Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (South Kumaun)
|
25/06/2021
|
CF may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
2
|
CF (South Kumaun)
|
EDS
|
DFO (Nainital)
|
26/06/2021
|
CF may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
3
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
26/06/2021
|
CF may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
4
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
09/08/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
02/09/2021
|
EDS is not uploaded
|
|
6
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
10/11/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
11/11/2021
|
Correct the CA detail option
|
|
8
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
11/11/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Nainital)
|
REPLY
|
CF (South Kumaun)
|
12/11/2021
|
The Letter is attached with proposal
|
|
10
|
CF (South Kumaun)
|
EDS
|
DFO (Nainital)
|
17/11/2021
|
please attached the Letter here with
|
|
11
|
DFO (Nainital)
|
REPLY
|
CF (South Kumaun)
|
17/11/2021
|
letter is attached
|
|
12
|
CF (South Kumaun)
|
REPLY
|
Nodal Officer
|
30/11/2021
|
as per your EDS dated 25-06-2021 The information of road attached here with.
|
|
13
|
Nodal Officer
|
EDS
|
CF (South Kumaun)
|
03/12/2021
|
find the letter attched
|
|
14
|
CF (South Kumaun)
|
EDS
|
DFO (Nainital)
|
15/12/2021
|
find the letter attched
|
|
15
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
20/12/2021
|
Reply EDS
|
|
16
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
09/06/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
13/06/2022
|
Submit the reply of Objection in written
|
|
18
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
14/06/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
14/06/2022
|
Kindly submit the hard copies
|
|
20
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
08/07/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
24/07/2022
|
Plz reply eds
|
|
22
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
30/08/2022
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Nainital)
|
REPLY
|
CF (South Kumaun)
|
13/09/2022
|
Plz find reply
|
|
24
|
CF (South Kumaun)
|
REPLY
|
Nodal Officer
|
22/09/2022
|
as per your on line query dated 03-12-2022 Reply from DFO Nainital the letter is inclosed here with
|
|
25
|
Nodal Officer
|
EDS
|
CF (South Kumaun)
|
03/11/2022
|
find the letter attched
|
|
26
|
CF (South Kumaun)
|
EDS
|
DFO (Nainital)
|
09/11/2022
|
find the letter attched
|
|
27
|
DFO (Nainital)
|
EDS
|
User Agency (mohan.singh@vtlrewa.com)
|
09/11/2022
|
plz reply eds
|
|
28
|
User Agency (mohan.singh@vtlrewa.com)
|
REPLY
|
DFO (Nainital)
|
26/07/2023
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Nainital)
|
REPLY
|
CF (South Kumaun)
|
10/08/2023
|
pzl find eds reply
|
|
30
|
CF (South Kumaun)
|
REPLY
|
Nodal Officer
|
08/09/2023
|
letter enclosed
|
|