FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/49792/2020   (ii). Name of Project for which Forest Land is required : Lower Bhagair 1 MW SHEP   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Forest land of Kiunr village in forest division Chamba district Chamba H.P. has to be diverted for the construction of Lower Bhagair SHEP (1.00 MW) on Bhagair khad which is a tributary of Kiunr nallah.This project has been alloted to M/s Shiv Shakti Enterprises .   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 743   (viii). Area of forest land proposed for diversion(in ha.): 0.7903   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : SHIV SHAKTI ENTERPRISES   (ii). Address1 : Anurag Kutir, Lower Doharu Mohlla Ghuggar P.O & Teh. Palampur Distt. Kangra (H.P)   (iii). Address2 : V.P.O Kunr Teh. & Distt. Chamba (H.P)   (iv). State : Himachal Pradesh   (v). District : Kangra   (vi). Pin : 176061   (vii). Landmark : NIL   (viii). Email address : arsharma_lic@yahoo.com   (ix). Landline Telephone No. : 0-   (x). Fax No. : 0-   (xi). Mobile No. : 8629081110   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Atma   (ii). Middle Name: Ram   (iii). Last Name: Sharma   (iv). Gender: Male   (v). Designation: Partner   (vi). Address 1: Anurag Kutir, Lower Doharu Ghuggar P.O and Teh. Palampur Distt Kangra H.P   (vii). Address 2: V.P.O Kunr Teh. and Distt. Chamba H.P   (viii). State: Himachal Pradesh   (ix). District: Kangra   (x). Tehsil: Palampur(T)   (xi). Pin: 176061   (xii). Landmark: NIL   (xiii). Email Address: arsharma_lic@yahoo.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 8629081110   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chamba0.79030
Total0.79030
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chamba0.79030
Total0.79030
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Kunr0.79030
Total 0.7903 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Intake/Tranch weir0.00840
2Dumping site-10.00560
3D-Tank Cum Forebay0.01690
4Dumping site - 20.00480
5Power House and Switch Yard0.05780
6Tail race Channe0.04450
7Water conductor system/ Pipe Line intake to forway0.06550
8Water conductor system/ Pipe Line 1 penstock0.06550
9Road cum transmission line in khasra 3045/3009/88/0.46480
10Road cum transmission line in khasra 201/10.0080
11Water conductor system/ Pipe Line 2 penstock0.04850
Total 0.7903 0
C. Maps of forest land proposed to be diverted
Division 1. : Chamba
  (i). Area of forest land proposed to be diverted(in ha.) : 0.7903   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.7903    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 8000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 1.00   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1Implementation agreement
2Village code certificate .
3Undertaking for additional amount of NPV.
4Undertaking for amount of NPV.
5consent latter from himurja.
6NOC Gram Panchyat
7NOC wildlife
8NOC from PWD department
9NOC Fisheries department
10Reply letter of observation raised by Nodal officer Shimla
11undertaking in respect of FRA certificate
12Copy of TEC
13Pointwise Reply
14non availability of non forest land
15reply
16point wise replay
17letter regard evacuation plan
18reclamation plan lower bhagair project
19esz certificate lower bhagair project
20iph noc
21component detail
22point wise reply
23LOCATION MAP LOWER BAHGAIR SMALL HYDRO PROJECT
24NEW POINT WISE REPLY LOWER BAHGAIR
25LIST OF HEPs IN THE LANDSCAPE OF LOWER BHAGAIR SHEP AND CAPACITY TRANSMISSION LINE
26LOWER BAHGAIR SMALL HYDRO PROJECT GLP
27TABLE NO 2 COMPONENT DETAIL
28REC Metting point wise reply
29Joint Inspection Report.
30Comments of DoE GoHP & HIMURJA