  (i). Proposal No. : FP/HP/HYD/147118/2021   (ii). Name of Project for which Forest Land is required : Jiwa-II (1.75 MW) SHEP   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Jiwa-II (1.75 MW) Hydro Electric Project is run-of-the river project. This project is located opposite village Kathiari/Bhiyali near Sainj town in Sub-Tehsil Sainj, Sub Division Banjar, District Kullu, Himachal Pradesh.   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 1313.83   (viii). Area of forest land proposed for diversion(in ha.): 0.8223   (ix). Non-forest land required for this project(in ha.): 0.0121   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : BEHAL MOTORS   (ii). Address1 : Plot No. 6-7, Industrial Area, Phase-III   (iii). Address2 : Saulikhad Mandi HP   (iv). State : Himachal Pradesh   (v). District : Mandi   (vi). Pin : 175001   (vii). Landmark : Saulikhad   (viii). Email address : d.pdhawan@rediffmail.com   (ix). Landline Telephone No. : 1905-235102   (x). Fax No. : 1905-   (xi). Mobile No. : 9418062183   (xii). Website (if any) : No   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Deepak   (ii). Middle Name: NIL   (iii). Last Name: Dhawan   (iv). Gender: Male   (v). Designation: Director   (vi). Address 1: S/o Sh. Rajinder Dhawan, 18/1, Jawahar Nagar, Mandi   (vii). Address 2: HP   (viii). State: Himachal Pradesh   (ix). District: Mandi   (x). Tehsil: Mandi(T)   (xi). Pin: 175001   (xii). Landmark: Jawahar Nagar Mandi   (xiii). Email Address: d.pdhawan@rediffmail.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 9418062183   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.GHNP0.82230.0121
Total0.82230.0121
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Kullu0.82230.0121
Total0.82230.0121
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Kathiari/ Bhiyali0.82230.0121
Total 0.8223 0.0121
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Weir Site0.02260
2Intake Tank0.00240
3Water Channel-10.04360
4MD-10.01410
5Score Pipe0.00320
6Desilting Tank0.02420
7MD-II0.01410
8Water Channel-II0.28920
9MD-III0.00710
10MD-IV0.00560
11Forebay Tank0.01410
12MD-V0.02540
13Penstock0.03950
14Power House cum Switchyard0.14820
15Tail Race0.00360
16MD-VI0.03990
17Raod Cum U/G Transmission Line-10.01690
18Road Cum U/G Transmission Line-II0.01210.0121
19Underground Road Cum U/G Transmission Line0.02730
20Raod Cum U/G Transmission Line-III0.03950
21MD-VII0.01980
22Interconnection Point0.00990
Total 0.8223 0.0121
C. Maps of forest land proposed to be diverted
Division 1. : GHNP
  (i). Area of forest land proposed to be diverted(in ha.) : 0.8223   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.8223    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 180000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes   (a). Whether Project or a part thereof is located within a Protected Area ? : No   (ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project : Application yet to be submitted
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 1.75   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1Allotment Letter
2Fisheries NOC
3Wildlife NOC
4Gram Panchayat NOC
5IPH NOC
6Jiwa-II IA
7Joint Inspection Report
8Population Detail
9PWD NOC
10Revenue Department NOC
11FRA undertaking
12Undertaking for Submission of Transmission Plan
13Additional NPV Undertaking
14Certificate for the approval of the Project
15Certificate for minimum use of forest land
16Certificate for not change the alignment
17Check List No. 7
18Check List No. 8
19Check List No. 32
20Check List No. 4
21detail repot on voilation
22Layout Plan of Jiwa
23Muck dumping site, Plan and Estimated Cost
24NPV Undertaking
25Undertaking for CA
26Undertaking for cooking gas etc.
27Undertaking for submission of Wild Life NOC
281.75 MW Jiwa-II Letter to Behal Motors
29Jiwa-II TEC
30Reply Letter to Nodal Officer
31Non Availability of non forest land certificate
32Non Availability of non forest land certificate for Compensatory Afforestation
33reply to DFO 3 Oct. 2022
34TEC
35FCA Proposal in Single PDF
36Reply Letter to DFO Jan. 2023
37Reply to The DFO 21 Jan. 2023
38HPSEBL Letter
39Impacts of HPSEBL
40Layout Plan
41Power Generation Capacity
42Private Land NOC
43Private Land NOC
44undertaking for no trees in MD Site
45undertaking for SMCP
46undertaking for WLMP
47Up stream and dowen stream projects digital map
48Undertaking to stipulated E-Flow
49Reply Letter to DFO 5 May 2023
50Jiwa up and down stream, aerial distance map
51Jiwa Transmission Plan and Letter
52Reply Letter to DFO
53Power Evacuation Letter to Jiwa with Layout Plan
54detail of transmission line
55Reply Letter to DFO 16 Feb. 2024
56Power Evacuation Letter to Jiwa with Layout Plan
57Transmission Line Detail
58Letter Issued by DOE and HIMURJA
59Reply Letter to DFO 03 April 2024
60Reply letter to DFO June 2024