FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/AR/HYD/24816/2017
(ii). Name of Project for which Forest Land is required :
New Melling Hydro Electric Project (90 MW)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
New Melling HEP(90 MW) is proposed on Mago Chu, under S.F Division Tawang in Arunachal Pradesh. 22m high & 47.8m long barrage,3128m long HRT & U.G Power House are proposed. The estimated annual generation is 433.01 GWh. The Forest land required for the project is 33.48 ha.
(iv). State :
Arunachal Pradesh
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
93802
(viii). Area of forest land proposed for diversion(in ha.):
33.48
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
SEW NEW MELLING POWER CORPORATION LTD
(ii). Address1 :
6-3-871, Snehalata Building , Greenlands Road, Begumpet, Hyderabad, Telangana State.
(iii). Address2 :
NIL
(iv). State :
Telangana
(v). District :
Hyderabad
(vi). Pin :
500016
(vii). Landmark :
Near Chief Minister's Camp Office
(viii). Email address :
sewnewmelling@sewinfra.com
(ix). Landline Telephone No. :
40-66300000
(x). Fax No. :
40-66300001
(xi). Mobile No. :
9447740422
(xii). Website (if any) :
www.sewinfra.com
(xiii). Legal status of User Agency :
Private
A-3.
Details of Person Making Application
(i). First Name:
Jayaprakash
(ii). Middle Name:
NIL
(iii). Last Name:
Natesan
(iv). Gender:
Male
(v). Designation:
BusinessAssociate
(vi). Address 1:
6-3-871, Snehalata Building, Greenlands Road, Begumpet, Hyderabad, Telangana State.
(vii). Address 2:
NIL
(viii). State:
Telangana
(ix). District:
Hyderabad
(x). Tehsil:
Ameerpet
(xi). Pin:
500016
(xii). Landmark:
Near Chief Minister's Camp Office
(xiii). Email Address:
sewnewmelling@sewinfra.com
(xiv). Landline Telephone No.:
40-66300000
(xv). Fax No.:
4066300001
(xvi). Mobile No.:
9447740422
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Tawang SF Division. Tawang
33.48
0
Total
33.48
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Tawang
33.48
0
Total
33.48
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Rho
28.615
0
2
Yuthembu
4.865
0
Total
33.48
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Muck Dump Yard 1
1.54
0
2
Muck Dump Yard 2
3.14
0
3
Facility Area 1
1.85
0
4
Facility Area 2
0.3
0
5
Facility Area 3
0.21
0
6
Labour Colony 1
0.58
0
7
Labour Colony 2
0.2
0
8
Labour Colony 3
0.15
0
9
Labour Colony 4
0.32
0
10
Stack yard 1
2.11
0
11
Stack yard 2
1.08
0
12
Quarry 1
0.3
0
13
Quarry 2
0.5
0
14
Approach Road to Surge Shaft
1.42
0
15
Approach Road to Portal of Adit to Surge Shaft
0.86
0
16
Approach Road to Magazine
0.07
0
17
Approach Road to Portal of Adit to P.H
0.04
0
18
Approach Road to Switch Yard
0.11
0
19
Approach Road in LB and Bridge Abutment
0.04
0
20
Switch Yard
0.3
0
21
Magazine
0.21
0
22
Reservoir area LB
1.16
0
23
Reservoir area RB
1.12
0
24
Barrage & Head works LB
2.21
0
25
Head works , Barrage, Feeder Tunnels- RB
3.33
0
26
Portal of Adit to MAT
0.24
0
27
Portal of Adit to Surge Shaft
0.05
0
28
Portal of Adit to Power House
0.08
0
29
Replacement Road RB
0.81
0
30
Surge Shaft area
0.75
0
31
River portion in Reservoir area
2.25
0
32
River portion in Head works area
0.63
0
33
River portion for Bridge to LB Barrage
0.03
0
34
Notional Under Ground area for Head Race Tunnel
2.55
0
35
Notional Under Ground area for P.H,Adits,MAT,TRT e
2.87
0
36
Notional Under Ground area for Adits to Surge Shaf
0.07
0
Total
33.48
0
C.
Maps of forest land proposed to be diverted
Division 1. : Tawang SF Division. Tawang
(i). Area of forest land proposed to be diverted(in ha.) :
33.48
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
33.48
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
75
(iii). Temporary Employment(Number of person-days):
525000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
Yes
(a). Status of the Environmental Clearance to the Project:
EC obtained
(b). Environmental Clearance File No.:
J-12011/44/2009-IA.I
(c). Copy of Environmental Clearance to the Project:
(d). Date of grant of Environmental Clearance to the Project:
03 Mar 2016
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Others
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
90
(ii). Total command area of the Project(in ha.):
0
(a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):
(b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No
Documents
Remarks
1
MOA
2
Executive Summary
3
Copy orders revising IC to 90 MW
4
Copy orders revising the TWL to 2506.24 m
5
Incorporation certificate of SPV
6
Permission for Survey and Investigation
7
Note on Alternate Sites considered
8
Salient Features
9
Project Layout Map
10
Copy of Muck Disposal Plan as provided in the approved EIA/EMP Report
11
Undertaking to bear the cost of Compensatory Afforestation
12
Undertaking to bear the cost of NPV
13
Undertaking to bear the Additional Cost of NPV
14
Undertaking to bear the Cost of Forest Produces
15
Undertaking that the Project works will be Commenced only after getting final Forest Clearance from MoEF & CC
16
Project Summary
17
Certificate under Section K of Form A regarding settlement of rights under FRA-2006
18
Certificate under Section L of Form A regarding land for Compensatory Afforestation
19
List of undertakings/certificates/undertakings/documents furnished
Print