FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/CG/OFC/45529/2020
(ii). Name of Project for which Forest Land is required :
BharatNet Project Phase-II Bijapur Forest Division
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
BharatNet project which is a GOI initiative. Under this project, connectivity will be provided at 5,987 GPs & 85 Blocks through optic fibre cable laying of approximately 32,466 KM. The laying of Optical Fiber cable of 32,466 KM will involve 26 districts across the State.
(iv). State :
Chhattisgarh
(v). Category of the Proposal :
Optical Fibre Cable
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
1789
(viii). Area of forest land proposed for diversion(in ha.):
8.706
(ix). Non-forest land required for this project(in ha.):
2.717
(x). Total period for which the forest land is proposed to be diverted(in years):
20
A-2.
Details of User Agency
(i). Name :
CHIPS
(ii). Address1 :
Chhattishgarh Infotech Promotion Society
(iii). Address2 :
3rd Floor,State Data Center Building,Civil Lines Raipur Chhattishgarh
(iv). State :
Chhattisgarh
(v). District :
Raipur
(vi). Pin :
492001
(vii). Landmark :
Opp.New Circuit House
(viii). Email address :
ceochips@nic.in
(ix). Landline Telephone No. :
771-4014158
(x). Fax No. :
771-4066205
(xi). Mobile No. :
9632444223
(xii). Website (if any) :
www.chips.gov.in
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Ravindra
(ii). Middle Name:
Kumar
(iii). Last Name:
Pateria
(iv). Gender:
Male
(v). Designation:
JCEO
(vi). Address 1:
CHiPS,2nd Floor,SDC Building, Civil Line Raipur
(vii). Address 2:
NIL
(viii). State:
Chhattisgarh
(ix). District:
Raipur
(x). Tehsil:
NIL
(xi). Pin:
492001
(xii). Landmark:
New Circuit house
(xiii). Email Address:
vivek.chandrakar@cgchips.in
(xiv). Landline Telephone No.:
771-4014158
(xv). Fax No.:
07714066205
(xvi). Mobile No.:
9630742261
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Inprinciple
FP/CG/Others/32736/2018
F-7-3/2018/10-2,Raipur Dated 26.05.2018
1.222
1.222
26 May 2018
2
Inprinciple
FP/CG/Others/28811/2017
F-5-10/2018/10-2,Raipur Dt 19/06/2018
2.488
2.488
19 Jun 2018
3
Inprinciple
FP/CG/Others/27433/2017
F-7-3/2018/10-2,Raipur Dt.26.05.2018
0.854
0.854
26 May 2018
4
Inprinciple
FP/CG/Others/27427/2017
F-5-15/2018/10-2,Raipur Dt.28/04/2018
1.588
1.588
28 Apr 2018
5
Inprinciple
FP/CG/Others/27425/2017
F-5-11/2018/10-2,Raipur Dt.28/04/2018
3.959
3.959
28 Apr 2018
6
Inprinciple
FP/CG/Others/27423/2017
F-5-12/2018/10-2,Raipur Dt.11/06/2018
2.014
2.014
11 Jun 2018
7
Inprinciple
FP/CG/Others/27422/2017
F-5-9/2018/10-2,Raipur 28/04/2018
3.064
3.064
28 Apr 2018
8
Inprinciple
FP/CG/Others/27420
F-5-08/2018/10-2,Raipur Dt.28/04/2018
2.383
2.383
28 Apr 2018
9
Inprinciple
FP/CG/Others/27383/2017
F-5-16/2018/10-2,Raipur Dt. 28/04/2018
0.947
0.947
28 Apr 2018
Total
18.519
18.519
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bijapur
8.706
2.717
Total
8.706
2.717
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bijapur
8.706
2.717
Total
8.706
2.717
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Ambeli
0
0.038
2
Badetungali
0
0.002
3
Bedre
0
0.008
4
BODLI
0
0.033
5
Cheramangi
0.178
0
6
Chinakwalli
0.067
0
7
Darbha
0
0.078
8
Dharavaram
0.113
0
9
Egpalli
0.491
0
10
Fulgatta
0.081
0
11
Gadamali
0
0.071
12
Galgam
0.211
0
13
Gilgicha
0.379
0
14
Gudma
0
0.053
15
Jaiwaram
0
0.051
16
Jangla
0.271
0.033
17
Karkeli
0
0.038
18
Kodoli
0
0.004
19
Kompalli
0
0.002
20
Kottapal
0.122
0
21
Mangalnar
0
0.006
22
Mankeli
0.09
0
23
Matwada
0
0.039
24
Mirtur
0.028
0.031
25
Nelasnar
0.219
0
26
Nukanpal
0.842
0
27
Painkram
0
0.002
28
Patarpara
0
0.027
29
Phulgatta
0
0.008
30
Pinkonda
0.473
0.068
31
Punnur
0.074
0
32
Pusnar
0.656
0
33
Somanpalli
0
0.031
34
Tekmetla
0.231
0
35
Temrubhata
0.704
0
36
Uskapatnam
0
0.013
37
Usur
0.391
0.054
38
Awapalii
0.322
0.257
39
Bhairamgarh
0.514
0.045
40
Dhanora
0.172
0.124
41
Dugaiguda
0.187
0.225
42
Ilmidi
0.004
0.055
43
Kanhaiguda
0.095
0.487
44
Karemrka
0.323
0.124
45
Pawrel
0.189
0.535
46
Saknapalli
0.29
0.083
47
Semaldodi
0
0.038
48
Tindodi
0
0.054
49
Naimed
0.989
0
Total
8.706
2.717
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
ofc
8.706
2.717
Total
8.706
2.717
C.
Maps of forest land proposed to be diverted
Division 1. : Bijapur
(i). Area of forest land proposed to be diverted(in ha.) :
8.706
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
8.706
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
NIL
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
10
(iii). Temporary Employment(Number of person-days):
20
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Laying of telephone/optical fibre lines
Additional information Details
Documents
S.No
Documents
Remarks
1
Project Approval Copy
2
LOI Issued To TPL
3
Letter to Collector FRA & NOC
4
DD against Registration and processing fees
5
Forest Area Statement
6
Lidar/DGPS Survey Report
7
Letter regarding EDS by nodal Officer
Print