Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
04/06/2019
|
Attached letter no-2669/12-1 dated- 4.6.2019
|
|
2
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
20/06/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
05/07/2019
|
Attached letter
|
|
4
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
11/07/2019
|
The correction have been made as per the instruction received
|
|
5
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
15/07/2019
|
Submit hard copy of proposal to CF office for necessary action.
|
|
6
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
26/07/2019
|
Hard copy of proposal has been submitted to the CF office.
|
|
7
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
30/07/2019
|
Find the letter attached.
|
|
8
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
03/08/2019
|
Find the letter attached.
|
|
9
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
30/10/2019
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
08/11/2019
|
Attached letter no-897/12-1 dated-07/11/2019
|
|
11
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
19/11/2019
|
Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
12
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
19/11/2019
|
Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
13
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
02/09/2020
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
02/09/2020
|
correction has been made by user agency as per the instruction received....
|
|
15
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
03/09/2020
|
It has been found that Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
16
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
03/09/2020
|
It has been found that Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it
|
|
17
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
04/09/2020
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
04/09/2020
|
correction have been made as per the instruction received
|
|
19
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
08/09/2020
|
It has been found that Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
20
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
09/09/2020
|
It has been found that Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
21
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
14/10/2020
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
14/10/2020
|
Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
23
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
22/10/2020
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
22/10/2020
|
Point no. 4 of EDS has not been resolved yet. User Agency kindly attend to it.
|
|
25
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
23/10/2020
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
23/10/2020
|
The correction have been made by the user agency as per the instruction received
|
|
27
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
26/10/2020
|
Point no. 4 of EDS has not been resolved yet. Google map is still uploaded at para D-a of online part I.
|
|
28
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
27/10/2020
|
It is very disappointing that the objection has not yet been resolved by your level. Point no. 4 of EDS has not been resolved yet. Google map is still uploaded at para D-a of online part I... kindly upload a original map prepared by forest department rather than Google map.....
|
|
29
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
28/10/2020
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
28/10/2020
|
The correction have been made as per the instruction received.......
|
|
31
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
13/11/2020
|
As per the direction of CCF Garhwal, DSS analysis of the site selected for CA to be uploaded online with the proposal. DFO to ensure uploading of DSS report online.
|
|
32
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
25/11/2020
|
DSS has not been completed due to some technical problems mentioned in lttr attached......
|
|
33
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
26/11/2020
|
Instruction of CF Yamuna given on the date 25-11-2020 is as follows. In case of DSS analysis is not getting carried out successfully, DFO ensure to upload the site inspection report of the land selected for CA till the technical problem is resolved. Site inspection must be carried out by the forest officer not below the rank of ACF/SDO.
|
|
34
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
08/12/2020
|
Find the letter attached.....
|
|
35
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
15/02/2023
|
The correction have been made as per the instruction received
|
|
36
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
19/02/2023
|
kindly upload map of CA land. and provide 4 copies of proposal.
|
|
37
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
02/05/2023
|
The correction have been made as per the instruction received
|
|
38
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
04/06/2023
|
correction has been made as per the instruction recieved..
|
|
39
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
13/06/2023
|
Previously only one hard copy of proposal was submitted to CF office. It needs to be submitted to CF office in triplicate for necessary action.
|
|
40
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
14/06/2023
|
Previously only one hard copy of proposal was submitted to CF office. It needs to be submitted to CF office in triplicate for necessary action.
|
|
41
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
25/08/2023
|
The correction have been made as per the instruction received
|
|
42
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
29/08/2023
|
user agency uploaded the suitability certificate of ca land which was rejected. so kindly rermove all the rejected document
|
|
43
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
04/12/2023
|
The correction have been made as per the instruction received
|
|
44
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
11/12/2023
|
According to CF yamuna .....Previously only one hard copy of proposal was submitted to CF office. It needs to be submitted to CF office in triplicate for necessary action. So kindly provide hardcopy of proposal
|
|
45
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
19/12/2023
|
The correction have been made as per the instruction received
|
|
46
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
21/12/2023
|
Kindly provide hardcopy of proposal
|
|
47
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
29/04/2024
|
The correction have been made as per the instruction received
|
|
48
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
04/05/2024
|
According to CF yamuna .....Previously only one hard copy of proposal was submitted to CF office. It needs to be submitted to CF office in triplicate for necessary action. So kindly provide hardcopy of proposal
|
|
49
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
09/05/2024
|
The correction have been made as per the instruction received
|
|
50
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
27/05/2024
|
Kindly attached the lttr of recieving hard copy by nodal....
|
|
51
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
05/06/2024
|
The correction have been made as per the instruction received
|
|
52
|
DFO (Tons,Purola)
|
REPLY
|
CF (Yamuna)
|
09/06/2024
|
According to user agency, they already have been submitted all 3 hard copies to nodal office dehradun. The lttr is attached in pdf.
|
|
53
|
CF (Yamuna)
|
EDS
|
DFO (Tons,Purola)
|
13/06/2024
|
Do the necessary as per letter attached.
|
|
54
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
24/06/2024
|
Do the necessary as per letter attached
|
|
55
|
User Agency (himansN@gmail.com)
|
REPLY
|
DFO (Tons,Purola)
|
09/11/2024
|
The correction have been made as per the instruction received
|
|
56
|
DFO (Tons,Purola)
|
EDS
|
User Agency (himansN@gmail.com)
|
09/11/2024
|
Kindly provide hard copy in division office
|
|