FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/AR/TRANS/145264/2021
(ii). Name of Project for which Forest Land is required :
Construction of 132kV Transmission line from Changlang to Jairampur under Comprehensive Scheme for Strengthening of Transmission and Distribution System in Arunachal Pradesh
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The Proposed 132 kV TL from Changlang to Jairampur is a Sub Project which is conceived under the Govt of India ambitious project namely Comprehensive Scheme for Strengthening of T&D system in Arunachal Pradesh ( A central sector project funded by GoI and being implemented by POWERGRID)
(iv). State :
Arunachal Pradesh
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
7000
(viii). Area of forest land proposed for diversion(in ha.):
136.458
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
75
A-2.
Details of User Agency
(i). Name :
DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH
(ii). Address1 :
BIDYUT BHAWAN, ZIRO POINT TINIALI,
(iii). Address2 :
ITANAGAR, ARUNACHAL PRADESH
(iv). State :
Arunachal Pradesh
(v). District :
Papum Pare
(vi). Pin :
791111
(vii). Landmark :
NEAR ZIRO POINT TINIALI
(viii). Email address :
baishyasantana@gmail.com
(ix). Landline Telephone No. :
360-2257301
(x). Fax No. :
360-
(xi). Mobile No. :
9436255253
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
NIDO
(ii). Middle Name:
NIL
(iii). Last Name:
TAKA
(iv). Gender:
Male
(v). Designation:
EE
(vi). Address 1:
DEPARTMENT OF POWER, OFFICE OF THE EXECUTIVE ENGINEER, MIAO ELECTRICAL DIVISION
(vii). Address 2:
NIL
(viii). State:
Arunachal Pradesh
(ix). District:
Changlang
(x). Tehsil:
Miao Circle
(xi). Pin:
792122
(xii). Landmark:
NIL
(xiii). Email Address:
miao_electricaldivision1@yahoo.com
(xiv). Landline Telephone No.:
360-2257301
(xv). Fax No.:
NIL
(xvi). Mobile No.:
8753993011
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Changlang S/F Division, Changlang
59.8482
0
2.
Nampong Forest Division,Jairampur
76.6098
0
Total
136.458
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Changlang
136.458
0
Total
136.458
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Yantang
5.57
0
2
Waltom
7.96
0
3
Phangtip
4.26
0
4
Longchuk
2.5
0
5
Nodi par
10.86
0
6
Sohe Laktong
4.42
0
7
Longlung
8.85
0
8
Kengkhu
11.17
0
9
Jungmaisung
7.17
0
10
Chinook
0.78
0
11
Khuchep 1
2.78
0
12
Khuchep 2
3.46
0
13
Jonglim Pothar
7.14
0
14
Forest area
13.011
0
15
Manmao Town
6.65
0
16
Lungsang
5.13
0
17
Old Kamlao
4.57
0
18
New Kamlao
14.86
0
19
Hetlong
5.67
0
Total
126.811
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
ROW of 132kV (USF Changlang)
59.8482
0
2
ROW of 132kV (USF Nampong)
38.1915
0
3
ROW of 132kV (Khamtang RF)
25.4178
0
4
ROW of 132kV (Honkap RF)
13.0005
0
Total
136.458
0
C.
Maps of forest land proposed to be diverted
Division 1. : Changlang S/F Division, Changlang
(i). Area of forest land proposed to be diverted(in ha.) :
59.8482
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
59.8482
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Nampong Forest Division,Jairampur
(i). Area of forest land proposed to be diverted(in ha.) :
76.6098
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Three
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
38.1915
View File
2.
25.4178
View File
3.
13.0005
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
15
(iii). Temporary Employment(Number of person-days):
80000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
Yes
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Central Govt. Project
Additional information Details
Documents
S.No
Documents
Remarks
1
Undertaking for payment of NPV
2
Undertaking for payment of additional NPV
3
Undertaking for protection and regeneration of safety zone
4
Undertaking for payment of cost of compensatory afforestation
5
Undertaking for minimum use of forest land
6
Undertaking for compliance of FRA
7
Undertaking for survey done by TS
8
Undertaking for minimum felling of trees
9
Undertaking for payment of extraction cost
10
Statement of forest land
11
Cost benefit analysis
12
Justification for selection of proposed route
13
Comparative statement of three alternatives
14
GoI sanction order
15
MoU between POWERGRID & Department of Power
16
GPS coordinates of the proposed transmission line
17
3D Map of the proposed transmission line
18
3D view of the 132kV TL (ROW & clearance)
19
Proposed route map of 132kV Transmission line from Changlang to Jairampur
20
Topo map of 132kV Transmission line from Changlang to Jairampur
21
Geo ref map of 132kV Transmission line from Changlang to Jairampur
22
Topo map of Changlang Division for 132kV Transmission line from Changlang to Jairampur
23
Geo ref map of Changlang Division for 132kV Transmission line from Changlang to Jairampur
24
Topo map of Nampong Division for 132kV Transmission line from Changlang to Jairampur
25
Geo ref map of Nampong Division for 132kV Transmission line from Changlang to Jairampur
26
Topo map of USF, Nampong Division for 132kV Transmission line from Changlang to Jairampur
27
Geo ref map of USF, Nampong Division for 132kV Transmission line from Changlang to Jairampur
28
Topo map of Khamtang RF, Nampong Division for 132kV Transmission line from Changlang to Jairampur
29
Geo ref map of Khamtang RF, Nampong Division for 132kV Transmission line from Changlang to Jairampur
30
Topo map of Honkap RF, Nampong Division for 132kV Transmission line from Changlang to Jairampur
31
Geo ref map of Honkap RF, Nampong Division for 132kV Transmission line from Changlang to Jairampur