TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/21524/2016              (ii). Name of Project for which Forest Land is required : Construction of Mankot-Baset motor road in District-Bageshwar (CM Ghosna-2122/2015)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for diversion of 2.369 ha. forest land for construction of motor road.detail narrative attached form-11 (2.1) in additional enclosure.              (iv). File no. : 8B/UCP/06/81/2017/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.369
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/21524/201621/09/201627/01/2017  19/01/2017  13/01/2017  12/01/2017  09/11/2016  04/11/2016  14/10/2016   07/02/2017  19/01/2017  18/01/2017  13/01/2017  25/11/2016  05/11/2016  18/10/2016   19/12/2016   22/12/2016 Bageshwar :21/02/2017North Kumaun:
  28/08/2017 (Bageshwar)

Uttarakhand:
06/09/2017
Uttarakhand:
24/10/2017
Dehradun:
31/10/2017
17/01/2018
By :Regional Office
Uttarakhand
06/09/2024
24/02/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:17/11/2017  
Replied by State Government(Uttarakhand) on:29/12/2017  
Query raised by State Government (Uttarakhand) on:23/11/2017  
Replied by Nodal Officer (Uttarakhand) on:28/12/2017  
Query raised by Nodal Officer (Uttarakhand) on:06/09/2017  
Replied by Circle(North Kumaun) on:13/10/2017  
Query raised by Nodal Officer (Uttarakhand) on:25/11/2017  
Replied by Circle(North Kumaun) on:11/12/2017  
Query raised by Circle (North Kumaun) on:08/09/2017  
Replied by DFO (Bageshwar) on:12/10/2017  
Query raised by Circle (North Kumaun) on:27/11/2017  
Replied by DFO (Bageshwar) on:09/12/2017  
Query raised by DFO (Bageshwar) on:23/03/2017  
Replied by UA on :27/04/2017  
Query raised by DFO (Bageshwar) on:03/05/2017  
Replied by UA on :29/06/2017  
Query raised by DFO (Bageshwar) on:12/09/2017  
Replied by UA on :19/09/2017  
Query raised by DFO (Bageshwar) on:29/11/2017  
Replied by UA on :06/12/2017  
NOTE:- Stage-II Approval accorded by : Regional Office .