FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/49387/2020   (ii). Name of Project for which Forest Land is required : Integrated Kashang Stage II & III   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Hydrological surprises in the oration of Stage I of IKHEP, some modification/ amendment in the project component has been envisaged. This has resulted in the requirement of additional Forest land for the construction of Silt flushing Tunnel (SFT)   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 48819   (viii). Area of forest land proposed for diversion(in ha.): 0.4148   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : HIMACHAL PRADESH POWER CORPORATION LTD   (ii). Address1 : IKHEP, HPPCL, Kinfed Building   (iii). Address2 : Reckong Peo   (iv). State : Himachal Pradesh   (v). District : Kinnaur   (vi). Pin : 172107   (vii). Landmark : Near ITBP Gate   (viii). Email address : gmikhep@gmail.com   (ix). Landline Telephone No. : 1786-222001   (x). Fax No. : 1786-223992   (xi). Mobile No. : 7018930582   (xii). Website (if any) : hppcl.in   (xiii). Legal status of User Agency : State PSU
A-3. Details of Person Making Application
  (i). First Name: Surinder   (ii). Middle Name: Pal   (iii). Last Name: Rattan   (iv). Gender: Male   (v). Designation: DGM   (vi). Address 1: IKHEP, HPPCL, Kinfed Building   (vii). Address 2: Reckong Peo   (viii). State: Himachal Pradesh   (ix). District: Kinnaur   (x). Tehsil: NIL   (xi). Pin: 172107   (xii). Landmark: Near ITBP Gate   (xiii). Email Address: gmikhep@gmail.com   (xiv). Landline Telephone No.: 1786-222001   (xv). Fax No.: 01786223992   (xvi). Mobile No.: 7018930582   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1ApprovedFPE-B-F(2)-67/2009FPE-B-F(2)-67/200917.685717.685722 Mar 201114 Jun 2011
Total 17.6857 17.6857
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Kinnaur0.41480
Total0.41480
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Kinnaur0.41480
Total0.41480
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Kashang0.41480
Total 0.4148 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1SFT Portal0.00160
2Proposed U/G Flushing Tunnel0.050
3Flushing Channel0.17120
4SFT Drain0.1920
Total 0.4148 0
C. Maps of forest land proposed to be diverted
Division 1. : Kinnaur
  (i). Area of forest land proposed to be diverted(in ha.) : 0.4148   (ii). Nature of the Project: Non Linear   (a). No. of patches : One
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.0.4148    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 350
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes   (a). Status of the Environmental Clearance to the Project: EC obtained   (b). Environmental Clearance File No.: J-12011/81/2007-IA.I   (c). Copy of Environmental Clearance to the Project:   (d). Date of grant of Environmental Clearance to the Project: 2010-04-16
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : Yes
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 243   (ii). Total command area of the Project(in ha.): 0   (a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):   (b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No Documents
Remarks
1Inescability certificate
2Joint Inspection report
3Note on Project
4Revised Tatima as desired in Observation
5CERTIFICATE FOR MINIMUM USE OF FOREST LAND
6UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
7UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
8UNDERTAKING FOR PAYMENT OF ADDITIONAL NPV OF FOREST AREA
9Detail of Forest Land
10NOC of Pollution Control Board
11NOC of HPSEBL
12NOC of Fisheries
13Environment Management Plan
14Allotment Letter
15NOC of IPH
16TEC
17Non-Availability of Non-Forest Land Certificate for Project
18Muck Management Plan
19Reply Letter
20Combined1
21Combined2
22Layout Plan
23Revenue papers
24MAP of Alternate
25Reply With Annexure 18.01.2024
26Reply With Annexure 24.03.2023
27EDS 29.01.2024 reply
28Demand Draft
29Dumping Details
30Cost Mitigation letter
31CAT Plan
32Green Belt Development Plan
33EAC Minutes