A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/43637/2019   (ii). Name of Project for which Forest Land is required : Thaltu khorh-II HEP (5 MW)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Thaltu khorh Stage-II is 5.0 MW run of river small hydro electric project located in Teh. Padhar on Thaltukhod Nallah, Tributary of UHL River in jogindernager Forest Distt Mandi.   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 5281   (viii). Area of forest land proposed for diversion(in ha.): 3.6693   (ix). Non-forest land required for this project(in ha.): 0.297   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : CLIFF FINVEST PVT. LTD.   (ii). Address1 : 1-41, DLF Industrial Area Phase - 1, Faridabad - 121003   (iii). Address2 : NIL   (iv). State : Haryana   (v). District : Faridabad   (vi). Pin : 121003   (vii). Landmark : Near NHPC Chonk, Metro Station   (viii). Email address : kkkhpl@kkkhydropower.com   (ix). Landline Telephone No. : 129-413168   (x). Fax No. : 129-   (xi). Mobile No. : 9418850150   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Naresh   (ii). Middle Name: Kumar   (iii). Last Name: Thakur   (iv). Gender: Male   (v). Designation: Manager Admin   (vi). Address 1: V.P.O Barot, Tehsil Padhar, Distt. Mandi HP   (vii). Address 2: NIL   (viii). State: Himachal Pradesh   (ix). District: Mandi   (x). Tehsil: Padhar(T)   (xi). Pin: 175013   (xii). Landmark: NIL   (xiii). Email Address: cliffhydro207@gmail.com   (xiv). Landline Telephone No.: 129-413168   (xv). Fax No.: NIL   (xvi). Mobile No.: 9418850150   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.J/Nagar3.66930.297
Total3.66930.297
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Mandi3.66930.297
Total3.66930.297
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Khariyan0.84690.2284
2Mathi Bajgaan2.52680
3Cheling0.29560.0686
Total 3.6693 0.297
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Weir Site0.22230.0042
2Approach road to Weir site0.0370
3Desilting Tank00.1255
4Pipe Line00.0987
5Muck duping site - 1,II and III0.91850
6Tunnel and Adit Tunnel0.70980
7Forebay & Penstock0.62480
8Muck dumping site -IV0.03210
9Power House & Switch Yard0.5870
10Muck Dumping site - V0.16150
11Aproch road From PWD road to Power House0.14490.0686
12Bridge0.01580
13Transmission Line0.21560
Total 3.6693 0.297
C. Maps of forest land proposed to be diverted
Division 1. : J/Nagar
  (i). Area of forest land proposed to be diverted(in ha.) : 3.6693   (ii). Nature of the Project: Non Linear   (a). No. of patches : One
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.6693    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 32   (iii). Temporary Employment(Number of person-days): 160
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Diversion of forest land up to one hectare
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 5   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1Consent latter of the project.
2NOC from Gram Panchyat.
3NOC from I&PH.
4NOC from PWD.
5NOC from Wild Life.
6NOC from Fisheries.
7village Code Certificate from the revenue authority.
8Non Availability of non forest land Certificate.
9Non Availbility of Non forest land for CA.
10Joint Inspection Certificate.
113 Undertaking CA.
124 Undertaking NPV.
13Undertaking Additional NPV.
14Abstract of Land.
15Eco sensitive Zon Certificate.
16Undertaking for FRA certificate.
17Reply Latter for the objection.
18under taking for I/A.
19Replay of the objection
20observation reply letter raised by MOEF Derhadun office dated 10-03-2021
21Transmission line plan of the project
22component wise breakup of the forest land coming in the alignment of the project
23FCA pdf file of Thaltukhod stage -II project
24DFO observation reply letter dated -09-07-2021
25DFO observation reply letter dated 15-07-2021
26Transmission line detail
27Jarnal Lyout plane of Stage -1 & II
28basin study latter from DOE.
29journal layout plane.
30wild life area marked on toposheet.
31Report from wild life.
32complete wit latest reply.
33replay to DFO. on 27/01/2022.
34reply on 22/03/2023
35Evucation plan of 1& 2 projects.
36complete file of objection.
37basin study.
38basin study.
39rely latter on 06/04/2023.
40Reply on 20.03.2024
41Reply on 20.03.2024 detailed basion study of projects.
42list of approved/existing//proposed projects. Authenticated by compatent authorty.
43reply later.
44Approved TEC .
45Undertaking for IA.
46Reply latter of the objection
47Detail of the project in thaltu koth Nalaha by competent Authority.
48Tripartite Agreement Excited after change of the company and change the Shareholding after govt approval.
49reply latter on 08/08/2024
50Project detail of the Nalliah.
51reply of the EDS raised on September 2025