Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
23/03/2017
|
please enclose Part III to Part V filled in the hard copy to the Nodal office as it is filled in the online along with original hard copy containing original Documents...instruction received from Nodal office.
|
|
2
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
27/04/2017
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
03/05/2017
|
please enclose acknowledgement letter received from Nodal office...
|
|
4
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
29/06/2017
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
06/09/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
08/09/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
7
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
12/09/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
8
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
19/09/2017
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
12/10/2017
|
please fin enclosed
|
|
10
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
13/10/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 06-09-2017 has been clarified by DFO Bageshwar letter no 805/12-1 dated 11-10-2017
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
17/11/2017
|
State Govt. may attend following shortcomings as per the attachment.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
23/11/2017
|
State Govt. may attend following shortcomings as per the attachment.
|
|
13
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
25/11/2017
|
State Govt. may attend following shortcomings as per the attachment.
|
|
14
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
27/11/2017
|
State Govt. may attend shortcomings as per the attachment.
|
|
15
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
29/11/2017
|
please find enclosed
|
|
16
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
06/12/2017
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
09/12/2017
|
please find enclosed
|
|
18
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
11/12/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 25-11-2017 has been clarified by DFO Bageshwar letter no 1296/12-1 dated 08-12-2017
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
28/12/2017
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
29/12/2017
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|