TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/146204/2021              (ii). Name of Project for which Forest Land is required : Sumalta to koladungri motor road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : this road is proposed to connect an isolated village named koladungri having popualtion of 58 in karanprayah blockchamoli district UTTARAKHAND. It will connect the villagers to nearby market as simli and karanprayag and also to the schools and hospitals              (iv). File no. : 8b/UCP/06/17/2022/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.861
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/146204/202119/08/2021aa21/08/2021   14/09/2021 Badrinath,Gopeshwar :15/09/2021Garhwal:
  20/12/2021 (Badrinath,Gopeshwar)

Uttarakhand:
06/01/2022
Uttarakhand:
04/03/2022
Dehradun:
14/03/2022
11/12/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:30/03/2022  
Replied by State Government(Uttarakhand) on:22/06/2022  
Query raised by Regional Office (Dehradun) on:30/06/2022  
Replied by State Government(Uttarakhand) on:01/11/2022  
Query raised by Regional Office (Dehradun) on:07/11/2022  
Replied by State Government(Uttarakhand) on:31/01/2023  
Query raised by Regional Office (Dehradun) on:17/02/2023  
Replied by State Government(Uttarakhand) on:28/04/2023  
Query raised by Regional Office (Dehradun) on:01/06/2023  
Replied by State Government(Uttarakhand) on:05/10/2023  
Query raised by Regional Office (Dehradun) on:03/11/2023  
Replied by State Government(Uttarakhand) on:26/12/2023  
Query raised by State Government (Uttarakhand) on:31/03/2022  
Replied by Nodal Officer (Uttarakhand) on:16/06/2022  
Query raised by State Government (Uttarakhand) on:22/06/2022  
Replied by Nodal Officer (Uttarakhand) on:22/06/2022  
Query raised by State Government (Uttarakhand) on:30/06/2022  
Replied by Nodal Officer (Uttarakhand) on:01/11/2022  
Query raised by State Government (Uttarakhand) on:07/11/2022  
Replied by Nodal Officer (Uttarakhand) on:31/01/2023  
Query raised by State Government (Uttarakhand) on:21/02/2023  
Replied by Nodal Officer (Uttarakhand) on:28/04/2023  
Query raised by State Government (Uttarakhand) on:02/06/2023  
Replied by Nodal Officer (Uttarakhand) on:05/10/2023  
Query raised by State Government (Uttarakhand) on:16/11/2023  
Replied by Nodal Officer (Uttarakhand) on:13/12/2023  
Query raised by State Government (Uttarakhand) on:13/12/2023  
Replied by Nodal Officer (Uttarakhand) on:22/12/2023  
Query raised by Nodal Officer (Uttarakhand) on:17/01/2022  
Replied by Circle(Garhwal) on:07/02/2022  
Query raised by Nodal Officer (Uttarakhand) on:31/03/2022  
Replied by Circle(Garhwal) on:14/06/2022  
Query raised by Nodal Officer (Uttarakhand) on:30/06/2022  
Replied by Circle(Garhwal) on:22/10/2022  
Query raised by Nodal Officer (Uttarakhand) on:11/11/2022  
Replied by Circle(Garhwal) on:11/01/2023  
Query raised by Nodal Officer (Uttarakhand) on:21/02/2023  
Replied by Circle(Garhwal) on:24/04/2023  
Query raised by Nodal Officer (Uttarakhand) on:02/06/2023  
Replied by Circle(Garhwal) on:20/09/2023  
Query raised by Nodal Officer (Uttarakhand) on:16/11/2023  
Replied by Circle(Garhwal) on:06/12/2023  
Query raised by Circle (Garhwal) on:21/12/2021  
Replied by DFO (Badrinath,Gopeshwar) on:01/01/2022  
Query raised by Circle (Garhwal) on:17/01/2022  
Replied by DFO (Badrinath,Gopeshwar) on:01/02/2022  
Query raised by Circle (Garhwal) on:31/03/2022  
Replied by DFO (Badrinath,Gopeshwar) on:30/04/2022  
Query raised by Circle (Garhwal) on:05/05/2022  
Replied by DFO (Badrinath,Gopeshwar) on:18/05/2022  
Query raised by Circle (Garhwal) on:18/05/2022  
Replied by DFO (Badrinath,Gopeshwar) on:10/06/2022  
Query raised by Circle (Garhwal) on:13/06/2022  
Replied by DFO (Badrinath,Gopeshwar) on:13/06/2022  
Query raised by Circle (Garhwal) on:01/07/2022  
Replied by DFO (Badrinath,Gopeshwar) on:12/09/2022  
Query raised by Circle (Garhwal) on:17/09/2022  
Replied by DFO (Badrinath,Gopeshwar) on:14/10/2022  
Query raised by Circle (Garhwal) on:14/11/2022  
Replied by DFO (Badrinath,Gopeshwar) on:30/12/2022  
Query raised by Circle (Garhwal) on:25/02/2023  
Replied by DFO (Badrinath,Gopeshwar) on:23/03/2023  
Query raised by Circle (Garhwal) on:02/06/2023  
Replied by DFO (Badrinath,Gopeshwar) on:28/08/2023  
Query raised by Circle (Garhwal) on:17/11/2023  
Replied by DFO (Badrinath,Gopeshwar) on:30/11/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:30/09/2021  
Replied by UA on :30/10/2021  
Query raised by DFO (Badrinath,Gopeshwar) on:08/11/2021  
Replied by UA on :16/11/2021  
Query raised by DFO (Badrinath,Gopeshwar) on:01/04/2022  
Replied by UA on :07/04/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:11/04/2022  
Replied by UA on :23/04/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:18/05/2022  
Replied by UA on :06/06/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:07/07/2022  
Replied by UA on :12/08/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:30/08/2022  
Replied by UA on :07/09/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:14/11/2022  
Replied by UA on :27/12/2022  
Query raised by DFO (Badrinath,Gopeshwar) on:03/03/2023  
Replied by UA on :11/03/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:22/06/2023  
Replied by UA on :26/06/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:15/07/2023  
Replied by UA on :18/07/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:02/08/2023  
Replied by UA on :03/08/2023  
Query raised by DFO (Badrinath,Gopeshwar) on:21/11/2023  
Replied by UA on :29/11/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .