FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/AR/HYD/26673/2017   (ii). Name of Project for which Forest Land is required : CHANGE IN LOCATION OF TWO PATCHES “PH QUARRY SITE OF 0.3 HA & BARRAGE QUARRY SITE OF 0.3 HA TO ANOTHER LOCATION & ADDITIONAL .50 HA BARRAGE & PH QUARRY SITE & 3.7 HA FOR BARRAGE ACCESS ROAD IN RESPECT OF PROPOSAL FOR DIVERSION OF FOREST LAND OF 59.90 HA (SURFACE FOREST LAND =51.30 HA; RIVER BED=5.9 HA AND UG AREA=2.7 HA) IN LIEU OF 55.70 HA FOR   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Earlier identified “Barrage Quarry site” of 0.3 Ha in Hiri village and “PH Quarry site” of 0.3 Ha in Gapo village are not meeting the technical requirement and the same can-not be utilized for the construction of (240MW) Heo HEP and earlier proposal of Pauk land requirement an area of 12.6 Ha has b   (iv). State : Arunachal Pradesh   (v). Category of the Proposal : Hydel   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 160418   (viii). Area of forest land proposed for diversion(in ha.): 4.8   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 40
A-2. Details of User Agency
  (i). Name : HEO HYDRO POWER PRIVATE LIMITED   (ii). Address1 : G-77   (iii). Address2 : Sujan Singh Park   (iv). State : Delhi   (v). District : New Delhi   (vi). Pin : 110003   (vii). Landmark : NIL   (viii). Email address : prkiran67@gmail.com   (ix). Landline Telephone No. : 11-24618780   (x). Fax No. : 11-24643891   (xi). Mobile No. : 8794726099   (xii). Website (if any) : www.velcanenergy.com   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Ravikiran   (ii). Middle Name: Rajendra   (iii). Last Name: Pinapotu   (iv). Gender: Male   (v). Designation: V P   (vi). Address 1: G -77   (vii). Address 2: Sujan Singh Park   (viii). State: Arunachal Pradesh   (ix). District: West Siang   (x). Tehsil: Mechuka Circle   (xi). Pin: 110003   (xii). Landmark: NIL   (xiii). Email Address: prkiran67@gmail.com   (xiv). Landline Telephone No.: 11-24618780   (xv). Fax No.: 01124643891   (xvi). Mobile No.: 8794726099   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/AR/HYD/3548/20128-94/2013-FC55.7027 Oct 2016
Total 55.7 0
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Aalo Forest Division, Aalo4.80
Total4.80
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.West Siang4.80
Total4.80
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Meying0.30
2Lipusi0.30
3Hiri3.70
4Chingrong0.50
Total 4.8 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1PH Quarry Site0.30
2Barrage Quarry site0.30
3Barrage Access Road3.70
4Barrage & PH Quarry site0.50
Total 4.8 0
C. Maps of forest land proposed to be diverted
Division 1. : Aalo Forest Division, Aalo
  (i). Area of forest land proposed to be diverted(in ha.) : 4.8   (ii). Nature of the Project: Non Linear   (a). No. of patches : Four
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of PatchesTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.0.3    View File
2.0.3    View File
3.3.7    View File
4.0.5    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 30   (iii). Temporary Employment(Number of person-days): 400
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes   (a). Status of the Environmental Clearance to the Project: EC obtained   (b). Environmental Clearance File No.: NIL   (c). Copy of Environmental Clearance to the Project:   (d). Date of grant of Environmental Clearance to the Project: NIL
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : Yes
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Certificate from Chief Secretary regarding non-availability of suitable non-forest/ revenue forest land
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 240   (ii). Total command area of the Project(in ha.): 0   (a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):   (b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No Documents
Remarks
1FC-Stage-I
2Revise Land Breakup
3Undertaking for NPV
4Undertaking for CA