline and same is uploaded in the respective dialogue box
42Sir, Please find attached herewith the item wise compliance of EDS dated 12.10.2023 for your kind information and necessary action