Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
05/05/2015
|
pls submit the noc of vp
|
|
2
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
08/05/2015
|
Acceptance letter uploaded
|
|
3
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
11/05/2015
|
pl submit the correct CA land which is recommended by DFO Almora
|
|
4
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
14/05/2015
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
24/05/2015
|
Please give compartment wise area details of RF involved. The compartment no. mentioned in land schedule is different from what is seen in the digitized toposheet.
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Civil Soyam,Almora)
|
25/05/2015
|
As per letter no 2728/12-1 dated 25-05-2015
|
|
7
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
26/05/2015
|
short the query by cf
|
|
8
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
27/05/2015
|
Acknowledgement slip submitted by User Agency regarding acceptance of proposal
|
|
9
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
28/05/2015
|
full fill the query details
|
|
10
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
28/05/2015
|
Reply by User Agency
|
|
11
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
02/06/2015
|
pl submit the top sheet & digital map
|
|
12
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
02/06/2015
|
Objection has been rectified by user agency
|
|
13
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
05/06/2015
|
short the query as per letter
|
|
14
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
05/06/2015
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Civil Soyam,Almora)
|
REPLY
|
CF (North Kumaun)
|
10/06/2015
|
short out the topo sheet query
|
|
16
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
12/06/2015
|
As per enclose letter no 2916/12-1 dated 12-06-2015
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
21/07/2015
|
1.Short narrative of the project does not provide any information about the project .
2.Employment generation data not provided in part I.
3.Land schedule scattered in different performa. May be consolidated in one performa.
4.Exclude trees on nap land from detail of trees in part II
5.Information at point 5 and point 12 of Part II not correct.
6.Not able to open DFO recommendation in part II. May upload again.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
23/07/2015
|
Plz reply to obj of RO-1.Short narrative of the project does not provide any information about the project . 2.Employment generation data not provided in part I. 3.Land schedule scattered in different performa. May be consolidated in one performa. 4.Exclude trees on nap land from detail of trees in part II 5.Information at point 5 and point 12 of Part II not correct. 6.Not able to open DFO recommendation in part II. May upload again.
|
|
19
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
24/07/2015
|
Plz reply to obj of RO-1.Short narrative of the project does not provide any information about the project . 2.Employment generation data not provided in part I. 3.Land schedule scattered in different performa. May be consolidated in one performa. 4.Exclude trees on nap land from detail of trees in part II 5.Information at point 5 and point 12 of Part II not correct. 6.Not able to open DFO recommendation in part II. May upload again.
|
|
20
|
CF (North Kumaun)
|
EDS
|
DFO (Civil Soyam,Almora)
|
28/07/2015
|
As per letter no 273/12-1 dated 27-07-2015
|
|
21
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
04/08/2015
|
short out the query by cf offcie
|
|
22
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
13/08/2015
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Civil Soyam,Almora)
|
REPLY
|
CF (North Kumaun)
|
02/09/2015
|
send it back for correction
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Civil Soyam,Almora)
|
02/09/2015
|
send back
|
|
25
|
DFO (Civil Soyam,Almora)
|
REPLY
|
CF (North Kumaun)
|
07/09/2015
|
query short out
|
|
26
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
09/09/2015
|
The On line objections raised by Nodal officer/Reg. Officer on date 24.07.2015 has been clarified by DFO Civil Almora latter no 795/12-1 dated 07-09-2015.
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
09/09/2015
|
this is the reply by user agency consider through CF and DFO
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
16/09/2015
|
this is the reply by user agency consider through CF and DFO
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
09/10/2015
|
kindly refer to the reply of this office EDS dated 21-07-2015, submitted on 16-09-2015. It is observed that-
1. The reply of point 1, 2, 5 and 6 is either not submitted or is incomplete.
2. CB analysis is not submitted as per prescribed format Annexure-vi b and Annexure vi c of the handbook.
3. Although 2.1375 ha forest land proposed for diversion is RF but working plan prescriptions is not given in the relevant para of Part II.
4. Vulnerability of the area to erosion has not been commented upon suitably.
5. 71 trees per ha may not account for 0.5 density. The state govt may remove above shortcomings and submit revised documents/ information/ clarification.
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
12/10/2015
|
Plz reply to obj of RO-kindly refer to the reply of this office EDS dated 21-07-2015, submitted on 16-09-2015. It is observed that- 1. The reply of point 1, 2, 5 and 6 is either not submitted or is incomplete. 2. CB analysis is not submitted as per prescribed format Annexure-vi b and Annexure vi c of the handbook. 3. Although 2.1375 ha forest land proposed for diversion is RF but working plan prescriptions is not given in the relevant para of Part II. 4. Vulnerability of the area to erosion has not been commented upon suitably. 5. 71 trees per ha may not account for 0.5 density. The state govt may remove above shortcomings and submit revised documents/ information/ clarification.
|
|
31
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/10/2015
|
Plz reply to obj of RO-kindly refer to the reply of this office EDS dated 21-07-2015, submitted on 16-09-2015. It is observed that- 1. The reply of point 1, 2, 5 and 6 is either not submitted or is incomplete. 2. CB analysis is not submitted as per prescribed format Annexure-vi b and Annexure vi c of the handbook. 3. Although 2.1375 ha forest land proposed for diversion is RF but working plan prescriptions is not given in the relevant para of Part II. 4. Vulnerability of the area to erosion has not been commented upon suitably. 5. 71 trees per ha may not account for 0.5 density. The state govt may remove above shortcomings and submit revised documents/ information/ clarification.
|
|
32
|
CF (North Kumaun)
|
EDS
|
DFO (Civil Soyam,Almora)
|
15/10/2015
|
As per letter no 1509/12-1 dated 14-10-2015
|
|
33
|
DFO (Civil Soyam,Almora)
|
EDS
|
User Agency (eecdalmorapwd@rediffmail.com)
|
19/10/2015
|
submit the query
|
|
34
|
User Agency (eecdalmorapwd@rediffmail.com)
|
REPLY
|
DFO (Civil Soyam,Almora)
|
30/10/2015
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Civil Soyam,Almora)
|
REPLY
|
CF (North Kumaun)
|
03/11/2015
|
reply of the query
|
|
36
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
07/11/2015
|
As per latter no. 1775/12-1 date 04-11-2015
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
09/11/2015
|
Point wise reply to objections raised by Regional office has been received from user agency through DFO and CF and is being attached herewith for further action.
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
16/11/2015
|
Point wise reply to objections raised by Regional office has been received from user agency through DFO and CF and is being attached herewith for further action.
|
|