FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/38741/2019   (ii). Name of Project for which Forest Land is required : Bloot Fozal   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 4.8639 ha of forest land in favour of M/s Bloot Hydro Power for the c/o of Bloot Fozal HEP (5.0 MW) within the jurisdiction of Kullu Forest Division   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 4134   (viii). Area of forest land proposed for diversion(in ha.): 4.864   (ix). Non-forest land required for this project(in ha.): 0.063   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : BLOOT FOZAL HYDRO PRIVATE LIMITED   (ii). Address1 : Bloot Fozal Hydro Pvt. Ltd. C-209, F/F Sector-100 Noida-201304   (iii). Address2 : NIL   (iv). State : Uttar Pradesh   (v). District : Gautam Buddha Nagar   (vi). Pin : 201304   (vii). Landmark : NIL   (viii). Email address : sankaran.n@gmail.com   (ix). Landline Telephone No. : 0--   (x). Fax No. : 0-   (xi). Mobile No. : 9958895355   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Anoop   (ii). Middle Name: NIL   (iii). Last Name: Kumar   (iv). Gender: NIL   (v). Designation: Supervisor   (vi). Address 1: Anoop Kumar S/o Late Sh. Prithi Chand R/o Vill Henja PO Bhawarna Tehsil Palampur, Distt. Kangra-176083   (vii). Address 2: NIL   (viii). State: Himachal Pradesh   (ix). District: Kangra   (x). Tehsil: NIL   (xi). Pin: 176083   (xii). Landmark: NIL   (xiii). Email Address: blootfozal@gmail.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 8219823351   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Kullu4.8640.063
Total4.8640.063
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Kullu4.8640.063
Total4.8640.063
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Pichhalihar4.86390.0628
Total 4.8639 0.0628
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Trench Weir0.120
2Power Channel0.06170
3Desilting Tank0.0750
4Flushing Channel0.0640
5HRT0.34650
6Adit-I0.01280
7Adit-II0.01050
8Forebay0.04920
9Penstock0.1450.0614
10Power House0.15010
11Switch Yard0.09780
12T/line Platform0.0570
13Transmission Line0.80220
14Dumping-I0.23750
15Dumping-20.180
16Dumping-30.090
17Dumping-40.1350
18Dumping-50.0510
19Dumping-60.090
20Footpath0.01660
21Working Area0.0160
22Road1.97180
23Bridge0.0230
24Ropeway0.0280
25TRC0.03320.0014
Total 4.8639 0.0628
C. Maps of forest land proposed to be diverted
Division 1. : Kullu
  (i). Area of forest land proposed to be diverted(in ha.) : 4.864   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.4.8639    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 22000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Certificate from Chief Secretary regarding non-availability of suitable non-forest/ revenue forest land
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 5.0   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1Joint Inspection Report
2Gram Panchayat NOC
3EDS dated 27.01.2022 Reply
4Checklist-2-Demand Letter
5Checklist-3-Part-1
6Checklist-4-Detailed Note
7Checklist-7-Statement Showing Forest Area
8Checklist-8-Statement Showing Non-Forest area
9Checklist-9-Non availability Certificate
10Checklist-11-Certificate for Minimum use of forest land
11Checklist-12-CA Undertaking
12Checklist-13-NPV & Addl. NPV Undertaking
13Checklist-20-CA land suitability Certificate
14Checklist-21-Certificate of CA land non-availability
15Checklist-28-Reclamation Plan/bill
16Villages to be benefited certificate
17Distance Certificate
18Checklist-15-Enumeration List of trees
19Checklist-16-Site Inspection report of DFO
20Checklist-17-Location Map
21Checklist-18-CA Scheme and Bill
22Checklist-30-Revenue Papers
23Checklist-30-Joint Inspection, NPV, NOCs etc.
24Allotment letter from HIMURJA
25Distance of PAs and their ESZs from the projects falling in the landscape/stream
26Muck Management Plan and their X-Section
27Checklist-6-Layout Plan
28Soil Moisture Conservation Plan Undertaking
29Undertaking regarding providing NOC/sale deed of non-forest/Private area
30EDS dated 20.07.2023 reply
31Lenght and Width detail of Road, Footpath and T/line
32Detail of Transmission Line and Power evacuation Plan
33Approved capacity of stream alongwith list of projects
34TEC, IA, NOCs (PWD, Fishries, I&PH) and Authority letter
35EDS 17.01.2024 reply
36EDS dated 22.11.2024 reply