FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/CG/MIN/41389/2019
(ii). Name of Project for which Forest Land is required :
GEVRA OPENCAST PROJECT
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Diversion of additional 94.293 Ha. of Revenue Forest Land for capacity enhancement of Gevra OCP from 35 to 70 MTY.
(iv). State :
Chhattisgarh
(v). Category of the Proposal :
Mining
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
1181640
(viii). Area of forest land proposed for diversion(in ha.):
94.293
(ix). Non-forest land required for this project(in ha.):
4687.505
(x). Total period for which the forest land is proposed to be diverted(in years):
30
A-2.
Details of User Agency
(i). Name :
SOUTH EASTERN COALFIELDS LTD
(ii). Address1 :
Post Box No. 60 Seepat Road Bilaspur Chhattisgarh
(iii). Address2 :
NIL
(iv). State :
Chhattisgarh
(v). District :
Bilaspur
(vi). Pin :
495006
(vii). Landmark :
SECL HQ
(viii). Email address :
seclforest@rediffmail.com
(ix). Landline Telephone No. :
7752-246351
(x). Fax No. :
7752-246351
(xi). Mobile No. :
9425531622
(xii). Website (if any) :
www.secl.gov.in
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
Swarup
(ii). Middle Name:
Kumar
(iii). Last Name:
Mohanty
(iv). Gender:
Male
(v). Designation:
GENERAL MANAGER
(vi). Address 1:
Office of the General Manager GEVRA AREA
(vii). Address 2:
NIL
(viii). State:
Chhattisgarh
(ix). District:
Korba
(x). Tehsil:
NIL
(xi). Pin:
495452
(xii). Landmark:
GM Office Gevra Area
(xiii). Email Address:
noenvgevra@gmail.com
(xiv). Landline Telephone No.:
7815-275430
(xv). Fax No.:
7815275434
(xvi). Mobile No.:
9425531732
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Apporved
8-33/2005-FC
8-33/2005-FC
100.898
100.898
20 Oct 2006
05 May 2008
2
Apporved
8-79/2006-FC
8-79/2006-FC
564.885
564.885
20 Oct 2006
20 Apr 2015
3
Apporved
8-77/2006-FC
8-79/2006-FC
192.046
192.046
20 Oct 2006
20 Apr 2015
4
Apporved
8-81/2006-FC
8-81/2006-FC
46.198
46.198
20 Oct 2006
20 Apr 2015
5
Approved
FP/CG/MIN/962/2005
8-CHA033/2005-FCD
100.898
100.898
20 Oct 2006
05 May 2008
Total
1004.925
1004.925
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Katghora
94.293
4687.505
Total
94.293
4687.505
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Korba
94.293
4687.505
Total
94.293
4687.505
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Gevra
81.38
393.419
2
khodri
12.913
11.023
3
Mangaon
0
256.127
4
Pondi
0
254.348
5
Bareli
0
474.886
6
Beltikiri
0
114.076
7
Gevra (old)
0
219.085
8
Dipka
0
119.47
9
Dhurena
0
145.277
10
Bahanpath
0
108.605
11
Bhathora
0
141.707
12
Raliya
0
142.21
13
Bhilaibazar
0
73.462
14
Ghatmuda
0
249.656
15
Junadih
0
296.762
16
Kosmunda
0
655.5
17
Binjhra
0
352.833
18
Jhingatpur
0
2.023
19
Amgaon
0
329.745
20
Naraibodh
0
248.714
21
Salora
0
21.112
22
Barbhatha
0
21.846
23
Pandripani
0
42.925
24
Churail
0
12.694
Total
94.293
4687.505
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Mining Quarry
94.168
2427.814
2
Mine Infratructure
0.125
1180.227
3
External OB Dump
0
480
4
Other (Safety Zone etc)
0
599.464
Total
94.293
4687.505
C.
Maps of forest land proposed to be diverted
Division 1. : Katghora
(i). Area of forest land proposed to be diverted(in ha.) :
94.293
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
Two
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
81.38
View File
2.
12.913
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
4391
(iii). Temporary Employment(Number of person-days):
500
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
Yes
(a). Total Number of families :
2046
(b). Number of Scheduled Caste families :
251
(c). Number of Schedule Tribes families :
706
(d). Number of other families :
1089
(ii). Copy of Rehabilitation and Resettlement Plan:
(a). Copy of approval to Ministry of Tribal Affairs,Government of India to Rehabilitation and Resettlement:
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
Yes
(a). Status of the Environmental Clearance to the Project:
EC obtained
(b). Environmental Clearance File No.:
J-11015/85/2010-IA.II (M)
(c). Copy of Environmental Clearance to the Project:
(d). Date of grant of Environmental Clearance to the Project:
2020-06-04
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
M.
Mining Details
M-1.
Details of Mineral Concessions
(i). Whether the forest land is aquired under Coal Bearing Areas Act:
Yes
(a). Total area of the mining lease(in ha.):
4781.798
(b). Area of forest land located in the mining lease(in ha.):
1110.705
M-2.
Details of Mining Plan
(i). Date of approval of mining plan:
05 Mar 2016
(ii). Approval authority:
COAL INDIA LTD BOARD
(iii). Copy of approval of mining plan:
(iv). Copy of approved mining plan:
(v). Nature of mining (underground/opencast):
Opencast
(vi). Copy of the detailed land use plan in 1:4,000 scale prepared by using GPS or Total Station :
(vii). Copy of map of the outer boundary of mining lease area:
View file
M-3.
Details of prospecting undertaken to assess mineral reserves
(i). Whether detailed prospecting to assess mineral reserve in the lease has been undertaken:
No
M-4.
Details of extension (if any) of original prospecting licence issued in the past
(i). Whether detailed prospecting to assess mineral reserve in the lease has been undertaken:
No
M-5.
Brief details of prospecting activities undertaken in the mining lease :
M-5.2
Estimated Reserve along with accuracy and confidence level
Estimated Reserve along with accuracy and confidence level
Minerals
Estimated Reserve
(million tones)
% accuracy (+ -)
% confidence level
Estimated Reserve
(million tones)
% accuracy (+ -)
Estimated mineral reserve
at the end of mining lease(million tons.)
NIL
M-6.
Details of approval under the Forest (Consevation) Act,1980 obtained for undertaking prospecting activities in the forest land located in the mining lease
(i).Whether approval under the Forest (Conservation) Act, 1980 for undertaking prospecting activities in the forest land located in the mining lease have been obtained
No
Details of approval under the Forest(Consevation) Act,1980
S.no
MoEF File No
Date of approval
Area of forest land diverted(in ha.)
From Date
To Date
NIL
M-7.
Mineral wise details
(i). No. of minerals:
One
Mineral wise details
Minerals
Estimated reserve in
non forest land(million tons.)
Estimated reserve
in forest land(million tons.)
Estimated annual
extraction(million tons.)
Estimated life
of mine(Yrs.)
Total estimated extraction during
mining lease period(million tons.)
Estimated mineral reserve
at the end of mining lease(million tons.)
Coal and Lignite
872.88
258.11
70
17
1130.99
0
M-7.1
Proposed use of the minerals proposed to be raised from the mining lease
(i). Proposed use of the minerals proposed to be raised from the mining lease:
Non captive
(ii).Copy note containing details of the plan for the transportation of the minerals proposed to be raised from the mining lease:
Additional information Details
Documents
S.No
Documents
Remarks
1
Sub Block Level Committee certificate along with supporting documents
2
Verified copy of proposed Forest land (Khasara wise Details)
3
Mine Plan
4
Letter made to collector for issuance of NOC under FCA 1980 & FRA 2006
5
Reply to EDS dt: 29.11.2019
6
Land break up of 4781.798 ha.
7
Diversion of Road details
8
Land Acquisition details as per the Project report of Gevra Expansion Project (35-70 MTPA)
9
Land Notification & details of Gevra OCP
10
Gevra Cardinal
11
Submission of DD for Registration & processing of application
12
Reply to EDS dt 28.10.2020
13
DGPS Report
14
Reply to query dt 19.01.2022
15
Certified CA report of Gariyaband & Pali
16
Reply to query dt:07.07.2023
Print