FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/43637/2019   (ii). Name of Project for which Forest Land is required : Thaltu khorh-II HEP (5 MW)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Thaltu khorh Stage-II is 5.0 MW run of river small hydro electric project located in Teh. Padhar on Thaltukhod Nallah, Tributary of UHL River in jogindernager Forest Distt Mandi.   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 5281   (viii). Area of forest land proposed for diversion(in ha.): 3.6693   (ix). Non-forest land required for this project(in ha.): 0.297   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : CLIFF FINVEST PVT. LTD.   (ii). Address1 : 1-41, DLF Industrial Area Phase - 1, Faridabad - 121003   (iii). Address2 : NIL   (iv). State : Haryana   (v). District : Faridabad   (vi). Pin : 121003   (vii). Landmark : Near NHPC Chonk, Metro Station   (viii). Email address : kkkhpl@kkkhydropower.com   (ix). Landline Telephone No. : 129-413168   (x). Fax No. : 129-   (xi). Mobile No. : 9418850150   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Naresh   (ii). Middle Name: Kumar   (iii). Last Name: Thakur   (iv). Gender: Male   (v). Designation: Manager Admin   (vi). Address 1: V.P.O Barot, Tehsil Padhar, Distt. Mandi HP   (vii). Address 2: NIL   (viii). State: Himachal Pradesh   (ix). District: Mandi   (x). Tehsil: Padhar(T)   (xi). Pin: 175013   (xii). Landmark: NIL   (xiii). Email Address: cliffhydro207@gmail.com   (xiv). Landline Telephone No.: 129-413168   (xv). Fax No.: NIL   (xvi). Mobile No.: 9418850150   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.J/Nagar3.66930.297
Total3.66930.297
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Mandi3.66930.297
Total3.66930.297
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Khariyan0.84690.2284
2Mathi Bajgaan2.52680
3Cheling0.29560.0686
Total 3.6693 0.297
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Weir Site0.22230.0042
2Approach road to Weir site0.0370
3Desilting Tank00.1255
4Pipe Line00.0987
5Muck duping site - 1,II and III0.91850
6Tunnel and Adit Tunnel0.70980
7Forebay & Penstock0.62480
8Muck dumping site -IV0.03210
9Power House & Switch Yard0.5870
10Muck Dumping site - V0.16150
11Aproch road From PWD road to Power House0.14490.0686
12Bridge0.01580
13Transmission Line0.21560
Total 3.6693 0.297
C. Maps of forest land proposed to be diverted
Division 1. : J/Nagar
  (i). Area of forest land proposed to be diverted(in ha.) : 3.6693   (ii). Nature of the Project: Non Linear   (a). No. of patches : One
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.6693    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 32   (iii). Temporary Employment(Number of person-days): 160
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Diversion of forest land up to one hectare
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 5   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1Consent latter of the project.
2NOC from Gram Panchyat.
3NOC from I&PH.
4NOC from PWD.
5NOC from Wild Life.
6NOC from Fisheries.
7village Code Certificate from the revenue authority.
8Non Availability of non forest land Certificate.
9Non Availbility of Non forest land for CA.
10Joint Inspection Certificate.
113 Undertaking CA.
124 Undertaking NPV.
13Undertaking Additional NPV.
14Abstract of Land.
15Eco sensitive Zon Certificate.
16Undertaking for FRA certificate.
17Reply Latter for the objection.
18under taking for I/A.
19under taking for TEC.
20Replay of the objection
21observation reply letter raised by MOEF Derhadun office dated 10-03-2021
22Transmission line plan of the project
23component wise breakup of the forest land coming in the alignment of the project
24FCA pdf file of Thaltukhod stage -II project
25DFO observation reply letter dated -09-07-2021
26DFO observation reply letter dated 15-07-2021
27Transmission line detail
28Jarnal Lyout plane of Stage -1 & II
29basin study latter from DOE.
30journal layout plane.
31wild life area marked on toposheet.
32Report from wild life.
33complete wit latest reply.
34replay to DFO. on 27/01/2022.
35reply on 22/03/2023
36Evucation plan of 1& 2 projects.
37complete file of objection.
38basin study.
39basin study.
40rely latter on 06/04/2023.
41Reply on 20.03.2024
42Reply on 20.03.2024 detailed basion study of projects.
43list of approved/existing//proposed projects. Authenticated by compatent authorty.
44reply later.