FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/GJ/TRANS/43664/2019
(ii). Name of Project for which Forest Land is required :
765 kV D/C Lakadia to Banaskantha Transmission Line
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The Ministry of Power, Government of India, initiated a scheme to establish transmission system for Bhuj-II, Dwaraka and Lakadia Solar/Wind energy potential zone and to evacuate the power to be generated at these RE sources under SPV named “Lakadia Banaskantha Transco limited with establishing 765 k
(iv). State :
Gujarat
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
70246
(viii). Area of forest land proposed for diversion(in ha.):
25.1315
(ix). Non-forest land required for this project(in ha.):
1155.0592
(x). Total period for which the forest land is proposed to be diverted(in years):
35
A-2.
Details of User Agency
(i). Name :
LAKADIA BANASKANTHA TRANSCO LIMITED
(ii). Address1 :
House no 22, Odhav Vandana-4, Airport Road, Bhuj
(iii). Address2 :
NIL
(iv). State :
Gujarat
(v). District :
kutch
(vi). Pin :
370001
(vii). Landmark :
Airport
(viii). Email address :
lbtltransco@gmail.com
(ix). Landline Telephone No. :
79-25556169
(x). Fax No. :
79-
(xi). Mobile No. :
6359965931
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
Sukh
(ii). Middle Name:
NIL
(iii). Last Name:
Ram
(iv). Gender:
Male
(v). Designation:
Associate General Manager
(vi). Address 1:
House no 22, Odhav Vandana-4, Airport Road, Bhuj
(vii). Address 2:
NIL
(viii). State:
Gujarat
(ix). District:
kutch
(x). Tehsil:
Bhuj
(xi). Pin:
370001
(xii). Landmark:
Airport
(xiii). Email Address:
mkhanna31@gmail.com
(xiv). Landline Telephone No.:
79-25556169
(xv). Fax No.:
NIL
(xvi). Mobile No.:
6359965931
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kutch-East
15.104
421.5113
2.
Kutch SF
0.2903
0
3.
Patan
8.5297
408.7302
4.
Banaskantha SF
1.2075
324.8177
Total
25.1315
1155.0592
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
kutch
15.3943
421.5113
1.
Patan
8.5297
408.7302
3.
Banaskantha
1.2075
324.8177
Total
25.1315
1155.0592
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
SHIVLAKHA
0
28.3434
2
GOVINDPUR
0
7.2675
3
CHITROD
0
14.9175
4
DEDARWA
0.2903
28.6915
5
KHIRAI
0
10.854
6
SAI
0
30.8347
7
TINDALWA
0
22.6649
8
KIDIYANAGAR
0
41.5467
9
BHUTAKIYA
0
34.7638
10
BHIMASAR
0
19.5774
11
HAMIRPUR MOTI
0
19.8856
12
MORA
0
52.5161
13
SANWA
15.104
47.2864
14
KUTCH CREEK AREA
0
62.3618
15
MADHUTRA
0
32.7451
16
VAUVA
0
23.0515
17
DATRANA
0
24.7903
18
DHOKAVADA
0
9.1625
19
BAKUTRA
0
37.074
20
BAVARDA
0
8.8403
21
BABRA
0
29.2214
22
PATANKA
4.3885
24.2388
23
DALDI
3.9867
27.8862
24
JAMVADA
0
3.0692
25
KORDA
0
34.988
26
RAMPURA
0
11.3247
27
GADHA
0
18.6695
28
JHANDALA
0
24.1967
29
DAHISAR
0.1545
25.7937
30
GANJESWAR
0
15.6816
31
SATHALI
0
22.4485
32
LOTIYA
0
20.0881
33
THIKARIA
0
15.4602
34
GOSAN
0
18.8436
35
CHICHODRA
0.2713
14.6472
36
CHACHASNA
0.1251
16.0497
37
WARSARA
0.1868
25.7963
38
TERVADA
0
29.1095
39
FATEPURA
0
2.814
40
KASHIPURA, NATHPURA, KUDVA
0
21.6839
41
ISARVA
0
9.6841
42
RAJPUR
0
5.9898
43
KANTHERIYA
0.1551
10.9303
44
KATERIYA
0
14.9259
45
NEKOI
0
24.4803
46
PADARDI
0.1872
19.0998
47
CHIMANGARH
0
6.4187
48
RATANGARH
0
22.0373
49
RAVIYANA
0
8.6175
50
KHIMANA
0.282
30.1816
51
KHODLA
0
12.7414
52
MUDETHA
0
30.7667
Total
25.1315
1155.0592
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
765 KV D/C Lakadia-Banaskantha Transmission Line
25.1315
1155.0592
Total
25.1315
1155.0592
C.
Maps of forest land proposed to be diverted
Division 1. : Kutch-East
(i). Area of forest land proposed to be diverted(in ha.) :
15.104
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
15.104
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Patan
(i). Area of forest land proposed to be diverted(in ha.) :
8.5297
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Three
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.3017
View File
2.
0.1545
View File
3.
8.0735
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : Banaskantha SF
(i). Area of forest land proposed to be diverted(in ha.) :
1.2075
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Five
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.2713
View File
2.
0.3119
View File
3.
0.1551
View File
4.
0.1872
View File
5.
0.282
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 4. : Kutch SF
(i). Area of forest land proposed to be diverted(in ha.) :
0.2903
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.2903
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
135
(iii). Temporary Employment(Number of person-days):
1566000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
Yes
(b). Status of approval of the Supreme Court :
Approval under cons
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application under process
(a). Date of submission of proposals :
13 Jan 2020
(b). Current status :
NIL
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
For laying of transmission lines
Additional information Details
Documents
S.No
Documents
Remarks
1
Undertaking for minimum felling of trees
2
Undertaking for minimum use of forest land
3
Undertaking for no violation
4
Undertaking for payment of cost of trees
5
Undertaking for payment of NPV
6
Undertaking for protected area
7
Undertaking for additional conditions
8
Undertaking for payment of CA cost
9
Undertaking for archaeological
10
Undertaking for FRA compliance
11
Letter reg. revision of proposal
12
F.R.A. Certificates