FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/HYD/144511/2021
(ii). Name of Project for which Forest Land is required :
C/o Hydro Electric Power Project Baggi (2x21 MW)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The proposed Baggi Power project will harness the head available between Pandoh Reservoir Level of Sundernagar Hydel Channel at Baggi. At present this hydro energy is dissipated through a stilling basin downstream of Baggi Control Works (BCW). The existing by-pass tunnel of dia 6.1 m will be used
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
28487
(viii). Area of forest land proposed for diversion(in ha.):
0.87
(ix). Non-forest land required for this project(in ha.):
18.5
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
CHIEF ENGINEER B S L (P BBMB)
(ii). Address1 :
Chief Engineer B S L (P) BBMB Sundernagar Distt. Mandi H.P
(iii). Address2 :
NIL
(iv). State :
Himachal Pradesh
(v). District :
Mandi
(vi). Pin :
175019
(vii). Landmark :
BBMB Colony
(viii). Email address :
cebsl@bbmb.nic.in
(ix). Landline Telephone No. :
1907-262333
(x). Fax No. :
1907-
(xi). Mobile No. :
9812012121
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central Government
A-3.
Details of Person Making Application
(i). First Name:
Satya
(ii). Middle Name:
Prakash
(iii). Last Name:
Sharma
(iv). Gender:
Male
(v). Designation:
Sr Executive Engineer
(vi). Address 1:
H C B G Division B S L P BBMB Colony Sundernagar
(vii). Address 2:
NIL
(viii). State:
Himachal Pradesh
(ix). District:
Mandi
(x). Tehsil:
Sundarnagar(T)
(xi). Pin:
175019
(xii). Landmark:
BBMB Colony
(xiii). Email Address:
xenhcbdsnrbbmb77@gmail.com
(xiv). Landline Telephone No.:
1907-262233
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9418096035
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Suket
0.87
18.5
Total
0.87
18.5
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Mandi
0.87
18.5
Total
0.87
18.5
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Khiuri Daum
0.87
0.1701
Total
0.87
0.1701
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Surge Shaft and Catcher Chamber
0.87
0
2
Protection works and working space for Catcher Cha
0
1.17
3
Project Road and Main Pandoh Baggi tunnel
0
0.27
4
Existing Baggi Control Works and Part of Proposed
0
1.81
5
Tail race Channel and Power House of Baggi HEP
0
1.01
6
Switchyard of Baggi HEP
0
12.09
7
Dumping site for Baggi HEP
0
2.15
Total
0.87
18.5
C.
Maps of forest land proposed to be diverted
Division 1. : Suket
(i). Area of forest land proposed to be diverted(in ha.) :
0.87
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.87
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
NA Because this site is final and suitable for Sur
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
640157
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
42
(ii). Total command area of the Project(in ha.):
0
(a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):
(b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No
Documents
Remarks
1
Undertaking for Document
2
Village Benefit
3
Justification Regarding IPH NOC
4
Approval Copy
5
Letter of Allotment
6
Non-Availability Non-Forest Land for Project
7
Undertaking for FRA
8
Award
9
Eco Sensitive Zone Certificate
10
REPLY LETTER
11
DETAIL OF COST
12
CLARIFICATION REGARDING DUMPING
13
Project Cost
14
Brief Note On Project
15
Joint Inspection Report
16
Muck Management Plan
17
Land Detail
18
List of HEPs
19
Power Evacuation
20
layout Plan
21
Techno Economic Clearance
22
Affidavit for Non-Forest land
23
Undertaking for Additional NPV
24
Undertaking for Payment of CA
25
Certificate for Minimum Use of forest land
26
Certificate for Water Intake
27
Undertaking for Payment of NPV
28
Undertaking for FRA
29
Combined PDF
30
Purpose wise breakup with Land detail
31
Reply with Annexure
32
Digital Map Showing Location of Existing/Approved/Proposed Proposals
33
TOPO Sheet Showing Location of Existing/Approved/Proposed Proposals
34
Hydro Power Potential of Beas River
35
Reply letter 01.04.2024
36
Detail of Beas RIver Basin
37
Reply 30.04.2024
Print