FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/AS/MIN/23089/2016
(ii). Name of Project for which Forest Land is required :
Drilling Location MKD
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Oil India Limited intends to drill Loc. MKD located in the Mechaki PML area. The identified location lies within the Mechaki reserve forest and in western boundary of the Reserve Forest. Once hydrocarbon is established in this area, it is expected to enhance the cumulative oil production of OIL.
(iv). State :
Assam
(v). Category of the Proposal :
Mining
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
5400
(viii). Area of forest land proposed for diversion(in ha.):
3.545
(ix). Non-forest land required for this project(in ha.):
0.73
(x). Total period for which the forest land is proposed to be diverted(in years):
20
A-2.
Details of User Agency
(i). Name :
OIL INDIA LIMITED
(ii). Address1 :
OIL INDIA LIMITED DULIAJAN District : Dibrugarh
(iii). Address2 :
NIL
(iv). State :
Assam
(v). District :
Dibrugarh
(vi). Pin :
786602
(vii). Landmark :
Adjacent to Police Station
(viii). Email address :
safety@oilindia.in
(ix). Landline Telephone No. :
374-2800542
(x). Fax No. :
374-2801796
(xi). Mobile No. :
9435039020
(xii). Website (if any) :
www.oilindia..com
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
Ajit
(ii). Middle Name:
Chandra
(iii). Last Name:
Haloi
(iv). Gender:
Male
(v). Designation:
CGM(HSE)
(vi). Address 1:
Safety & Environment Department , Oil India Limited, Duliajan
(vii). Address 2:
NIL
(viii). State:
Assam
(ix). District:
Dibrugarh
(x). Tehsil:
NIL
(xi). Pin:
786602
(xii). Landmark:
Near Union Office
(xiii). Email Address:
safety@oilindia.in
(xiv). Landline Telephone No.:
374-2800542
(xv). Fax No.:
03742801796
(xvi). Mobile No.:
9435185558
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Doomdooma
3.545
0.73
Total
3.545
0.73
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Tinsukia
3.545
0.73
Total
3.545
0.73
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
NIL
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Plinth Area
2.541
0
2
Approach Road
1.004
0.73
Total
3.545
0.73
C.
Maps of forest land proposed to be diverted
Division 1. : Doomdooma
(i). Area of forest land proposed to be diverted(in ha.) :
3.545
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
Two
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
2.541
View File
2.
1.004
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
15
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
Yes
(a). Status of the Environmental Clearance to the Project:
EC under process
(ii). Environmental Clearance File No.:
A-J-11011/105/2017-IA-II(I)
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
No
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application yet to be submitted
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
M.
Mining Details
M-1.
Details of Mineral Concessions
(i). Whether the forest land is aquired under Coal Bearing Areas Act:
No
(a). Reference number of Letter of Intent for grant of mining lease.(approval letter of the State Mines and Geology Department):
PEM.93/2003/161, dated Dispur, 16.06.08
(b). Date of issue of the Letter of Intent(LOI) for grant of mining lease:
16 Jun 2008
(c). Copy the Letter of Intent(LOI):
(d). Total area of the mining lease(in ha.):
19500
(e). Area of forest land located in the mining lease(in ha.):
5538
M-2.
Details of Mining Plan
(i). Date of approval of mining plan:
16 Jun 2008
(ii). Approval authority:
Under Secretary to the Govt of Assam
(iii). Copy of approval of mining plan:
(iv). Copy of approved mining plan:
(v). Nature of mining (underground/opencast):
Underground
(a).Copy of 3D subsidence analysis report:
(vi). Copy of the detailed land use plan in 1:4,000 scale prepared by using GPS or Total Station :
(vii). Copy of map of the outer boundary of mining lease area:
View file
M-3.
Details of prospecting undertaken to assess mineral reserves
(i). Whether detailed prospecting to assess mineral reserve in the lease has been undertaken:
Yes
prospecting undertaken to assess mineral reserves
S.no
Designation of authority responsible
for grant of the original propecting license
Date of grant of prospecting licence
Period of validity of extension prospecting licence From date
Period of validity of extension prospecting licence To date
Copy of prospecting licence
1
Under Secretary to the Govt. of Assam
08 Apr 2008
19 May 2003
18 May 2023
M-4.
Details of extension (if any) of original prospecting licence issued in the past
(i). Whether detailed prospecting to assess mineral reserve in the lease has been undertaken:
No
M-5.
Brief details of prospecting activities undertaken in the mining lease :
(i). Detail of prospecting activity under taken in the mining lease:
Two (2) wells have been already drilled in Mechaki PML of OIL
M-5.1
Details of bore holes drilled for prospecting :
Bore holes drilled for prospecting
S.no
No. of Bore holes (in forest land)
Diameters(in inch.) forest land
No. of Bore holes (in non-forest land)
Diameters(in inch.) non-forest land
1
0
0
2
17.5
M-5.2
Estimated Reserve along with accuracy and confidence level
Estimated Reserve along with accuracy and confidence level
Minerals
Estimated Reserve
(million tones)
% accuracy (+ -)
% confidence level
Estimated Reserve
(million tones)
% accuracy (+ -)
% confidence level
Petroleum and Natural Gas
2.125
100
100
0
100
100
M-6.
Details of approval under the Forest (Consevation) Act,1980 obtained for undertaking prospecting activities in the forest land located in the mining lease
(i).Whether approval under the Forest (Conservation) Act, 1980 for undertaking prospecting activities in the forest land located in the mining lease have been obtained
No
Details of approval under the Forest(Consevation) Act,1980
S.no
MoEF File No
Date of approval
Area of forest land diverted(in ha.)
From Date
To Date
NIL
M-7.
Mineral wise details
(i). No. of minerals:
One
Mineral wise details
Minerals
Estimated reserve in
non forest land(million tons.)
Estimated reserve
in forest land(million tons.)
Estimated annual
extraction(million tons.)
Estimated life
of mine(Yrs.)
Total estimated extraction during
mining lease period(million tons.)
Estimated mineral reserve
at the end of mining lease(million tons.)
Petroleum and Natural Gas
0
2.125
0.032
20
0.637
1.49
M-7.1
Proposed use of the minerals proposed to be raised from the mining lease
(i). Proposed use of the minerals proposed to be raised from the mining lease:
Non captive
(ii).Copy note containing details of the plan for the transportation of the minerals proposed to be raised from the mining lease:
Additional information Details
Documents
S.No
Documents
Remarks
1
List of Annexure
2
Reply to the EDS query submitted on 08.06.17
3
A copy of PML grant letter by the State Mines & Mineral Dept. of Assam.
4
A copy of PML grant letter by MoPNG
5
An undertaking for payment of NPV in non-judicial stamp paper
6
An undertaking for payment of C.A. in non-judicial stamp paper
7
An undertaking that the survey was done by DGPS/Total Station in non-judicial stamp Paper
8
An undertaking that the project area is the barest minimum and shall not be changed
9
TOR application of Mechaki block
10
FRA 2006 Clearance Certificate for Loc. MKD
11
Proposal for forest diversion was submitted by Oil India Limited vide letter No. Land/2/MKD-303/2010 dated 14.06.2010 for location MKD in Mechaki Area in legacy regime
12
Inspection of the same was completed by DFO, Dumdooma and report (Part II) submitted on 12.03.2011.
13
Site inspection was further carried out by Conservator Forest, EAC, Jorhat on 31.07.12.
14
Dy.Secy. ,Govt.of Assam after approval forwarded the proposal to RO, MoEF &CC, Shillong vide letter No. FRS.80/2015/64 dated 21.08.2015
15
FC proposal approved by Addl.PCCF and Nodal Officer vide letter No. FG.27/Nodal/proposal/drilling location MKD dated 21.07.2015 and forwarded to Addl. Chief Secy, Govt.of Assam.
16
17
18
FC submission Letter under Mining Category
19
Undertaking for inability to upload KML file.
20
Toposheet
21
Geo reference map
22
EDS reply against query on 15.07.17 and submitted by OIL on 03.08.2017
23
EDS reply against query on 14.08.17 and submitted by OIL on 05.12.17
24
EDS reply by OIL on 26.12.17 against EDS query on 15.12.17
25
EDS replied on 12.02.2018 against query on 05.01.2018
26
EDS replied on 27.02.2018 against query on 21.02.2018
Print