| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
12/09/2022
|
Sir, Please remove the objection.
|
|
|
2
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
11/04/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
24/06/2023
|
Sir Please remove the objection
|
|
|
4
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
15/07/2023
|
Please remove the objection.
|
|
|
5
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
22/08/2023
|
The correction have been made as per the instruction received
|
|
|
6
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
15/09/2023
|
please remove the ojbection
|
|
|
7
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
13/11/2023
|
The correction have been made as per the instruction received
|
|
|
8
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
17/11/2023
|
the proposal hard copy is not submitted to dfo office.
|
|
|
9
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
20/11/2023
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
03/02/2024
|
EDS has been removed
|
|
|
11
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
12/02/2024
|
Sir Please remove the objection
|
|
|
12
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
16/02/2024
|
Sir, eds objection has been removed.
|
|
|
13
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
17/02/2024
|
Sir Please remove the objection
|
|
|
14
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
27/02/2024
|
Please remove the objection.
|
|
|
15
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
06/03/2024
|
The correction have been made as per the instruction received
|
|
|
16
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
06/03/2024
|
Sir, EDS objection has been removed.
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
04/05/2024
|
find the letter attached
|
|
|
18
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
06/05/2024
|
find the letter attached
|
|
|
19
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
10/05/2024
|
Please remove the objection.
|
|
|
20
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
27/07/2024
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
21/08/2024
|
please remove the objection.
|
|
|
22
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
24/09/2024
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
19/12/2024
|
Sir,
eds objection has been remove.
|
|
|
24
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
19/12/2024
|
Kindly rectify the errors
|
|
|
25
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
19/12/2024
|
Sir, eds objection has been removed by dfo office and user agency.
|
|
|
26
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
21/12/2024
|
The attachments which are indicate in forwarding letter are not provided.
|
|
|
27
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
24/01/2025
|
sir, eds objection has been removed.
|
|
|
28
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
04/02/2025
|
Please find the attachments.
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
19/08/2025
|
Kindly find the nodal EDS letter and kindly provide the pointwise reply.
|
|
|
30
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
23/08/2025
|
Kindly find the nodal EDS letter and kindly provide the pointwise reply.
|
|
|
31
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
03/09/2025
|
Correction has been made as per instruction received.
|
|
|
32
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
18/09/2025
|
Sir Please received the information this proposal
|
|
|
33
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
03/10/2025
|
After Examining the proposal online, in part-II it is observed that the CA scheme for 200 plants uploaded. While proposal is related to less than 1.0 ha. i.e. 0.595 ha. & no. of trees to be affected in the proposal are total 89 trees. Hence as per the rule 10 times plantation scheme will be required in the proposal. Instead of 200 plants total 890 plantation scheme may kindly be uploaded on part-II and accordingly site suitability certificate, maps of CA land may kindly be uploaded, so that further action can be taken.
|
|
|
34
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
04/10/2025
|
After Examining the proposal online, in part-II it is observed that the CA scheme for 200 plants uploaded. While proposal is related to less than 1.0 ha. i.e. 0.595 ha. & no. of trees to be affected in the proposal are total 89 trees. Hence as per the rule 10 times plantation scheme will be required in the proposal. Instead of 200 plants total 890 plantation scheme may kindly be uploaded on part-II and accordingly site suitability certificate, maps of CA land may kindly be uploaded, so that further action can be taken.
|
|
|
35
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
24/10/2025
|
Plantation scheme has been attached.
|
|