TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/41149/2019              (ii). Name of Project for which Forest Land is required : New Construction of Lachair to Katyani Motor Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : New Construction of Lachair to Katyani Motor Road started from Km 4.00 of Lachair Chirali M/R and goes to Katyani. There are 8 Tok villages connected by this project with 662 population. By this road two Block head quaters ( MUNAKOT & KANALICHINA) will be joined. This Motor road is used as bypass              (iv). File no. : 8B/UCP/06/164/2020/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 5.6
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UK/ROAD/41149/201916/07/201931/08/2019  27/08/2019  07/08/2019  23/07/2019   12/09/2019  29/08/2019  24/08/2019  06/08/2019   16/09/2019   29/09/2019 Pithoragarh :10/10/2019North Kumaun:
  21/10/2019 (Pithoragarh)

Uttarakhand:
16/11/2019
Uttarakhand:
20/11/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:24/12/2020  
Replied by State Government(Uttarakhand) on:23/11/2021  
Query raised by Regional Office (Dehradun) on:03/12/2021  
Replied by State Government(Uttarakhand) on:10/08/2022  
Query raised by State Government (Uttarakhand) on:29/12/2020  
Replied by Nodal Officer (Uttarakhand) on:23/11/2021  
Query raised by State Government (Uttarakhand) on:06/12/2021  
Replied by Nodal Officer (Uttarakhand) on:10/08/2022  
Query raised by Nodal Officer (Uttarakhand) on:18/11/2019  
Replied by Circle(North Kumaun) on:19/12/2019  
Query raised by Nodal Officer (Uttarakhand) on:28/12/2019  
Replied by Circle(North Kumaun) on:10/02/2020  
Query raised by Nodal Officer (Uttarakhand) on:13/02/2020  
Replied by Circle(North Kumaun) on:19/10/2020  
Query raised by Nodal Officer (Uttarakhand) on:29/12/2020  
Replied by Circle(North Kumaun) on:18/11/2021  
Query raised by Nodal Officer (Uttarakhand) on:07/12/2021  
Replied by Circle(North Kumaun) on:08/08/2022  
Query raised by Circle (North Kumaun) on:21/11/2019  
Replied by DFO (Pithoragarh) on:11/12/2019  
Query raised by Circle (North Kumaun) on:13/12/2019  
Replied by DFO (Pithoragarh) on:16/12/2019  
Query raised by Circle (North Kumaun) on:31/12/2019  
Replied by DFO (Pithoragarh) on:05/02/2020  
Query raised by Circle (North Kumaun) on:02/07/2020  
Replied by DFO (Pithoragarh) on:16/10/2020  
Query raised by Circle (North Kumaun) on:04/01/2021  
Replied by DFO (Pithoragarh) on:26/10/2021  
Query raised by Circle (North Kumaun) on:09/11/2021  
Replied by DFO (Pithoragarh) on:12/11/2021  
Query raised by Circle (North Kumaun) on:13/12/2021  
Replied by DFO (Pithoragarh) on:21/07/2022  
Query raised by Circle (North Kumaun) on:27/07/2022  
Replied by DFO (Pithoragarh) on:29/07/2022  
Query raised by DFO (Pithoragarh) on:23/11/2019  
Replied by UA on :28/11/2019  
Query raised by DFO (Pithoragarh) on:28/11/2019  
Replied by UA on :29/11/2019  
Query raised by DFO (Pithoragarh) on:10/12/2019  
Replied by UA on :11/12/2019  
Query raised by DFO (Pithoragarh) on:03/01/2020  
Replied by UA on :29/01/2020  
Query raised by DFO (Pithoragarh) on:02/07/2020  
Replied by UA on :12/10/2020  
Query raised by DFO (Pithoragarh) on:06/01/2021  
Replied by UA on :16/10/2021  
Query raised by DFO (Pithoragarh) on:14/12/2021  
Replied by UA on :07/07/2022  
Query raised by DFO (Pithoragarh) on:09/07/2022  
Replied by UA on :09/07/2022  
Query raised by DFO (Pithoragarh) on:28/07/2022  
Replied by UA on :29/07/2022  
NOTE:- Proposal has been : Rejected By REC .