TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/39053/2019              (ii). Name of Project for which Forest Land is required : Construction of Tanakpur Tawaghat M/R to Sigda Motor Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Tanakpur Tawaghat M/R to Sidga Motor Raod is proposed to connect 757 population with road of 8.250 km, which is estimated to connect the village with highway making the villagers accessible to social facilities such as road, school, hospital etc.              (iv). File no. : 8B/UCP/06/02/2020/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.9115
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/39053/201925/02/201917/06/2019  13/03/2019   02/07/2019  15/06/2019   09/07/2019   27/07/2019 Champawat :30/07/2019North Kumaun:
  09/08/2019 (Champawat)

Uttarakhand:
09/09/2019
Uttarakhand:
24/12/2019
Dehradun:
15/01/2020
09/09/2020
By :Regional Office
Uttarakhand
03/11/2022
03/09/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:31/01/2020  
Replied by State Government(Uttarakhand) on:04/06/2020  
Query raised by Regional Office (Dehradun) on:15/06/2020  
Replied by State Government(Uttarakhand) on:03/09/2020  
Query raised by State Government (Uttarakhand) on:04/02/2020  
Replied by Nodal Officer (Uttarakhand) on:03/06/2020  
Query raised by State Government (Uttarakhand) on:15/06/2020  
Replied by Nodal Officer (Uttarakhand) on:02/09/2020  
Query raised by Nodal Officer (Uttarakhand) on:09/09/2019  
Replied by Circle(North Kumaun) on:23/09/2019  
Query raised by Nodal Officer (Uttarakhand) on:28/09/2019  
Replied by Circle(North Kumaun) on:19/10/2019  
Query raised by Nodal Officer (Uttarakhand) on:04/11/2019  
Replied by Circle(North Kumaun) on:23/12/2019  
Query raised by Nodal Officer (Uttarakhand) on:04/02/2020  
Replied by Circle(North Kumaun) on:01/06/2020  
Query raised by Nodal Officer (Uttarakhand) on:15/06/2020  
Replied by Circle(North Kumaun) on:29/08/2020  
Query raised by Circle (North Kumaun) on:11/09/2019  
Replied by DFO (Champawat) on:22/09/2019  
Query raised by Circle (North Kumaun) on:01/10/2019  
Replied by DFO (Champawat) on:11/10/2019  
Query raised by Circle (North Kumaun) on:07/11/2019  
Replied by DFO (Champawat) on:30/11/2019  
Query raised by Circle (North Kumaun) on:03/12/2019  
Replied by DFO (Champawat) on:20/12/2019  
Query raised by Circle (North Kumaun) on:10/02/2020  
Replied by DFO (Champawat) on:29/05/2020  
Query raised by Circle (North Kumaun) on:22/06/2020  
Replied by DFO (Champawat) on:26/08/2020  
Query raised by DFO (Champawat) on:12/09/2019  
Replied by UA on :16/09/2019  
Query raised by DFO (Champawat) on:03/10/2019  
Replied by UA on :09/10/2019  
Query raised by DFO (Champawat) on:08/11/2019  
Replied by UA on :26/11/2019  
Query raised by DFO (Champawat) on:04/12/2019  
Replied by UA on :04/12/2019  
Query raised by DFO (Champawat) on:17/12/2019  
Replied by UA on :19/12/2019  
Query raised by DFO (Champawat) on:13/02/2020  
Replied by UA on :09/05/2020  
Query raised by DFO (Champawat) on:23/06/2020  
Replied by UA on :17/07/2020  
Query raised by DFO (Champawat) on:21/07/2020  
Replied by UA on :21/07/2020  
Query raised by DFO (Champawat) on:26/08/2020  
Replied by UA on :26/08/2020  
Query raised by DFO (Champawat) on:26/08/2020  
Replied by UA on :26/08/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:30/11/2022  
Replied by State Government(Uttarakhand) on:20/08/2024  
Query raised by State Government (Uttarakhand) on:06/12/2022  
Replied by Nodal Officer (Uttarakhand) on:12/08/2024  
Query raised by Nodal Officer on:06/12/2022  
Replied by UA on :22/07/2024  
NOTE:- Stage-II Approval accorded by : Regional Office .