Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
18/11/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
2
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
21/11/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
3
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
23/11/2019
|
The user agency may provide original hard copy of the proposal to CF office including authenticated copy of Part I to Part iii as in online web portal.
|
|
4
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
28/11/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
28/11/2019
|
The user agency may provide original hard copy of the proposal to CF office including authenticated copy of Part I to Part iii as in online web portal. And send receiving letter.
|
|
6
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
29/11/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
10/12/2019
|
The user agency may provide original hard copy of the proposal to CF office including authenticated copy of Part I to Part iii as in online web portal. And send receiving letterto us.
|
|
8
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
11/12/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
11/12/2019
|
hard copy has been submitted as per letter.
|
|
10
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
13/12/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
11
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
16/12/2019
|
The correction have been made as per the instruction received
|
|
12
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
19/12/2019
|
hard copy has been sent by user agency.
|
|
13
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
28/12/2019
|
find the letter attached
|
|
14
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
31/12/2019
|
find the letter attached
|
|
15
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
03/01/2020
|
Remove obj as per letter.
|
|
16
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
29/01/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
05/02/2020
|
The correction have been made as per the instruction received
|
|
18
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
10/02/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 28-12-2019 has been clarified by Dfo Pithoragarh letter no 2840/12-1 dated 04-02-2020.
|
|
19
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
13/02/2020
|
find the letter attached
|
|
20
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
02/07/2020
|
As per letter no 43/12-1 dated 02-07-2020
|
|
21
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
02/07/2020
|
As per letter no 43/12-1 dated 02-07-2020
|
|
22
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
12/10/2020
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
16/10/2020
|
The correction have been made as per the instruction received
|
|
24
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
19/10/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 13-02-2020 has been clarified by Dfo Pithoraghar letter no 1480/12-1 dated 14-10-2020
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
24/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
29/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
27
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
29/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
28
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
04/01/2021
|
state govt. may attend the following shortcomings as per the attachment here
|
|
29
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
06/01/2021
|
remove objection as per letter.
|
|
30
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
16/10/2021
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
26/10/2021
|
Objection has been removed as per letter.
|
|
32
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
09/11/2021
|
Send 4 more hard copies of the answer to the objection, so that the matter can be sent to the higher level & direct the user agency to collect the returning letter for the proposal with the recommendation of CF North Kumaon and submit the hard copy at the Nodal Office.
|
|
33
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
12/11/2021
|
all copies are already sent to the CF Office.
|
|
34
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
18/11/2021
|
As per letter no 1879/ 12-1 dated 12-11-2021
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
23/11/2021
|
The correction have been made as per the instruction received
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
23/11/2021
|
The correction have been made as per the instruction received
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
03/12/2021
|
State Govt. may attend to the shortcomings as per the minutes of REC meeting attached.
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
06/12/2021
|
State Govt. may attend to the shortcomings as per the minutes of REC meeting attached.
|
|
39
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
07/12/2021
|
State Govt. may attend to the shortcomings as per the minutes of REC meeting attached.
|
|
40
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
13/12/2021
|
State Govt. may attend to the shortcomings as per the minutes of REC meeting attached.
|
|
41
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
14/12/2021
|
State Govt. may attend to the shortcomings as per the minutes of REC meeting attached.
|
|
42
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
07/07/2022
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
09/07/2022
|
plz verify point no. 5
|
|
44
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
09/07/2022
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
21/07/2022
|
corrections have been made
|
|
46
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
27/07/2022
|
Plz dfo latter attachment
|
|
47
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
28/07/2022
|
Objection has been removed.
|
|
48
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
29/07/2022
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
29/07/2022
|
Objections have been removed.
|
|
50
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
08/08/2022
|
As per letter no 406/12-1 dated 30-07-2022
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
10/08/2022
|
The correction have been made as per the instruction received
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
10/08/2022
|
The correction have been made as per the instruction received
|
|