FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/HYD/43637/2019
(ii). Name of Project for which Forest Land is required :
Thaltu khorh-II HEP (5 MW)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Thaltu khorh Stage-II is 5.0 MW run of river small hydro electric project located in Teh. Padhar on Thaltukhod Nallah, Tributary of UHL River in jogindernager Forest Distt Mandi.
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
5281
(viii). Area of forest land proposed for diversion(in ha.):
3.6693
(ix). Non-forest land required for this project(in ha.):
0.297
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
CLIFF FINVEST PVT. LTD.
(ii). Address1 :
1-41, DLF Industrial Area Phase - 1, Faridabad - 121003
(iii). Address2 :
NIL
(iv). State :
Haryana
(v). District :
Faridabad
(vi). Pin :
121003
(vii). Landmark :
Near NHPC Chonk, Metro Station
(viii). Email address :
kkkhpl@kkkhydropower.com
(ix). Landline Telephone No. :
129-413168
(x). Fax No. :
129-
(xi). Mobile No. :
9418850150
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
Naresh
(ii). Middle Name:
Kumar
(iii). Last Name:
Thakur
(iv). Gender:
Male
(v). Designation:
Manager Admin
(vi). Address 1:
V.P.O Barot, Tehsil Padhar, Distt. Mandi HP
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Mandi
(x). Tehsil:
Padhar(T)
(xi). Pin:
175013
(xii). Landmark:
NIL
(xiii). Email Address:
cliffhydro207@gmail.com
(xiv). Landline Telephone No.:
129-413168
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9418850150
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
J/Nagar
3.6693
0.297
Total
3.6693
0.297
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Mandi
3.6693
0.297
Total
3.6693
0.297
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Khariyan
0.8469
0.2284
2
Mathi Bajgaan
2.5268
0
3
Cheling
0.2956
0.0686
Total
3.6693
0.297
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Weir Site
0.2223
0.0042
2
Approach road to Weir site
0.037
0
3
Desilting Tank
0
0.1255
4
Pipe Line
0
0.0987
5
Muck duping site - 1,II and III
0.9185
0
6
Tunnel and Adit Tunnel
0.7098
0
7
Forebay & Penstock
0.6248
0
8
Muck dumping site -IV
0.0321
0
9
Power House & Switch Yard
0.587
0
10
Muck Dumping site - V
0.1615
0
11
Aproch road From PWD road to Power House
0.1449
0.0686
12
Bridge
0.0158
0
13
Transmission Line
0.2156
0
Total
3.6693
0.297
C.
Maps of forest land proposed to be diverted
Division 1. : J/Nagar
(i). Area of forest land proposed to be diverted(in ha.) :
3.6693
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
3.6693
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
32
(iii). Temporary Employment(Number of person-days):
160
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Diversion of forest land up to one hectare
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
5
(ii). Total command area of the Project(in ha.):
0
Additional information Details
Documents
S.No
Documents
Remarks
1
Consent latter of the project.
2
NOC from Gram Panchyat.
3
NOC from I&PH.
4
NOC from PWD.
5
NOC from Wild Life.
6
NOC from Fisheries.
7
village Code Certificate from the revenue authority.
8
Non Availability of non forest land Certificate.
9
Non Availbility of Non forest land for CA.
10
Joint Inspection Certificate.
11
3 Undertaking CA.
12
4 Undertaking NPV.
13
Undertaking Additional NPV.
14
Abstract of Land.
15
Eco sensitive Zon Certificate.
16
Undertaking for FRA certificate.
17
Reply Latter for the objection.
18
under taking for I/A.
19
under taking for TEC.
20
Replay of the objection
21
observation reply letter raised by MOEF Derhadun office dated 10-03-2021
22
Transmission line plan of the project
23
component wise breakup of the forest land coming in the alignment of the project
24
FCA pdf file of Thaltukhod stage -II project
25
DFO observation reply letter dated -09-07-2021
26
DFO observation reply letter dated 15-07-2021
27
Transmission line detail
28
Jarnal Lyout plane of Stage -1 & II
29
basin study latter from DOE.
30
journal layout plane.
31
wild life area marked on toposheet.
32
Report from wild life.
33
complete wit latest reply.
34
replay to DFO. on 27/01/2022.
35
reply on 22/03/2023
36
Evucation plan of 1& 2 projects.
37
complete file of objection.
38
basin study.
39
basin study.
40
rely latter on 06/04/2023.
41
Reply on 20.03.2024
42
Reply on 20.03.2024 detailed basion study of projects.
43
list of approved/existing//proposed projects. Authenticated by compatent authorty.
44
reply later.
Print