FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/HYD/148103/2021
(ii). Name of Project for which Forest Land is required :
Banuala Baroond-I
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Banuala Baroond-I small Hydro project (2 MW ) is a run of the river scheme which has been envisaged to utilize the water of Churkhu Nala for Power generation in Tehsil Churah Distt. Chamba HP.
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
2045
(viii). Area of forest land proposed for diversion(in ha.):
1.0188
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
GYATRI HYDEL PROJECT PVT. LTD.
(ii). Address1 :
Mohalla Charpat PO, tehsil and Distt. Chamba HP
(iii). Address2 :
NIL
(iv). State :
Himachal Pradesh
(v). District :
Chamba
(vi). Pin :
176310
(vii). Landmark :
Near Laxmi Narayan Temple
(viii). Email address :
gyatrihydelp.ltd@gmail.com
(ix). Landline Telephone No. :
0-
(x). Fax No. :
0-
(xi). Mobile No. :
7831831053
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
ved
(ii). Middle Name:
Vyas
(iii). Last Name:
Thakur
(iv). Gender:
Male
(v). Designation:
Project Manager
(vi). Address 1:
Village Gholti PO Sarol tehsil and Distt. Chamba HP 176310
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Chamba
(x). Tehsil:
Chamba(T)
(xi). Pin:
176310
(xii). Landmark:
Near sheep Development farm sarol
(xiii). Email Address:
bbshep2mw@gmail.com
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9459242593
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Chamba
1.0188
0
Total
1.0188
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Chamba
1.0188
0
Total
1.0188
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Prabha
1.0188
0
Total
1.0188
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Weir Site
0.0065
0
2
Conveyance Channel
0.017
0
3
D tank Cum Forebay
0.0354
0
4
Penstock
0.3208
0
5
Silt Flushing
0.0061
0
6
Dumping Site-I
0.017
0
7
Dumping Site-II
0.0142
0
8
Dumping Site-III
0.0194
0
9
Power House Complex & Switch Yard
0.091
0
10
Dumping Site-IV
0.0156
0
11
Tail race
0.004
0
12
Dumping Site-V
0.017
0
13
Road
0.0872
0
14
Transmission Line
0.3676
0
Total
1.0188
0
C.
Maps of forest land proposed to be diverted
Division 1. : Chamba
(i). Area of forest land proposed to be diverted(in ha.) :
1.0188
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
1.0188
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
12
(iii). Temporary Employment(Number of person-days):
27000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Others
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
2
(ii). Total command area of the Project(in ha.):
0
Additional information Details
Documents
S.No
Documents
Remarks
1
Approval of Bifurcation of project
2
Approval of Feasibility Report
3
DC Certificate No Alternative Land
4
DC Certificate Non availability of non Forest land CA
5
HPPWD NOC
6
IPH NOC
7
Joint Inspection Report
8
Non Violation Certificate
9
Panchayat NOC
10
Consent Letter
11
Eco sensitive zone certificate
12
Undertaking to Pay CA cost
13
Undertaking to Pay cost of NPV
14
Reply to EDS Point wise
15
Undertaking to Pay Addl NPV
16
Beneficiary Certificate
17
Reply of EDS to DFO
18
Land suitability Certificate For CA Land
19
PROPOSAL PDF(SCANNED)
20
Proposal Documents (scanned) after Attending Observations
21
Form-A (Part-I)
22
Minimum Use of Land Certificate
23
Reply of EDS to Nodal
24
Proposal (Scanned)
25
Fishery NOC
26
Detail Note on the Project
27
Component wise Land Detail
28
Detail of Forest Land
29
Aproach Road Detail
30
Transmission Line and Pole Distance
31
Undertaking to Submit TEC and IA
32
Evacuation Plan
33
Reclamation and Muck Dumping Plan
34
EDSs (by IRO Shimla) Reply on 6-2-2023
35
EDSs (by IRO Shimla on 15-03-2023) Reply
36
General Layout Plan
37
Reply to EDSs(by IRO Shimla) on 15-05-2023
38
Reply of EDSs made by IRO Shimla on 2-5-2024
39
Reply to EDSs 11.6.24 by Nodal Office
Print