FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/AR/SubStation/46601/2020   (ii). Name of Project for which Forest Land is required : Diversion Proposal of 5336 sq.mtrs (0.534 Ha) of Forest land for Construction of 132 kV LILO Switching Sub-Station at Tippi near Industrial Estate area.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 132 kV Loop-In Loop-Out switching sub-station at Tippi near industrial estate area.   (iv). State : Arunachal Pradesh   (v). Category of the Proposal : Sub Station   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 500.53   (viii). Area of forest land proposed for diversion(in ha.): 0.534   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 75
A-2. Details of User Agency
  (i). Name : DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH   (ii). Address1 : Executive Engineer (E) Transmission Division No.I Department of Power, Govt. of Arunachal Pradesh Dirang.   (iii). Address2 : NIL   (iv). State : Arunachal Pradesh   (v). District : West Kameng   (vi). Pin : 790101   (vii). Landmark : NIL   (viii). Email address : td1tpmz@gmail.com   (ix). Landline Telephone No. : 0-   (x). Fax No. : 0-   (xi). Mobile No. : 9612000238   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Hage   (ii). Middle Name: NIL   (iii). Last Name: Habung   (iv). Gender: Male   (v). Designation: Assistant Engineer   (vi). Address 1: Grid Station Sub-Division Khuppi   (vii). Address 2: camp office 132/11 kV Sub-Station, Tippi near Bhalukpong.   (viii). State: Arunachal Pradesh   (ix). District: West Kameng   (x). Tehsil: Bhalukpong Circle   (xi). Pin: 790114   (xii). Landmark: NIL   (xiii). Email Address: hage.habung964@gmail.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 9612000238   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Khellong Forest Division, Bhalukpong0.5340
Total0.5340
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.West Kameng0.5340
Total0.5340
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Tippi0.5340
Total 0.534 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Control Room0.0040
2132 kV LILO Sub-Station0.52960
Total 0.5336 0
C. Maps of forest land proposed to be diverted
Division 1. : Khellong Forest Division, Bhalukpong
  (i). Area of forest land proposed to be diverted(in ha.) : 0.534   (ii). Nature of the Project: Non Linear   (a). No. of patches : One
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.0.534    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: No
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : Yes
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1Certificate of Panel compensatory
2Certificate for survey done by total station.
3Certificate for minimum use of forest land
4Certificate for bearing cost of afforastation
5Certificate of breakup of land propose wise.
6Certificate for cost of Net Payment Value
7Certificate of Employment Generation
8Certificate of land required for Department of Power.
9Detailed Cost of Project
10statement of forest land to be diverted
11Undertaking for extraction cost of trees.
12Undertaking for submission of all documents in compliance under Forest Right Act 2006
13Minutes of Meeting regarding completion of abandoned 132 kV Loop-In Loop-Out switching Sub-Station at Tippi near Industrial estate area.
14Agreement between Platinum Alloys Pvt. Ltd. and Department of Power for construction of 2 x 20 MVA, 132/33 kV Sub-Station Including construction of 132 kV LILO Sub-Station at Tippi