FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/HYD/37189/2018
(ii). Name of Project for which Forest Land is required :
Kasol Hydro Power Project
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
TO GENERATE EMPLOYMENT FOR LOCAL PEOPLE AND GENERATION OF ELECTRICITY TO MEET OUT NEEDS OF COUNTRY.
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
534900
(viii). Area of forest land proposed for diversion(in ha.):
1.496448
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
MS BEENA BUTAIL PALMPUR
(ii). Address1 :
BANDLA TEA ESTATE PALMPUR TEH PALMPUR DISTT KANGRA HP
(iii). Address2 :
NIL
(iv). State :
Himachal Pradesh
(v). District :
Kangra
(vi). Pin :
176061
(vii). Landmark :
BANDLA TEA ESTATE
(viii). Email address :
kasolhydroproject1971@gmail.com
(ix). Landline Telephone No. :
1902-223510
(x). Fax No. :
1902-
(xi). Mobile No. :
7018562123
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
jitender
(ii). Middle Name:
NIL
(iii). Last Name:
singh
(iv). Gender:
Male
(v). Designation:
consultant
(vi). Address 1:
c/o global computr center near puri petrol pump gandhi nagar kullu hp
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Kullu
(x). Tehsil:
Kullu(T)
(xi). Pin:
175101
(xii). Landmark:
NIL
(xiii). Email Address:
kasolhydroproject1971@gmail.com
(xiv). Landline Telephone No.:
1902-223510
(xv). Fax No.:
NIL
(xvi). Mobile No.:
7018562123
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Parbati
1.496448
0
Total
1.496448
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kullu
1.496448
0
Total
1.496448
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
kasol
1.496448
0
Total
1.496448
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
WEIR SIDE ROAD
0.018809
0
2
MUCK DUMPING-1
0.019821
0
3
DIVERSION WEIR
0.017798
0
4
WATER CHANNEL-1
0.00809
0
5
DESILTING TANK
0.04672
0
6
MUCK DUMPING-2
0.015573
0
7
WATER CHANNEL-2
0.009708
0
8
MUCK DUMPING-3
0.065125
0
9
TUNNEL INLET
0.011124
0
10
TUNNEL
0.610795
0
11
ADIT
0.023461
0
12
MUCK DUMPING-4
0.077866
0
13
FOREWAY TANK
0.017798
0
14
MUCK DUMPING-5
0.031147
0
15
PENSTOCK
0.115687
0
16
MUCK DUMPING-6
0.004247
0
17
MUCK DUMPING-7
0.004247
0
18
POWER/SWITCHYARD
0.04672
0
19
MUCK DUMPING-8
0.059462
0
20
WEIR ROAD
0.019416
0
21
TAIL RACE
0.008899
0
22
ROPEWAY STRUCTURE
0.00991
0
23
ROPEWAY-1
0.140766
0
24
STRUCTURE
0.00991
0
25
ROPEWAY-2 STRUCTURE
0.00991
0
26
ROPEWAY-2
0.080091
0
27
INTER CONNECTION POINT
0.0133
0
Total
1.4964
0
C.
Maps of forest land proposed to be diverted
Division 1. : Parbati
(i). Area of forest land proposed to be diverted(in ha.) :
1.496448
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
1.496448
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
16
(iii). Temporary Employment(Number of person-days):
200
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Others
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
5.00
(ii). Total command area of the Project(in ha.):
0
Additional information Details
Documents
S.No
Documents
Remarks
1
FOREST AREA FOR DIVERSION
2
NON-FOREST AREA FOR DIVERSION
3
Inescapability crtificate
4
JUSTIFICATION FOR LOCATING THR PROJECT IN FOREST AREA
5
CERTIFICATE FOR MINIMUM USE OF FOREST LAND
6
ALTERNATIVE STUDY
7
UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTSTION
8
UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE
9
UNDERTAKING FOR PAYMENT OF ADDITIONAL NET PRESENT VALUE
10
NON-AVAILABILITY OF LAND FOR COMPENSATORY
11
ALLOTMENT LETTER
12
JOINT INSPECTION
13
NOC PWD
14
NOC IPH
15
NOC REVENEW
16
NOC WILDLIFE
17
UNDERTAKING FOR GEO-REFERENCE
18
UNDERTAKING FOR NPV
19
UNDERTAKING FOR NOT CHANGE THE ALIGNMENT
20
UNDERTAKING FOR PROVIDE COOKING GAS AND KEROSENE
21
UNDERTAKING FOR DAMAGES TREES ETC
22
UNDERTAKING FOR EXTRA LAND DAMAGES ETC
23
UNDERTAKING FOR LABOUR CAMP
24
UNDERTAKING FOR NOC FISHERIES
25
UNDERTAKING FOR FRA CERTIFICATE
26
UNDERTAKING FOR PANCHYAT NOC
27
COMPONENT WISE BREAKUP
28
UNDERTAKING FOR INTERCONNECTION POINT
29
UNDERTAKING FOR DISTANCE CERTIFICATE FROM ECO SENSITIVE ZONE
30
village breakup with code
31
inter connection point
32
Techno Economic Clearance
33
Detail of HEPs over stream and distance from ESZs and PAs
34
Reply to REC observations
35
River Beas Basin Study Data
36
WLMP and SMCP undertaking
37
Undertaking Implementation Agreement
38
Undertaking regarding comments of CWLW
39
Approved capacity and detail of proposals over the stream/nallah
40
EDS dated 12.10.2023 reply
41
HIMURJA letter on Implementation Agreement
42
EDS 09.11.2023 Reply
43
EDS dated 27.01.2024 reply
44
Comments of CWLW
Print