FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/AP/Pipeline/42672/2019
(ii). Name of Project for which Forest Land is required :
Laying of 20 inch gas Pipeline (about 31 km) from Offshore Platform to Onshore gas Terminal at Mallavaram
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
ONGC proposes to lay 20" Pipeline (about 31 km) from Offshore Platform, through Mouth of the Goutami River to ONGC onshore plant at Mallavaram village, Tallaravu Mandal, East Godavari District, Andhra Pradesh. The proposed pipeline length of 1.17 km is passing through forest boundary (which is falli
(iv). State :
Andhra Pradesh
(v). Category of the Proposal :
Pipeline
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
156200
(viii). Area of forest land proposed for diversion(in ha.):
3.26
(ix). Non-forest land required for this project(in ha.):
58.37
(x). Total period for which the forest land is proposed to be diverted(in years):
25
A-2.
Details of User Agency
(i). Name :
ONGC
(ii). Address1 :
Corporate HSE, 8th Floor Core IV, SCOPE Minar, Delhi 10092
(iii). Address2 :
Corporate HSE, 8th Floor Core IV, SCOPE Minar, Delhi 10092
(iv). State :
Delhi
(v). District :
East
(vi). Pin :
110092
(vii). Landmark :
SCOPE Minar
(viii). Email address :
sharma_js@ongc.co.in
(ix). Landline Telephone No. :
11-22406672
(x). Fax No. :
11-22406681
(xi). Mobile No. :
9868282230
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
Ravi
(ii). Middle Name:
Kumar
(iii). Last Name:
Chacham
(iv). Gender:
Male
(v). Designation:
ChiefGeneralManager
(vi). Address 1:
ONGC, Deendayal Urja Bhavan,5 Nelson Mandela Marg, Vasant Kunj
(vii). Address 2:
ONGC, Deendayal Urja Bhavan,5 Nelson Mandela Marg, Vasant Kunj
(viii). State:
Delhi
(ix). District:
South West
(x). Tehsil:
Vasant Vihar
(xi). Pin:
110070
(xii). Landmark:
Deendayal Urja Bhavan
(xiii). Email Address:
kumar_rajeeva@ongc.co.in
(xiv). Landline Telephone No.:
11-26753023
(xv). Fax No.:
26129067
(xvi). Mobile No.:
9428828040
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kakinada
3.26
58.37
Total
3.26
58.37
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
East Godavari
3.26
58.37
Total
3.26
58.37
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Matlatippa
2.67
0
2
Sea
0
36.9
3
Mallavaram
0
3.2
4
Moolapalem
0.44
2.69
5
Guthinadeevi
0.15
15.58
Total
3.26
58.37
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
pipeline
3.26
58.37
Total
3.26
58.37
C.
Maps of forest land proposed to be diverted
Division 1. : Kakinada
(i). Area of forest land proposed to be diverted(in ha.) :
3.26
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Four
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
2.67
View File
2.
0.44
View File
3.
0.12
View File
4.
0.03
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
100
(iii). Temporary Employment(Number of person-days):
200
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
No
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application under process
(a). Date of submission of proposals :
12 Dec 2019
(b). Current status :
NIL
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Undertaking 1
2
Undertaking 3
3
Undertaking 4
4
Non-applicability of Environmental Clearance
5
Undertaking to provide cost for development of CA land identified by DFO
6
Undertaking to provide RoFR Certificate
7
Clarifications with respect to EDS
8
EDS raised on 26-11-2020
9
Reply to EDS raised o 26-11-2020
10
Forest Area Statement
11
Non Forest Area Statement
12
Certificate
13
Pipe Cross section
14
Description of Project
15
Undertaking 2
16
letter vide F. No 6-60/2020/WL Part (1) dated 16.07.2020 by MOEFCC, Wildlife division
17
Reply to EDS raised by DFO on 23-07-2021
18
Clause 2.5 of Handbook of FCA
19
Pipeline CRZ Clearance letter
20
EDS raised by PCCF dated 11-08-2021
21
ONGC reply to EDS raised by PCCF dated 11-08-2021
22
Wildlife Management plan
23
EDS raised by PCCF 26-08-2021
24
ONGC reply to EDS raised by PCCF 26-08-2021