TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/Pipeline/42629/2019              (ii). Name of Project for which Forest Land is required : Uttarkhand payjal nigam bageshwar for kapkot village group pumping payjal scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : uttrakhand payjal nigam bageshwar for kapkot village group pumping pay jal scheme              (iv). File no. : 2(46)/21              (v). State : Uttarakhand              (vi). Category of the Project : Pipeline              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.71
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UK/Pipeline/42629/201923/10/2019aa01/11/2019   25/11/2019 Bageshwar :25/11/2019North Kumaun:
  20/01/2020 (Bageshwar)

Uttarakhand:
08/09/2020
Uttarakhand:
22/10/2021
09/12/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttarakhand) on:14/09/2020  
Replied by Circle(North Kumaun) on:03/11/2020  
Query raised by Nodal Officer (Uttarakhand) on:06/11/2020  
Replied by Circle(North Kumaun) on:25/03/2021  
Query raised by Nodal Officer (Uttarakhand) on:30/03/2021  
Replied by Circle(North Kumaun) on:08/07/2021  
Query raised by Nodal Officer (Uttarakhand) on:12/07/2021  
Replied by Circle(North Kumaun) on:05/10/2021  
Query raised by Circle (North Kumaun) on:23/01/2020  
Replied by DFO (Bageshwar) on:19/08/2020  
Query raised by Circle (North Kumaun) on:18/09/2020  
Replied by DFO (Bageshwar) on:02/11/2020  
Query raised by Circle (North Kumaun) on:25/11/2020  
Replied by DFO (Bageshwar) on:20/03/2021  
Query raised by Circle (North Kumaun) on:03/04/2021  
Replied by DFO (Bageshwar) on:05/07/2021  
Query raised by Circle (North Kumaun) on:23/07/2021  
Replied by DFO (Bageshwar) on:24/09/2021  
Query raised by DFO (Bageshwar) on:02/12/2019  
Replied by UA on :09/01/2020  
Query raised by DFO (Bageshwar) on:25/01/2020  
Replied by UA on :14/08/2020  
Query raised by DFO (Bageshwar) on:19/09/2020  
Replied by UA on :22/09/2020  
Query raised by DFO (Bageshwar) on:08/10/2020  
Replied by UA on :26/10/2020  
Query raised by DFO (Bageshwar) on:26/11/2020  
Replied by UA on :08/03/2021  
Query raised by DFO (Bageshwar) on:16/03/2021  
Replied by UA on :18/03/2021  
Query raised by DFO (Bageshwar) on:03/04/2021  
Replied by UA on :18/06/2021  
Query raised by DFO (Bageshwar) on:29/07/2021  
Replied by UA on :13/09/2021  
Query raised by DFO (Bageshwar) on:18/09/2021  
Replied by UA on :24/09/2021  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)
Close(X)
Please wait ...