TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/WATER/14692/2015              (ii). Name of Project for which Forest Land is required : Diswane Malli Water Supply Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diswane Malli Water Supply Scheme              (iv). File no. : 2(39)/2015              (v). State : Uttarakhand              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.186
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UK/WATER/14692/201515/08/201508/09/2015  03/09/2015   16/09/2015  08/09/2015   26/09/2015   28/09/2015 Garhwal,Pauri :01/10/2015Garhwal:
  23/10/2015 (Garhwal,Pauri)

Uttarakhand:
18/11/2015
Uttarakhand:
26/11/2015
27/01/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Garhwal) on:30/10/2015  
Replied by DFO (Garhwal,Pauri) on:06/11/2015  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)
Close(X)
Please wait ...