FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/HYD/41259/2019
(ii). Name of Project for which Forest Land is required :
Pharari SHEP 2.00 MW
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The Pharari SHEP 2.00 MW is a run of the river scheme for hydro power generation on Pharari Nallah, tributary of Fozal/Beas River is project is proposed in Pharari village of Kullu District of Himachal Pradesh.
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
1686.74
(viii). Area of forest land proposed for diversion(in ha.):
0.4476
(ix). Non-forest land required for this project(in ha.):
0.0138
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
PHARARI POWER PVT LTD
(ii). Address1 :
House no. 99, ward no. 8, Dhalpur Kullu HP
(iii). Address2 :
NIL
(iv). State :
Himachal Pradesh
(v). District :
Kullu
(vi). Pin :
175101
(vii). Landmark :
Behind SBI Bank Dhalpur
(viii). Email address :
gangananna@gmail.com
(ix). Landline Telephone No. :
1902-222120
(x). Fax No. :
1902-
(xi). Mobile No. :
9459992049
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
Disha
(ii). Middle Name:
NIL
(iii). Last Name:
Sharma
(iv). Gender:
Female
(v). Designation:
Manager
(vi). Address 1:
W/o. Sh. Rajneesh Sharma, House No. 1, Ward No. 11, Near HDFC Bank , Mahant Behr, Kullu
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Kullu
(x). Tehsil:
Kullu(T)
(xi). Pin:
175101
(xii). Landmark:
Dhalpur
(xiii). Email Address:
gauriganga22@gmail.com
(xiv). Landline Telephone No.:
1902-222120
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9805444180
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kullu
0.4476
0.0138
Total
0.4476
0.0138
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kullu
0.4476
0.0138
Total
0.4476
0.0138
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Pharari
0.2649
0.0138
2
Runga-II
0.1619
0
3
Meha
0.0208
0
Total
0.4476
0.0138
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
MD-3
0.004
0
2
Trench Weir
0.0144
0
3
Feeder Channel
0.0136
0
4
Desilting Tank
0.024
0
5
Water Conductor System
0.1514
0.0138
6
Forebay
0.016
0
7
Penstock
0.1161
0
8
Power House
0.05
0
9
Tail Race
0.0048
0
10
Switchyard
0.0195
0
11
MD-2
0.005
0
12
MD-1, Road & U/G Transmission Line
0.008
0
13
Road Cum U/G Transmission Line
0.0048
0
14
Bridge Cum U/G Transmission Line
0.016
0
Total
0.4476
0.0138
C.
Maps of forest land proposed to be diverted
Division 1. : Kullu
(i). Area of forest land proposed to be diverted(in ha.) :
0.5959
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.4476
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
12
(iii). Temporary Employment(Number of person-days):
4000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
2.00
(ii). Total command area of the Project(in ha.):
0
Additional information Details
Documents
S.No
Documents
Remarks
1
Allotment Letter
2
Triparty Agreement
3
Joint Inspection Report
4
Non availability on non forest land certificate
5
Wildlife NOC
6
IPH NOC
7
undertaking of payment of CA
8
undertaking for cooking gas etc
9
Not change of the proposal certificate
10
minimum use of forest land
11
Fisheries NOC
12
Gram Panchayat NOC Letter
13
Dumping Site & Reclamation Plan
14
Population Details Village wise issud by the Deputy Commissioner
15
PWD NOC
16
revised layout plan
17
comparative statement
18
dumping site
19
fieldbook
20
Gram Panchayat Dwada NOC
21
Gram Panchayat Pichlihar NOC
22
Supplementary Implementation Agreement
23
Detial of Transmission Line and Road
24
PCCF Wild Life Shimla NOC
25
undertaking for WLMP and SMCP
26
undertaking for e flow
27
up and down with aerial distance map
28
power generation pharari
29
TEC
30
power evuacation
31
River Basin Study of Beas River
32
Pharari Revised fca in single PDF
33
undertaking for abide by all condition
34
Reply Letter to the DFO July 2025
35
detail of road bridge and ug t. line
36
power evacuation Approval Letter and plan
37
reply 23.8.25
38
check list no. 7
39
check list no. 32
40
power evacuation letter and plan
41
Reply Letter to DFO Sep. 2025
42
digital map of approved and existing project with aerial distance map
43
DoE Letter
44
Holistic assesment report of Pharari
45
Reply letter to The DFO 8 Jan. 2026