FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/146882/2021   (ii). Name of Project for which Forest Land is required : Banuala Baroond-II   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Banuala Baroond-II small Hydro Project(0.80MW) is a run of the river scheme which has been envisaged to utilize the water of Churku Nala for Power generation in Tehsil Churah Distt. Chamba HP.   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 789   (viii). Area of forest land proposed for diversion(in ha.): 0.603   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : NEW HYDEL POWER   (ii). Address1 : Village Gholti PO Sarol Tehsil and Distt. Chamba HP 176210   (iii). Address2 : NIL   (iv). State : Himachal Pradesh   (v). District : Chamba   (vi). Pin : 176312   (vii). Landmark : Near Sheep farm   (viii). Email address : newhydel.power@gmail.com   (ix). Landline Telephone No. : 0-   (x). Fax No. : 0-   (xi). Mobile No. : 7018349447   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Ved   (ii). Middle Name: Vyas   (iii). Last Name: Thakur   (iv). Gender: Male   (v). Designation: Partner   (vi). Address 1: Village Gholti PO Sarol tehsil and Distt. Chamba HP   (vii). Address 2: NIL   (viii). State: Himachal Pradesh   (ix). District: Chamba   (x). Tehsil: Chamba(T)   (xi). Pin: 176215   (xii). Landmark: Sheep Farm   (xiii). Email Address: namaneng.8000@gmail.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 7018349447   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chamba0.6030
Total0.6030
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chamba0.6030
Total0.6030
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Prabha0.6030
Total 0.603 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Weir Site0.00970
2Conveyance Channel0.01130
3Dumping Site-I0.03120
4D Tank Cum Forebay0.01620
5Penstock0.03360
6Dumping Site-II0.01520
7Tail race0.00850
8Power House Complex & switch yard0.06070
9Dumping Site-III0.01620
10Road0.14560
11Transmission Line0.25480
Total 0.603 0
C. Maps of forest land proposed to be diverted
Division 1. : Chamba
  (i). Area of forest land proposed to be diverted(in ha.) : 0.603   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.603    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 8   (iii). Temporary Employment(Number of person-days): 12000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 0.80   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1DC Certficate No Alternative land
2DC Certficate Non availability of CA land
3Certficate Non Violation
4Tripartite Agreement for name change
5Feasibilty Report approval Letter
6HPPWD Noc
7Panchayat Noc
8Joint Inspection report
9consent / Allotment Letter
10Undertaking to Pay CA cost
11Undertaking to Pay Addl NPV
12Undertaking to Pay NPV
13IPH NoC
14ECO SENSITIVE ZONE CERTIFICATE
15Reply Point Wise to EDS
16Beneficiary Certificate
17CL 7-No Private Land
18Road Muck Detail
19Land Suitability Certificate
20Reply of Observations to DFO
21Checklist-6 Detail of Forest Land
22Transmission Line ,Road and Pole Distance
23Reclamation and Muck Dumping Plan
24Evacuation Plan
25Proposal Documents (scanned) after Attending Observations
26Detail Note on project
27Minimum Use of Land certificate
28Reply of EDS to Nodal
29Form-A
30Proposal (Scanned)
31Fishery NOC
32Reply of EDSs to DFO Chamba
33Undertaking to Submit TEC & IA
34Reply (EDSs by IRO Shimla)5-2-23
35Component wise Land Detail
36EDSs (by IRO Shimla on 15-3-2023) Reply
37Reply of EDSs (by IRO Shimla )on 15-05-2023
38Reply of EDSs from IRO Shimla on 26-4-2024
39Reply of EDSs on 11-6-24 by Nodal Office