FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/AR/TRANS/35448/2018   (ii). Name of Project for which Forest Land is required : Construction of 132kV T/L from Namsai to Miao under Comprehensive Scheme for Strengthening of Transmission and Distribution in Arunachal Pradesh   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Proposed 132 kV TL from Namsai to Miao is a Sub Project which is conceived under the Govt of India ambitious project namely Comprehensive Scheme for Strengthening of T&D system in Arunachal Pradesh ( A central sector project funded by GoI and being implemented by POWERGRID)   (iv). State : Arunachal Pradesh   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 7000   (viii). Area of forest land proposed for diversion(in ha.): 110.817   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 75
A-2. Details of User Agency
  (i). Name : DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH   (ii). Address1 : BIDYUT BHAWAN, ZIRO POINT TINIALI,   (iii). Address2 : ITANAGAR, ARUNACHAL PRADESH   (iv). State : Arunachal Pradesh   (v). District : Papum Pare   (vi). Pin : 791111   (vii). Landmark : NEAR ZIRO POINT TINIALI   (viii). Email address : baishyasantana@gmail.com   (ix). Landline Telephone No. : 360-2257301   (x). Fax No. : 360-   (xi). Mobile No. : 9436255253   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Nido   (ii). Middle Name: NIL   (iii). Last Name: Taka   (iv). Gender: Male   (v). Designation: EE   (vi). Address 1: Miao Electrical Division, DoP, Miao   (vii). Address 2: NIL   (viii). State: Arunachal Pradesh   (ix). District: Changlang   (x). Tehsil: Miao Circle   (xi). Pin: 792122   (xii). Landmark: NIL   (xiii). Email Address: miao_electricaldivision@yahoo.com   (xiv). Landline Telephone No.: 360-2257301   (xv). Fax No.: NIL   (xvi). Mobile No.: 8753993011   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Nampong Forest Division,Jairampur58.410
2.Namsai Forest Division,Namasi52.4070
Total110.8170
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Changlang110.8170
Total110.8170
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1PAGODA82.210
Total 82.21 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1RIGHT OF WAY OF 132kV TL( NAMPONG DIVISION)58.410
2RIGHT OF WAY OF 132kV TL( NAMSAI DIVISION)52.4070
Total 110.817 0
C. Maps of forest land proposed to be diverted
Division 1. : Nampong Forest Division,Jairampur
  (i). Area of forest land proposed to be diverted(in ha.) : 58.41   (ii). Nature of the Project: Linear   (b). No. of Segments : Three
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.17.6    View File
2.22.9    View File
3.17.91    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Namsai Forest Division,Namasi
  (i). Area of forest land proposed to be diverted(in ha.) : 52.407   (ii). Nature of the Project: Linear   (b). No. of Segments : Two
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.48.217    View File
2.4.19    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 15   (iii). Temporary Employment(Number of person-days): 80000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : Yes
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Central Govt. Project
Additional information Details
Documents
S.No Documents
Remarks
1STATEMENT OF FOREST LAND PROPOSED TO BE DIVERTED
2UNDERTAKING FOR COMPENSATORY AFFORESTATION
3COST BENEFIT ANALYSIS
4UNDERTAKING FOR PAYMENT OF NPV AND ADDITIONAL NPV
5UNDERTAKING FOR SUBMISSION OF FOREST RIGHTS ACT COMPLIANCE CERTIFICATE
6JUSTIFICATION OF LOCATING THE PROJECT IN FOREST LAND
7UNDERTAKING OF SURVEY DONE BY TOTAL STATION
8MAP SHOWING ALTERNATIVE ROUTES STUDIED
9MAP SHOWING FOREST AREA UNDER NAMSAI DIVISION
10MAP SHOWING FOREST AREA UNDER NAMPONG DIVISION
11BASIC COMPONENT OF A TRANSMISSION LINE
12GOVT. OF INDIA APPROVAL AGAINST THE PROJECT
13MoU BETWEEN POWERGRID AND DEPARTMENT OF POWER, ARUNACHAL PRADESH
14TOWER DETAILS OF NAMSAI TO MIAO T/L UNDER NAMSAI AND NAMPONG FOREST DIVISION
15TOWER DIAGRAM
16PROPOSED ROUTE ALIGNMENT OF 132kV NAMSAI TO MIAO T/L
17Tower Diagram
183D Diagram