FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/TRANS/151522/2022
(ii). Name of Project for which Forest Land is required :
Construction of 66kV S/C transmission line from Proposed 220/66kV S/Stn. Nadukhar to Shakrori, Shimla (H.P
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
SJPNL has requested to provide power to its water supply schemes (Stage-I Shakrori) for catering water requirements of Shimla & surrounding areas. Hence, a 220kV GIS sub-station by tapping nearby Bhaba-Kunihar line has been proposed by HPSEBL. This will ensure ample water supply to shimla .
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
571.96
(viii). Area of forest land proposed for diversion(in ha.):
1.6681
(ix). Non-forest land required for this project(in ha.):
1.6937
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
HIMACHAL PRADESH STATE ELECTRICITY BOARD LTD
(ii). Address1 :
Himachal Pradesh Electricity Board Shimla
(iii). Address2 :
NIL
(iv). State :
Himachal Pradesh
(v). District :
Shimla
(vi). Pin :
171004
(vii). Landmark :
NIL
(viii). Email address :
sr.xenes.totu@gmail.com
(ix). Landline Telephone No. :
177-2837161
(x). Fax No. :
177-
(xi). Mobile No. :
9418090947
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Er Suresh
(ii). Middle Name:
NIL
(iii). Last Name:
Patial
(iv). Gender:
Male
(v). Designation:
Sr. Executive Engeener
(vi). Address 1:
Himachal Pradesh Electricity Board Divsion Totu Shimla
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Shimla
(x). Tehsil:
Shimla Urban(T)
(xi). Pin:
171004
(xii). Landmark:
NIL
(xiii). Email Address:
sr.xenes.totu@gmail.com
(xiv). Landline Telephone No.:
177-2837161
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9418090947
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Shimla(shimla)
1.6681
1.6937
Total
1.6681
1.6937
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Shimla
1.6681
1.6937
Total
1.6681
1.6937
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Kamla Dungri
0.2571
0.6675
2
Nadukhar
0.6512
0
3
Matogri
0.3578
0.0532
4
Shakrori
0.402
0.973
Total
1.6681
1.6937
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Tower Locations(18m*18m) for Transmission Line
0.162
0.0648
2
Minimum R.O.W. ( i.e. 18m) for transmission line
1.5061
1.6289
Total
1.6681
1.6937
C.
Maps of forest land proposed to be diverted
Division 1. : Shimla(shimla)
(i). Area of forest land proposed to be diverted(in ha.) :
1.6681
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
1.6681
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
14600
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Certificate from Chief Secretary regarding non-availability of suitable non-forest/ revenue forest land
Additional information Details
Documents
S.No
Documents
Remarks
1
Joint Inspection Report
2
Details of Village Code
3
Distance Certificate
4
Line Plan
5
NAC Certificate
6
Information regardign transmission line/Checklist 23
7
Details of Project
8
Catchment Area Treatment Plan
9
Muck Plan
10
Detail Reclamation Plan
11
Justification for Locating in project in F Area
12
Rehablitation of project
13
Compensatory Afforestation
14
Minimunm Use of forest land
15
Net Present value
16
NPV
17
Breakup wise
18
Reply to point No. 3 & 5 of EDS raised on 17.06.2022
19
Reply to point 1 to 5 of EDS raised on 16.07.2022
20
Tatima of Nadukhar
21
Form A
22
Field Book Nadukhar
23
Jamabandi of Nadukhar
24
Tatima of Kamladungri
25
Jamabandi of Kamladungri
26
Field Book of Kamladungri
27
Tatima of Matogari
28
Field Book of Matogari
29
Jamabandi of Matogari
30
Tatima of Shakrori
31
Field book of Shakrori
32
Jamabandi of Shakrori
33
Undertaking FRA
34
Check List Serial Number 8
35
Check List Serial Number 24
36
Three Alignment route Topo and G Map
37
Minutes of Meeting of EHV Transmision line
38
Reply to EDS dt.23.02.2023
39
Revised tree enumeration list along with Joint Inspection report
40
Administrative Approval
41
Revised Detailed Reclamation Plan
42
Revised Muck Disposal Plan
43
Component wise revised digital plan layout
44
Reply to EDS raised by Integrated Regional Office ,Chandigarh, Sub-Office, Shimla on dated:-04.03.2024
45
Complete tree Enumertaion list(to be felled) (ROW+Tower locations) of Nadukhar-Shakrori line
46
Complete tree Enumertaion list(not to be felled) (ROW) of Nadukhar-Shakrori line
47
NAC regarding CA site of Nadukhar-Shakrori line
48
Reply to EDS Dated 14.10.2024
Print