  (i). Proposal No. : FP/UK/WATER/42059/2019              (ii). Name of Project for which Forest Land is required : Tharali Water Pumping Supply Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : in this project approx 19.60 Km supply main, 27 Km distribution pipe line and 310 KL, 250 KL and 150 Kl clear water reservoir and 0.70 MLD, 0.50 MLD amd 0.30 MLd water treatment plants has proposed.              (iv). State : Uttarakhand              (v). Category of the Project : Drinking Water              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.365
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/WATER/42059/201917/09/201909/03/2020  01/11/2019  23/09/2019   17/06/2020  27/02/2020  25/10/2019   16/07/2020   03/07/2021 Badrinath,Gopeshwar :03/07/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Badrinath,Gopeshwar) on:07/08/2021  
Replied by UA on :12/10/2021  
Query raised by DFO (Badrinath,Gopeshwar) on:10/01/2022  
Replied by UA on :17/05/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:03/08/2022  
Replied by UA on :  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .