FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/HYD/14491/2015   (ii). Name of Project for which Forest Land is required : Kurpan-II 4.8 MW SHEP in distti. Kullu/Shimla   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This project lies on the left bank of kurpan nallah near Nirmand. Project comprises of Trench weir, Intake Structure, Power Channel, Feeder pipe Desilting tank, Head Race Tunnel, surge shaft, Penstock, Anchor blocks and saddle supports Power House, Tail race & Transmission line.   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 3938.17   (viii). Area of forest land proposed for diversion(in ha.): 2.8926   (ix). Non-forest land required for this project(in ha.): 0.3085   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : HIMPRABHA POWER PRIVATE LIMITED   (ii). Address1 : Village Karnguhi, PO. Panthera   (iii). Address2 : Tehsil Ghumarwin,Distt. Bilaspur   (iv). State : Himachal Pradesh   (v). District : Bilaspur   (vi). Pin : 174028   (vii). Landmark : Near Durga General Store   (viii). Email address : kmnhydrobharti@gmail.com   (ix). Landline Telephone No. : 1978-250289   (x). Fax No. : 1978-250289   (xi). Mobile No. : 9418451289   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Veena   (ii). Middle Name: NIL   (iii). Last Name: Kumari   (iv). Gender: Female   (v). Designation: Managing Director   (vi). Address 1: Village Karnguhi, PO. Panthera   (vii). Address 2: Tehsil Ghumarwin,Distt. Bilaspur   (viii). State: Himachal Pradesh   (ix). District: Bilaspur   (x). Tehsil: Ghumarwin(T)   (xi). Pin: 174028   (xii). Landmark: Near Durga General Store   (xiii). Email Address: kmnhydrobharti@gmail.com   (xiv). Landline Telephone No.: 1978-250289   (xv). Fax No.: 01978250289   (xvi). Mobile No.: 9418451289   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Ani at Luhri2.33070.2812
2.Rampur0.56190.0273
Total2.89260.3085
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Kullu2.33070.2812
1.Shimla0.56190.0273
Total2.89260.3085
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Nirmand1.35760.0859
2Gadej0.66190.0692
3Khakrola0.01160.1261
4Kumsu0.40340.0273
5Duttnagar0.45810
Total 2.8926 0.3085
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Weir Site0.06070
2Desilting tank0.0420
3Head Race Tunnel1.08210.0375
4Forebay0.04050
5Penstock0.2750.0886
6Power House00.068
7Adit 1&20.00240.0012
8Span-1&20.0210.0066
9Dumping Sites of Project0.39650.0793
10Dumping Sites of Transmission Line0.30
11Transmission Line Shimla0.26190.0273
12Transmission Line Kullu0.41050
Total 2.8926 0.3085
C. Maps of forest land proposed to be diverted
Division 1. : Ani at Luhri
  (i). Area of forest land proposed to be diverted(in ha.) : 2.3307   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.2.3307    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Rampur
  (i). Area of forest land proposed to be diverted(in ha.) : 0.5619   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.5619    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 15   (iii). Temporary Employment(Number of person-days): 100
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Certificate from Chief Secretary regarding non-availability of suitable non-forest/ revenue forest land
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 0   (ii). Total command area of the Project(in ha.): 0
Additional information Details
Documents
S.No Documents
Remarks
1Award Letter
2Non availability for compensatory forestation
3NOC Fisheries kullu
4NOC Fisheries shimla
5NOC IPH kullu
6NOC IPH shimla
7NOC Wild life kullu
8NOC Wild life shimla
9NOC HPSEB
10NOC PWD laying transmission line
11NOC ROW
12Joint inspection kullu
13Joint inspection shimla
14Non availability of non forest land kullu
15Non availability of non forest land shimla
16TEC
17Undertaking NPV kullu
18Undertaking NPV shimla
19Gram panchayat NOC
20Undertaking for geo-reference map
21observation reply
22certificate regarding Aerial Distance from Wildlife Sanctuary
23Reply Letter
24CERTIFICATE FOR MINIMUM USE OF FOREST LAND
25UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
26UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
27UNDERTAKING FOR PAYMENT OF ADDITIONAL NPV OF FOREST AREA
28Detail of Component wise Breakup
29Area detail of Underground Cable Line Kullu & Shimla
30NOC
31Reply Point No.3
32Guideline of Bare conductor Underground/ Insulated Cable