| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Pithoragarh)
|
EDS
|
User Agency (mcjoshi1206@gmail.com)
|
13/05/2022
|
Send part 1
|
|
|
2
|
User Agency (mcjoshi1206@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
25/05/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Pithoragarh)
|
EDS
|
User Agency (mcjoshi1206@gmail.com)
|
07/06/2022
|
plz revise the kml of the road alignment as per letter.
|
|
|
4
|
User Agency (mcjoshi1206@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
30/07/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Pithoragarh)
|
EDS
|
User Agency (mcjoshi1206@gmail.com)
|
31/08/2022
|
Plz remove objection.
|
|
|
6
|
User Agency (mcjoshi1206@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
25/10/2023
|
The correction have been made as per the instruction received
|
|
|
7
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
21/12/2023
|
No Records Found
|
|
|
8
|
DFO (Pithoragarh)
|
EDS
|
User Agency (mcjoshi1206@gmail.com)
|
22/12/2023
|
send part 1
|
|
|
9
|
User Agency (mcjoshi1206@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
22/12/2023
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
27/02/2024
|
proposal are sent to CF office.
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
29/02/2024
|
find the letter attached
|
|
|
12
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
01/03/2024
|
find the letter attached
|
|
|
13
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdberinag@gmail.com)
|
04/03/2024
|
find the letter attached
|
|
|
14
|
User Agency (eepwdberinag@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
09/08/2024
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
07/09/2024
|
Objection has been removed.
|
|
|
16
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
26/09/2024
|
Objection has been removed.
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
04/10/2024
|
As per letter attached
|
|
|
18
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
05/10/2024
|
As per letter attached
|
|
|
19
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdberinag@gmail.com)
|
05/04/2025
|
Remove objection as per letter attached.
|
|
|
20
|
User Agency (eepwdberinag@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
17/04/2025
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
03/05/2025
|
Objection removed.
|
|
|
22
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
16/05/2025
|
As per letter no 2930/12-1 dated 08-05-2025
|
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
31/05/2025
|
As per EDS letter
|
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
03/06/2025
|
As per EDS letter
|
|
|
25
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
05/06/2025
|
Remove objection.
|
|
|
26
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
06/06/2025
|
Correct file uploaded
|
|
|
27
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdberinag@gmail.com)
|
17/06/2025
|
Remove objection.
|
|
|
28
|
User Agency (eepwdberinag@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
30/06/2025
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
05/02/2026
|
OBJECTION HAS BEEN REMOVED
|
|